Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 102.90 |
Borrower/Recipient | 240.11 |
P086592
Active
Bakyt Arystanov
The Republic of Kazakhstan
December 19, 2005
(as of board presentation)
June 27, 2013
January 29, 2015
US$ 343.01 million
Committee of Water Resources,Ministry of Water Resources and Irrigation
2013
US$ 102.90 million
B
November 30, 2023
June 30, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 102.90 |
Borrower/Recipient | 240.11 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 102.90 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 102.90 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 343.01 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2016 | IBRD-82770 | Int Charges | 5,816.20 |
Nov 4, 2016 | IBRD-82770 | Loan Disb | 35,057.00 |
Jun 15, 2020 | IBRD-82770 | Int Charges | 6,528.63 |
Jun 15, 2020 | IBRD-82770 | Int Charges | 223,574.23 |
Oct 28, 2020 | IBRD-82770 | Loan Disb | 315,000.00 |
Nov 12, 2020 | IBRD-82770 | Loan Disb | 2,330,220.00 |
Aug 17, 2020 | IBRD-82770 | Loan Disb | 770,000.00 |
Jul 16, 2020 | IBRD-82770 | Loan Disb | 1,070,000.00 |
Oct 15, 2020 | IBRD-82770 | Loan Disb | 2,306,300.00 |
Dec 15, 2019 | IBRD-82770 | Int Charges | 108.27 |
Dec 15, 2019 | IBRD-82770 | Int Charges | 163,944.25 |
Jun 24, 2020 | IBRD-82770 | Loan Disb | 305,000.00 |
Jun 8, 2020 | IBRD-82770 | Loan Disb | 1,441,000.00 |
May 21, 2020 | IBRD-82770 | Loan Disb | 1,125,400.00 |
Sep 8, 2020 | IBRD-82770 | Loan Disb | 833,000.00 |
Mar 16, 2020 | IBRD-82770 | Loan Disb | 729,220.00 |
Dec 13, 2019 | IBRD-82770 | Loan Disb | 2,430,000.00 |
Nov 15, 2019 | IBRD-82770 | Loan Disb | 2,521,000.00 |
Aug 22, 2022 | IBRD-82770 | Loan Disb | 952,450.00 |
May 13, 2022 | IBRD-82770 | Loan Disb | 1,071,613.00 |
Apr 7, 2022 | IBRD-82770 | Loan Disb | 1,138,900.00 |
Sep 16, 2021 | IBRD-82770 | Loan Disb | -130,000.00 |
Jun 15, 2022 | IBRD-82770 | Int Charges | 3,276.10 |
Jun 15, 2022 | IBRD-82770 | Int Charges | 210,616.56 |
Jun 15, 2022 | IBRD-82770 | Loan Repay | 2,454,690.50 |
Aug 4, 2021 | IBRD-82770 | Loan Disb | 777,000.00 |
Nov 10, 2021 | IBRD-82770 | Loan Disb | 1,157,400.00 |
Jun 3, 2022 | IBRD-82770 | Loan Disb | 1,085,000.00 |
Apr 8, 2021 | IBRD-82770 | Loan Disb | 1,186,000.00 |
Jul 13, 2021 | IBRD-82770 | Loan Disb | 550,000.00 |
Jul 8, 2016 | IBRD-82770 | Loan Disb | 3,920.00 |
Dec 27, 2016 | IBRD-82770 | Loan Disb | 7,113.00 |
Dec 29, 2015 | IBRD-82770 | Loan Disb | 775,674.30 |
Dec 28, 2015 | IBRD-82770 | Loan Disb | 26,000.00 |
Feb 17, 2015 | IBRD-82770 | Fee Charges | 257,256.10 |
Jun 15, 2018 | IBRD-82770 | Int Charges | 189.91 |
Jun 15, 2018 | IBRD-82770 | Int Charges | 29,043.30 |
Sep 4, 2018 | IBRD-82770 | Loan Disb | 172,882.00 |
May 14, 2018 | IBRD-82770 | Loan Disb | 16,252.00 |
Dec 11, 2017 | IBRD-82770 | Loan Disb | 371,796.94 |
Feb 26, 2018 | IBRD-82770 | Loan Disb | 15,494.00 |
Dec 5, 2017 | IBRD-82770 | Loan Disb | 347,041.00 |
Aug 3, 2017 | IBRD-82770 | Loan Disb | 25,274.00 |
May 18, 2017 | IBRD-82770 | Loan Disb | 19,290.00 |
Apr 11, 2017 | IBRD-82770 | Loan Disb | 17,300.00 |
Jun 15, 2017 | IBRD-82770 | Int Charges | 56.29 |
Jun 15, 2017 | IBRD-82770 | Int Charges | 15,128.70 |
Aug 3, 2016 | IBRD-82770 | Loan Disb | 3,780.00 |
Dec 22, 2016 | IBRD-82770 | Loan Disb | 824,154.00 |
Jun 15, 2016 | IBRD-82770 | Int Charges | 4,516.97 |
