Abstract*

The objective of the Sustainable Land Management Project for Chile is to develop a national framework for sustainable land management to combat land degradation, mainstream biodiversity into national policies, and protect forest carbon assets. The project has 5 components. (1) National sustainable land management (SLM) framework component will: (a) carry out of an assessment of the potential of the member country's existing agriculture, forestry...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project’s Global Environment Objective (GEO) is to develop a national framework for sustainable land management to combat landdegradation, mainstream biodiversity into national policies, and protect forest carbon assets.

Key Details

Project Details

  • P085621

  • Closed

  • Gabriela Encalada Romero

  • Chilean Agency for International Cooperation (AGCI)

  • Chile

  • November 9, 2012

  • (as of board presentation)

    June 7, 2013

  • September 2, 2005

  • US$ 63.86 million

  • National Forestry Corporation (CONAF)

  • Latin America and Caribbean

  • 2013

  • US$ 11.73 million

  • B

  • Not Applicable

  • June 30, 2021

  • No

  • BANK APPROVED

  • March 15, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 58.00
Global Environment Facility (GEF) 11.73

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 11.73
Total Project Cost** 63.86

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2020-12-04
Counterpart Funding Satisfactory 2020-12-04
Procurement Satisfactory 2020-12-04
Summary Global Objective Rating Satisfactory 2020-12-04
Financial Management Satisfactory 2020-12-04
Monitoring and Evaluation Satisfactory 2020-12-04
Overall Implementation Progress (IP) Moderately Satisfactory 2020-12-04

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-16-2021
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Development of an effective national framework to mitigate land degradation, which includes biodiversity mainstreaming and protection of forest carbon assets.ValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Improved capacity to monitor SLM at the national level.ValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Land area under sustainable landscape management practicesValue0.0050475.0030000.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Increased management and coordination capacity for mainstreaming SLM into the institutional architecture of the Ministry of Agriculture.ValueNoYesYes
    DateDecember 9, 2013June 30, 2021August 15, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Assessment of and proposed adjustments to existing and future MAG instruments (incentive programs) and regulations that promote ecosystem restoration and protection for use in National SLM framework.ValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2013
    Comment
  • Training provided to national, regional and local agencies to promote inter-sectoral coordination on SLM implementation.Value0.0060.0060.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Direct project beneficiariesValue0.001845.001573.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Priority areas identified for SLM Framework.ValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • University-level course on SLM and biodiversity mainstreaming developed and taughtValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Female beneficiariesValue0.0051.000.00
    DateDecember 9, 2013June 8, 2018
    Comment
  • National monitoring system for SLM designed and operational.ValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Eligibility criteria established for activities to be implemented under the SLM Framework.ValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Strategic Plans for SLM for Pilot AreasValue0.005.005.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Mainstreaming Climate Change IssuesValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Annual public outreach program.ValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Early warning system for land degradation designed and operational.ValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2016
    Comment
  • Degraded Areas Identified and Categorized in Strategic Pilot Areas.ValueNoYesYes
    DateDecember 9, 2013June 30, 2020June 28, 2017
    Comment
  • Alignment of existing instruments with SLM Framework.ValueNoYesYes
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Number of farm level plans developed in Strategic Pilot Areas.Value0.00354.00235.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • New areas outside protected areas managed as biodiversity-friendly (ha)Value0.0022591.0012600.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Amount of tons of CO2e sequestered through project investments over 5 yearsValue0.002619920.001087131.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Area restored or re/afforestedValue0.007584.00570.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Forest area brought under management plansValue0.007588.007530.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Forest users trainedValue0.002383.001000.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Forest users trained - FemaleValue0.001117.00250.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment
  • Forest users trained - Ethnic minority/indigenous peopleValue0.00614.00300.00
    DateDecember 9, 2013June 30, 2021June 28, 2017
    Comment