DRC Education Sector Project

Abstract*

The objective of the Education Sector Project of the Democratic Republic of Congo is to prevent further deterioration in the delivery of essential services for primary education and prepare ground for a sustainable development and financing of the sector that will facilitate donor coordination and future transition to a sector wide program. There are 4 components to the Project. Component 1 will increase access and equity at primary level by providing...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To prevent further deterioration in the delivery of essential services for primary education and prepare ground for a sustainable development and financing of the sector that will facilitate donor coordination and future transition to a sector wide program.

Key Details

Project Details

  • P086294

  • Closed

  • Dung-Kim Pham

  • N/A

  • Congo, Democratic Republic of

  • January 20, 2006

  • (as of board presentation)

    June 5, 2007

  • January 11, 2008

  • US$ 150.00 million

  • Unite de Gestion et Coordination du Projet

  • Eastern and Southern Africa

  • 2007

  • US$ 150.00 million

  • B

  • N/A

  • October 31, 2014

  • BANK APPROVED

  • August 5, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 150.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 150.00
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 150.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2013 IDA-H3030 Loan Disb 2,118,885.50
Jun 5, 2007 IDA-H3030 Loan Commitment 150,000,000.00
Oct 2, 2013 IDA-H3030 Loan Disb 827,900.00
Oct 9, 2013 IDA-H3030 Loan Disb 1,681,094.60
Dec 19, 2013 IDA-H3030 Loan Disb 2,479,866.00
Dec 19, 2013 IDA-H3030 Loan Disb 1,241,522.40
Feb 3, 2014 IDA-H3030 Loan Disb 1,236,975.00
Jan 31, 2014 IDA-H3030 Loan Disb 5,945,111.00
Sep 11, 2013 IDA-H3030 Loan Disb 827,918.75
Oct 25, 2013 IDA-H3030 Loan Disb 2,369,080.20
Oct 2, 2013 IDA-H3030 Loan Disb 2,498,962.00
Oct 17, 2013 IDA-H3030 Loan Disb 573,863.94
Jun 19, 2013 IDA-H3030 Loan Disb -10,273.59
Aug 20, 2013 IDA-H3030 Loan Disb 2,511,586.00
Aug 26, 2013 IDA-H3030 Loan Disb 2,508,332.00
Mar 19, 2015 IDA-H3030 Loan Cancel 140,741.60
Mar 19, 2015 IDA-H3030 Loan Disb -11,833.83
Feb 13, 2015 IDA-H3030 Loan Disb -47,276.50
Sep 23, 2014 IDA-H3030 Loan Disb 401,278.72
Sep 5, 2014 IDA-H3030 Loan Disb 6,000,000.00
Sep 5, 2014 IDA-H3030 Loan Disb 440,062.28
Sep 3, 2014 IDA-H3030 Loan Disb -24,240.75
Mar 2, 2015 IDA-H3030 Loan Disb -131,585.66
Mar 4, 2015 IDA-H3030 Loan Disb 1,352,344.90
Jun 16, 2014 IDA-H3030 Loan Disb 5,951,543.50
Jul 3, 2014 IDA-H3030 Loan Disb 2,661,073.00
Jul 3, 2014 IDA-H3030 Loan Disb 117,975.69
Jul 15, 2014 IDA-H3030 Loan Disb 367,583.50
May 12, 2014 IDA-H3030 Loan Disb 1,181,943.10
Mar 27, 2014 IDA-H3030 Loan Disb 1,640,041.10
Feb 21, 2014 IDA-H3030 Loan Disb 2,461,486.50
Mar 11, 2014 IDA-H3030 Loan Disb 1,026,768.00
Sep 23, 2013 IDA-H3030 Loan Disb 3,541,060.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2014-12-10
Monitoring and Evaluation Moderately Satisfactory 2014-12-10
Counterpart Funding Satisfactory 2014-12-10
Overall Implementation Progress (IP) Moderately Satisfactory 2014-12-10
Project Management Moderately Satisfactory 2014-12-10
Procurement Satisfactory 2014-12-10
Financial Management Satisfactory 2014-12-10

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-06-2015
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-23-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Education sector strategy (including medium term financing plan) with indicators agreed with donors and approved by Government.ValueConsensus on priority for primary education (obligSector Strategy developed and approved by GovernmeSector Strategy developed and approved by Governme
    DateJanuary 11, 2008October 6, 2014October 31, 2014
    CommentTarget Met
  • Direct project beneficiariesValue0.004878140.004878140.00
    DateOctober 17, 2007February 28, 2014October 31, 2014
    CommentTarget has been rectified (see comment under Actual reported on 03/02/2012
  • Gross 1st grade intake rateValue107.70133.10129.80
    DateJuly 11, 2011February 28, 2014October 31, 2014
    Commentfor 20102012/13 school year datasame
  • Primary Completion RateValue29.0064.0072.00
    DateMay 4, 2007October 6, 2014October 31, 2014
    CommentTarget not met
  • Girls to boys ratio in primary schoolsValue85.0090.0097.00
    DateMay 4, 2007October 6, 2014October 31, 2014
    CommentUnduly optimistic target not met97% is target given by Government
  • Female beneficiariesValue0.0050.0050.00
    DateOctober 17, 2007February 28, 2014October 31, 2014
    Comment
  • teachers beneficiaries from teaching guidesValue0.00125208.00125000.00
    DateOctober 17, 2007February 28, 2014October 31, 2014
    Comment
  • Growth in the gross enrolment ratio (GER).Value64%101.3105.8
    DateJanuary 11, 2008October 6, 2014October 31, 2014
    CommentTarget Largely Met