May 21, 2021 | IBRD-82770 | Loan Disb | 710,195.00 |
Jun 15, 2021 | IBRD-82770 | Int Charges | 6,964.05 |
Jun 15, 2021 | IBRD-82770 | Int Charges | 143,724.90 |
Oct 18, 2021 | IBRD-82770 | Loan Disb | 1,908,545.00 |
Jun 10, 2021 | IBRD-82770 | Loan Disb | 506,860.00 |
Sep 7, 2021 | IBRD-82770 | Loan Disb | 1,575,000.00 |
Mar 22, 2021 | IBRD-82770 | Loan Disb | 1,010,000.00 |
Feb 10, 2021 | IBRD-82770 | Loan Disb | 1,035,100.00 |
Dec 28, 2020 | IBRD-82770 | Loan Disb | 172,000.00 |
Dec 14, 2020 | IBRD-82770 | Loan Disb | 2,117,450.00 |
Jun 29, 2021 | IBRD-82770 | Loan Disb | 56,300.00 |
Jun 29, 2021 | IBRD-82770 | Loan Disb | 767,635.00 |
Jan 27, 2021 | IBRD-82770 | Loan Disb | 627,220.00 |
Nov 20, 2020 | IBRD-82770 | Loan Disb | 536,195.00 |
Dec 29, 2020 | IBRD-82770 | Loan Disb | -148,000.00 |
Dec 15, 2020 | IBRD-82770 | Int Charges | 2,633.07 |
Dec 15, 2020 | IBRD-82770 | Int Charges | 117,391.27 |
Jun 15, 2024 | IBRD-82770 | Int Charges | 11,628.35 |
Jun 15, 2024 | IBRD-82770 | Int Charges | 1,812,346.10 |
Jun 15, 2024 | IBRD-82770 | Loan Repay | 3,717,050.20 |
Aug 22, 2023 | IBRD-82770 | Loan Disb | 1,737,560.00 |
May 22, 2023 | IBRD-82770 | Loan Disb | 685,000.00 |
Dec 15, 2023 | IBRD-82770 | Int Charges | 43,438.20 |
Dec 15, 2023 | IBRD-82770 | Int Charges | 1,796,372.40 |
Dec 15, 2023 | IBRD-82770 | Loan Repay | 3,717,050.20 |
Jul 26, 2023 | IBRD-82770 | Loan Disb | 627,000.00 |
Jun 21, 2023 | IBRD-82770 | Loan Disb | 1,204,710.00 |
Jun 15, 2023 | IBRD-82770 | Int Charges | 87,338.31 |
Jun 15, 2023 | IBRD-82770 | Loan Repay | 3,379,258.50 |
Jun 15, 2023 | IBRD-82770 | Int Charges | 1,499,596.50 |
Dec 15, 2022 | IBRD-82770 | Loan Disb | 2,100,000.00 |
Mar 3, 2023 | IBRD-82770 | Loan Disb | 1,931,000.00 |
Jan 31, 2023 | IBRD-82770 | Loan Disb | 790,005.00 |
Apr 18, 2023 | IBRD-82770 | Loan Disb | 1,150,400.00 |
Feb 23, 2023 | IBRD-82770 | Loan Disb | 488,775.00 |
Dec 15, 2022 | IBRD-82770 | Int Charges | 1,249.89 |
Dec 15, 2022 | IBRD-82770 | Int Charges | 897,294.25 |
Dec 15, 2022 | IBRD-82770 | Loan Repay | 2,835,233.00 |
Dec 15, 2021 | IBRD-82770 | Int Charges | 479.05 |
Dec 15, 2021 | IBRD-82770 | Int Charges | 154,623.40 |
Dec 15, 2021 | IBRD-82770 | Loan Repay | 2,000,672.00 |
Jan 21, 2022 | IBRD-82770 | Loan Disb | 535,177.00 |
Feb 11, 2022 | IBRD-82770 | Loan Disb | 1,161,532.00 |
Jun 27, 2013 | IBRD-82770 | Loan Commitment | 102,902,440.00 |
May 13, 2016 | IBRD-82770 | Loan Disb | 3,600.00 |
Dec 15, 2016 | IBRD-82770 | Int Charges | 3.96 |
Dec 31, 2019 | IBRD-82770 | Loan Disb | 770,418.94 |
Jun 15, 2019 | IBRD-82770 | Int Charges | 1,675.80 |
Jun 15, 2019 | IBRD-82770 | Int Charges | 122,263.78 |
Jun 13, 2019 | IBRD-82770 | Loan Disb | 558,400.00 |
Jun 20, 2019 | IBRD-82770 | Loan Disb | 1,230,000.00 |
Jul 24, 2019 | IBRD-82770 | Loan Disb | 3,000,000.00 |
Oct 10, 2018 | IBRD-82770 | Loan Disb | 335,000.00 |
Aug 17, 2018 | IBRD-82770 | Loan Disb | 19,400.00 |
Dec 13, 2018 | IBRD-82770 | Loan Disb | 3,065,497.00 |
Nov 29, 2018 | IBRD-82770 | Loan Disb | 845,000.00 |
Dec 15, 2018 | IBRD-82770 | Int Charges | 33.51 |
Dec 15, 2018 | IBRD-82770 | Int Charges | 42,473.57 |
Dec 15, 2017 | IBRD-82770 | Int Charges | 27.14 |
Dec 15, 2017 | IBRD-82770 | Int Charges | 17,368.51 |
Sep 8, 2022 | IBRD-82770 | Loan Disb | 1,948,145.00 |
