Financier | Commitments |
---|---|
Foreign Multilateral Institutions (unidentified) | 145.00 |
International Bank for Reconstruction and Development | 184.00 |
EC: European Commission | 130.00 |
Borrower/Recipient | 30.00 |
P086768
Closed
Berina Uwimbabazi
Republic of Poland
July 6, 2004
(as of board presentation)
March 21, 2007
July 9, 2007
US$ 489.00 million
Ministry of Environment
2007
US$ 459.00 million
A
October 12, 2023
June 30, 2020
BANK APPROVED
Financier | Commitments |
---|---|
Foreign Multilateral Institutions (unidentified) | 145.00 |
International Bank for Reconstruction and Development | 184.00 |
EC: European Commission | 130.00 |
Borrower/Recipient | 30.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 184.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 184.00 |
Lending Instrument | |
---|---|
Grant Amount | 275.00 |
Total Project Cost** | 489.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 27, 2020 | IBRD-74360 | Loan Disb | -978,960.25 |
Nov 30, 2020 | IBRD-74360 | Loan Cancel | 9,786,529.00 |
Nov 15, 2021 | IBRD-74360 | Loan Repay | 10,837,179.00 |
Nov 15, 2015 | IBRD-74360 | Int Charges | 1,449.22 |
Nov 15, 2015 | IBRD-74360 | Int Charges | 1,019.24 |
Nov 15, 2015 | IBRD-74360 | Int Charges | 46,387.19 |
Nov 15, 2015 | IBRD-74360 | Int Charges | 152,190.12 |
Nov 15, 2015 | IBRD-74360 | Loan Repay | 7,157,021.50 |
Apr 22, 2015 | IBRD-74360 | Loan Disb | 9,181,381.00 |
May 15, 2015 | IBRD-74360 | Int Charges | 66,458.96 |
May 15, 2015 | IBRD-74360 | Int Charges | 187,242.23 |
May 15, 2015 | IBRD-74360 | Loan Repay | 6,790,323.00 |
Nov 15, 2016 | IBRD-74360 | Int Charges | 38,469.98 |
Nov 15, 2016 | IBRD-74360 | Int Charges | 47,608.12 |
Nov 15, 2016 | IBRD-74360 | Loan Repay | 8,645,580.00 |
May 15, 2016 | IBRD-74360 | Int Charges | 48,149.66 |
May 15, 2016 | IBRD-74360 | Int Charges | 114,154.75 |
May 15, 2016 | IBRD-74360 | Loan Repay | 7,525,834.00 |
Sep 8, 2016 | IBRD-74360 | Loan Disb | 17,360,360.00 |
Nov 15, 2017 | IBRD-74360 | Int Charges | 27,979.56 |
Nov 15, 2017 | IBRD-74360 | Loan Repay | 9,514,113.00 |
May 15, 2017 | IBRD-74360 | Int Charges | 25,466.65 |
May 15, 2017 | IBRD-74360 | Int Charges | 26,578.52 |
May 15, 2017 | IBRD-74360 | Loan Repay | 8,809,408.00 |
May 15, 2018 | IBRD-74360 | Loan Repay | 10,450,084.00 |
May 15, 2018 | IBRD-74360 | Int Charges | 22,005.20 |
Jan 17, 2018 | IBRD-74360 | Loan Disb | 7,202,425.00 |
Nov 15, 2019 | IBRD-74360 | Loan Repay | 10,889,312.00 |
Nov 15, 2019 | IBRD-74360 | Int Charges | 10,733.44 |
May 15, 2019 | IBRD-74360 | Loan Repay | 9,817,011.00 |
May 15, 2019 | IBRD-74360 | Int Charges | 17,821.75 |
May 28, 2019 | IBRD-74360 | Loan Disb | 6,164,537.50 |
Nov 15, 2018 | IBRD-74360 | Int Charges | 18,307.29 |
Nov 15, 2018 | IBRD-74360 | Loan Repay | 9,920,039.00 |
May 15, 2020 | IBRD-74360 | Int Charges | 9,857.66 |
May 15, 2020 | IBRD-74360 | Loan Repay | 10,669,207.00 |
May 15, 2021 | IBRD-74360 | Int Charges | 930.25 |
May 15, 2021 | IBRD-74360 | Loan Repay | 11,452,873.00 |
Nov 30, 2020 | IBRD-74360 | Loan Disb | -14,374.11 |
Nov 15, 2020 | IBRD-74360 | Int Charges | 10,888.10 |
Nov 15, 2020 | IBRD-74360 | Int Charges | 26,838.17 |
Nov 15, 2020 | IBRD-74360 | Loan Repay | 11,664,617.00 |
Mar 21, 2007 | IBRD-74360 | Loan Commitment | 184,000,000.00 |
Nov 15, 2014 | IBRD-74360 | Loan Repay | 5,040,253.00 |
Sep 29, 2014 | IBRD-74360 | Loan Disb | 8,879,850.00 |
Nov 15, 2013 | IBRD-74360 | Int Charges | 2,487.02 |
Nov 15, 2013 | IBRD-74360 | Int Charges | 2,858.77 |
Nov 15, 2013 | IBRD-74360 | Int Charges | 154,355.98 |
