Financier | Commitments |
---|---|
Borrower/Recipient | 58.00 |
Global Environment Facility (GEF) | 11.73 |
P085621
Closed
Gabriela Encalada Romero
Chilean Agency for International Cooperation (AGCI)
November 9, 2012
(as of board presentation)
June 7, 2013
September 2, 2005
US$ 63.86 million
National Forestry Corporation (CONAF)
2013
US$ 11.73 million
B
Not Applicable
June 30, 2021
No
BANK APPROVED
March 15, 2022
Financier | Commitments |
---|---|
Borrower/Recipient | 58.00 |
Global Environment Facility (GEF) | 11.73 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 11.73 |
Total Project Cost** | 63.86 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2020-12-04 |
Counterpart Funding | Satisfactory | 2020-12-04 |
Procurement | Satisfactory | 2020-12-04 |
Summary Global Objective Rating | Satisfactory | 2020-12-04 |
Financial Management | Satisfactory | 2020-12-04 |
Monitoring and Evaluation | Satisfactory | 2020-12-04 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2020-12-04 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-16-2021 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Development of an effective national framework to mitigate land degradation, which includes biodiversity mainstreaming and protection of forest carbon assets. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Improved capacity to monitor SLM at the national level. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Land area under sustainable landscape management practices | Value | 0.00 | 50475.00 | 30000.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Increased management and coordination capacity for mainstreaming SLM into the institutional architecture of the Ministry of Agriculture. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | August 15, 2019 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Assessment of and proposed adjustments to existing and future MAG instruments (incentive programs) and regulations that promote ecosystem restoration and protection for use in National SLM framework. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2013 | |
Comment |
Training provided to national, regional and local agencies to promote inter-sectoral coordination on SLM implementation. | Value | 0.00 | 60.00 | 60.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 1845.00 | 1573.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Priority areas identified for SLM Framework. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
University-level course on SLM and biodiversity mainstreaming developed and taught | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Female beneficiaries | Value | 0.00 | 51.00 | 0.00 |
Date | December 9, 2013 | June 8, 2018 | ||
Comment |
National monitoring system for SLM designed and operational. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Eligibility criteria established for activities to be implemented under the SLM Framework. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Strategic Plans for SLM for Pilot Areas | Value | 0.00 | 5.00 | 5.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Mainstreaming Climate Change Issues | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Annual public outreach program. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Early warning system for land degradation designed and operational. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2016 | |
Comment |
Degraded Areas Identified and Categorized in Strategic Pilot Areas. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2020 | June 28, 2017 | |
Comment |
Alignment of existing instruments with SLM Framework. | Value | No | Yes | Yes |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Number of farm level plans developed in Strategic Pilot Areas. | Value | 0.00 | 354.00 | 235.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
New areas outside protected areas managed as biodiversity-friendly (ha) | Value | 0.00 | 22591.00 | 12600.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Amount of tons of CO2e sequestered through project investments over 5 years | Value | 0.00 | 2619920.00 | 1087131.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Area restored or re/afforested | Value | 0.00 | 7584.00 | 570.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Forest area brought under management plans | Value | 0.00 | 7588.00 | 7530.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Forest users trained | Value | 0.00 | 2383.00 | 1000.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Forest users trained - Female | Value | 0.00 | 1117.00 | 250.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |
Forest users trained - Ethnic minority/indigenous people | Value | 0.00 | 614.00 | 300.00 |
Date | December 9, 2013 | June 30, 2021 | June 28, 2017 | |
Comment |