Oct 17, 2022 | IBRD-82770 | Loan Disb | 2,131,095.00 |
Nov 23, 2022 | IBRD-82770 | Loan Disb | 1,811,257.00 |
Jul 12, 2022 | IBRD-82770 | Loan Disb | 1,135,500.00 |
Jul 21, 2022 | IBRD-82770 | Loan Disb | 651,585.00 |
Mar 7, 2022 | IBRD-82770 | Loan Disb | 1,453,910.00 |
Dec 16, 2021 | IBRD-82770 | Loan Disb | 1,276,065.00 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2024-12-17 |
Financial Management | Moderately Satisfactory | 2024-12-17 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-17 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-12-17 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2024-12-17 |
Procurement | Moderately Satisfactory | 2024-12-17 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Water users provided with new/improved irrigation and drainage services (number) | Value | 0.00 | 20000.00 | 120000.00 |
Date | December 31, 2014 | December 30, 2022 | June 30, 2025 | |
Comment |
Water users provided with irrigation and drainage services - female (number) | Value | 0.00 | 6700.00 | 60000.00 |
Date | December 31, 2014 | December 30, 2022 | June 30, 2025 | |
Comment |
Area provided with irrigation and drainage services (ha) | Value | 0.00 | 76000.00 | 100000.00 |
Date | December 31, 2014 | November 27, 2023 | June 30, 2025 | |
Comment |
Area provided with irrigation and drainage services - Improved (ha) | Value | 0.00 | 76000.00 | 100000.00 |
Date | December 31, 2014 | September 30, 2023 | June 30, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Agricultural cooperatives strengthened | Value | 0.00 | 2.00 | 2.00 |
Date | December 31, 2014 | December 30, 2022 | June 30, 2025 | |
Comment |
Client days of training provided | Value | 0.00 | 17800.00 | 20000.00 |
Date | December 31, 2014 | September 30, 2023 | June 30, 2025 | |
Comment |
Number of Subprojects where detailed designs and EAs/EMPs are prepared (Component 1, supported by Components 2 and 3) | Value | 0.00 | 11.00 | 10.00 |
Date | January 29, 2015 | December 30, 2022 | June 30, 2025 | |
Comment |
Number of sub-projects with automated canal flow and groundwater table monitoring and control technology is developed to help modernize sub-project performance (Components 2). | Value | 0.00 | 2.00 | 10.00 |
Date | January 29, 2015 | December 30, 2022 | June 30, 2025 | |
Comment |
Users satisfied by quality of irrigation services provided | Value | 0.00 | 92.10 | 90.00 |
Date | December 31, 2014 | December 30, 2022 | June 30, 2025 | |
Comment |
Length of the lined canals (Component 1) | Value | 0.00 | 698.00 | 800.00 |
Date | December 31, 2014 | September 30, 2023 | June 30, 2025 | |
Comment |
Client days of training provided - Female | Value | 0.00 | 2396.00 | 3000.00 |
Date | January 29, 2015 | September 30, 2023 | June 30, 2025 | |
Comment |
Secondary canal system Management, Operation and Maintenance plans developed and operationalized | Value | 0.00 | 20000.00 | 80000.00 |
Date | December 31, 2014 | September 30, 2023 | June 30, 2025 | |
Comment |
Preparation of Monitoring and Evaluation reports | Value | 0.00 | 2.00 | 2.00 |
Date | February 28, 2019 | December 30, 2022 | June 30, 2025 | |
Comment |
Grievance Redress Mechanism established and operationalized | Value | No | Yes | Yes |
Date | December 31, 2014 | December 30, 2022 | June 30, 2025 | |
Comment |