Nov 15, 2013 | IBRD-74360 | Int Charges | 137,375.06 |
Nov 15, 2013 | IBRD-74360 | Loan Repay | 3,541,777.20 |
Sep 23, 2013 | IBRD-74360 | Loan Disb | 12,319,089.00 |
Nov 15, 2014 | IBRD-74360 | Int Charges | 1,235.02 |
Nov 15, 2014 | IBRD-74360 | Int Charges | 1,419.65 |
Nov 15, 2014 | IBRD-74360 | Int Charges | 107,725.27 |
Nov 15, 2014 | IBRD-74360 | Int Charges | 251,535.89 |
May 15, 2015 | IBRD-74360 | Int Charges | 2,559.78 |
May 15, 2015 | IBRD-74360 | Int Charges | 4,291.89 |
Jan 5, 2015 | IBRD-74360 | Loan Disb | 23,810,000.00 |
Jun 9, 2014 | IBRD-74360 | Loan Disb | 8,318,392.00 |
May 15, 2014 | IBRD-74360 | Int Charges | 4,095.45 |
May 15, 2014 | IBRD-74360 | Int Charges | 138,044.22 |
May 15, 2014 | IBRD-74360 | Int Charges | 186,537.60 |
Apr 23, 2014 | IBRD-74360 | Loan Disb | 9,117,454.00 |
May 15, 2014 | IBRD-74360 | Loan Repay | 4,374,995.50 |
May 15, 2014 | IBRD-74360 | Int Charges | 4,519.81 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2020-06-23 |
Counterpart Funding | Satisfactory | 2020-06-23 |
Monitoring and Evaluation | Satisfactory | 2020-06-23 |
Overall Implementation Progress (IP) | Satisfactory | 2020-06-23 |
Overall Safeguards Rating | Moderately Satisfactory | 2020-06-23 |
Overall Safeguards Rating | Moderately Satisfactory | 2020-06-23 |
Procurement | Satisfactory | 2020-06-23 |
Project Management | Moderately Satisfactory | 2020-06-23 |
Financial Management | Satisfactory | 2020-06-23 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-28-2021 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-10-2021 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduction in area flooded, damages avoided and lives saved due to floods of various magnitudes and return periods | Value | The hectares that wereaffected during the 1997fl | Measured as construction progress until project is | Full protection against floods of the 1997 magnitu |
Date | July 5, 2007 | June 12, 2020 | June 30, 2020 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component A. Reduction in area flooded, damages avoided and lives saved in cities and settlements between Raciborz and Wroclaw city | Value | Area flooded during 1997.The hectares that were a | Measured as construction progress until project is | Full protection against floods of the 1997 magnitu |
Date | July 5, 2007 | June 12, 2020 | June 30, 2020 | |
Comment |
Component B: Full protection to Wroclaw city against flooding. | Value | Area flooded during 1997 floods.The hectares that | Measured as construction progress until project fu | Full protection against floods of the 1997 magnitu |
Date | July 5, 2007 | June 12, 2020 | June 30, 2020 | |
Comment |
Component C: Improved flood forecasting and better linkage of forecaster and communication with flood management | Value | Status of forecast and communication during 1997 f | These activities are successfully completed and in | Established institutional and communication setup |
Date | July 20, 1997 | June 12, 2020 | June 30, 2020 | |
Comment |
Component D: Implementation of RAP design of infrastructure and constructions completion on time. | Value | Not yet due | All RAPs prepared and RAP influenced designs (new | Complete constructions of all project facilities. |
Date | July 20, 1997 | June 12, 2020 | June 30, 2020 | |
Comment |
Construction completion and expenditures | Value | 0% | 43% | |
Date | July 5, 2007 | August 17, 2011 | ||
Comment |
Construction completion and expenditures | Value | 0% | All B1 and B2 contracts are completed (constructio | |
Date | July 5, 2007 | August 17, 2011 | ||
Comment |