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • System for learning assessment at the primary levelValueNoYesYes
    DateJanuary 11, 2008October 6, 2014October 31, 2014
    CommentIndicator discussed with TTL on 07/15/2009.Target Met
  • Loi cadre (organic law) is transmitted to Parliament for adoptionValueNoYesYes
    DateFebruary 1, 2008October 6, 2014October 31, 2014
    CommentTarget Met
  • Convention of partnerships revised and implementedValueNoYesYes
    DateFebruary 1, 2008October 6, 2014October 31, 2014
    CommentTarget Met
  • Parents finding the school fee in primary education has been reducedValuenoNot availableYes
    DateJuly 11, 2011October 6, 2014October 31, 2014
    CommentBeneficiary Survey not carried out
  • Primary teachers in "registered" schools integrated into the public payrollValue0.00100.0083.00
    DateJuly 11, 2011October 6, 2014October 31, 2014
    Commentunder the project, the target of 20,155 teachers as agreed at project restructuring in 2011 has been reached.
  • Student:textbook ratioValue01:21:2
    DateMay 4, 2007October 6, 2014October 31, 2014
    CommentMost schools in public sector have no textooksTarget met: each student has a math and French textbook)each student to have one French and one math textbook.
  • A textbook policy adopted by the GovernmentValueNono changeyes
    DateJuly 11, 2011October 6, 2014October 31, 2014
    CommentThere is a preliminary draft that is under discussion among the various technical directions of the ministry. This action is nowassumed under the new project PROSEB
  • Teacher guide ratioValue01:21:2
    DateMay 4, 2007October 6, 2014October 31, 2014
    CommentMost schools in public sector have no teacher guideTarget Met: each teacher has a guide in Mathematics and in Frenchrevised to show that each teacher has 2 guides (one in mathematics and one in French)
  • Inspectors and school advisors receiving in-service training in the use of textbooksValue25.00100.00100.00
    DateJuly 11, 2011October 6, 2014October 31, 2014
    Commentvalue is for 2008Target Met: 100% of inspectors and advisers trained
  • Basic education interim development plan is implemented according to agreed planValuenoyesyes
    DateJuly 11, 2011October 6, 2014October 31, 2014
    CommentTarget Met
  • Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions.Value0.001467.001572.00
    DateJuly 11, 2011October 6, 2014October 31, 2014
    Comment93.3% realized.
  • New school construction norms are adopted for application of cost-effective school construction strategyValueNoYes: Norms AdoptedYes
    DateJuly 11, 2011October 6, 2014October 31, 2014
    CommentTarget Met
  • Reformed guidelines for pre-service teacher training are developed and are appliedValuenoyesyes
    DateJuly 11, 2011October 6, 2014October 31, 2014
    CommentTarget Met
  • A draft teacher careeer structure (training, deployment, salary and incentives) approved by the GovernmentValuenoYesyes
    DateJuly 11, 2011October 6, 2014October 31, 2014
    CommentTarget Met
  • CRC and PETS have been piloted in selected educational provincesValuenoPETS carried out; CRC still under developmentyes
    DateJuly 11, 2011October 6, 2014October 31, 2014
    Comment
  • Based on lessons learnt from CRC and PETS, an action plan is put in place for an eventual scale upValuenoNoyes
    DateJuly 11, 2011October 6, 2014October 31, 2014
    Commentsee indicator 16
  • Utility of the learning assessment systemValue0.003.004.00
    DateJanuary 11, 2008October 6, 2014October 31, 2014
    CommentIndicator discussed with TTL on 07/15/2009.A partnership agreement was signed between MEPS and PASEC and led to the increase of the school sample of the learning evaluationsurvey. Preliminary results are expected by end December 2010
  • NEW - Classrooms built and/or rehabilitated (number)Value0450
    DateJanuary 11, 2008February 28, 2014December 31, 2013
    CommentMonitoring of this indicator is done through the core indicator.
  • NEW - Education facilities built and/or rehabilitated (units)Value0100
    DateJanuary 11, 2008February 28, 2014December 31, 2012
    CommentIndicator is monitored through the core indicator on classroooms
  • NEW - Textbooks purchased (number)Value018 million14 million
    DateJanuary 11, 2008October 6, 2014October 31, 2014
    CommentTarget Far Surpassed: A major Project success