Financier | Commitments |
---|---|
Borrower/Recipient | 8.90 |
IDA GRANT FOR POST-CONFLICT | 12.50 |
NETHERLANDS: Min. of Foreign Affairs / Min. of Dev. Coop. | 0.30 |
ITALY: Dev. Coop. Department (MOFA) | 19.90 |
OPEC FUND | 8.40 |
African Development Bank | 3.80 |
P086801
Closed
Syed Waqar Haider
N/A
April 20, 2005
(as of board presentation)
June 16, 2005
December 19, 2006
US$ 53.80 million
N/A
2005
US$ 44.90 million
A
Not Applicable
June 30, 2013
BANK APPROVED
November 1, 2023
Financier | Commitments |
---|---|
Borrower/Recipient | 8.90 |
IDA GRANT FOR POST-CONFLICT | 12.50 |
NETHERLANDS: Min. of Foreign Affairs / Min. of Dev. Coop. | 0.30 |
ITALY: Dev. Coop. Department (MOFA) | 19.90 |
OPEC FUND | 8.40 |
African Development Bank | 3.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 12.50 |
IBRD + IDA Commitment | 12.50 |
Lending Instrument | |
---|---|
Grant Amount | 32.40 |
Total Project Cost** | 53.80 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 16, 2005 | IDA-H1700 | Loan Commitment | 12,500,000.00 |
Nov 14, 2013 | IDA-H1700 | Loan Disb | -1.94 |
Aug 15, 2013 | IDA-H6250 | Loan Disb | 403,649.84 |
Nov 7, 2013 | IDA-H6250 | Loan Disb | 1,118.61 |
Nov 7, 2013 | IDA-H6250 | Loan Disb | 47,237.76 |
Nov 7, 2013 | IDA-H6250 | Loan Disb | 1,264.77 |
Nov 7, 2013 | IDA-H6250 | Loan Disb | 26,272.14 |
Nov 13, 2013 | IDA-H6250 | Loan Disb | 2,057.33 |
Nov 8, 2013 | IDA-H6250 | Loan Disb | 18,366.33 |
Nov 7, 2013 | IDA-H6250 | Loan Disb | 47,237.76 |
Aug 6, 2013 | IDA-H6250 | Loan Disb | 148,346.52 |
Nov 5, 2013 | IDA-H6250 | Loan Disb | 11,100.00 |
Nov 13, 2013 | IDA-H6250 | Loan Disb | 10,346.56 |
Nov 8, 2013 | IDA-H6250 | Loan Disb | 2,542.88 |
Nov 8, 2013 | IDA-H6250 | Loan Disb | 7,628.62 |
Nov 8, 2013 | IDA-H6250 | Loan Disb | 801.63 |
Nov 8, 2013 | IDA-H6250 | Loan Disb | 16,063.56 |
Nov 21, 2013 | IDA-H1700 | Loan Cancel | 7,636.83 |
Nov 14, 2013 | IDA-H6250 | Loan Cancel | 2,115,007.50 |
Nov 14, 2013 | IDA-H6250 | Loan Disb | -552.19 |
Sep 28, 2010 | IDA-H6250 | Loan Commitment | 9,500,000.00 |
Name | Review | Date |
---|---|---|
Overall | Moderately Ineffective | 2014-04-17 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2014-04-17 |
Procurement | Moderately Satisfactory | 2014-04-17 |
Project Management | Moderately Unsatisfactory | 2014-04-17 |
Counterpart Funding | Moderately Unsatisfactory | 2014-04-17 |
Financial Management | Moderately Satisfactory | 2014-04-17 |
Overall Safeguards Rating | Moderately Unsatisfactory | 2014-04-17 |
Monitoring and Evaluation | Moderately Satisfactory | 2014-04-17 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2014-04-17 |
Overall Safeguards Rating | Moderately Unsatisfactory | 2014-04-17 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 07-29-2014 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | High |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Moderately Unsatisfactory |
Government Performance | Unsatisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 12-02-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | Unsatisfactory | N/a |
Government Performance | Unsatisfactory | N/a |
Implementing Agency | Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Project Affected Persons (PAPs) claims related to the transmission line addressed | Value | 0.00 | 100.00 | 100.00 |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | Claims not addressed. | Compensation payments completed (except for some disputed cases) | Almost all claims have been addressed. The existing grievance mechanism continues to be functional. |
PAPs around the dam and reservoir area are resettled and compensated | Value | 0.00 | 100.00 | 100.00 |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | All PAPs have been settled. | PAPs resettled and compensated. Livelihood skills training is largely completed. | "Shoreline Farmers" or those who began planting inside the shoreline continue to be sensitized and are provided with life-skillstraining and access to community benefit schemes, to encourage alternative income sources. |
PAPs with livelihoods restored to same level as pre-project | Value | 0.00 | 80.00 | 100.00 |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | Livelihood Restoration Programs not implemented. | Livelihood Restoration Programs are completed, and initial evidence indicates that PAPs are better-off after the projectimplementation. | Livelihoods would have been restored to pre-project levels. |
BWMA fulfills its key functions | Value | 0 | 19 | 20 |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | Maximum score of 25 points (completion of RAP; water quality & water borne diseases Monitoring, management of conservation area) | BWMA functional and is performing key functions satisfactorily. | BWMA is fulfilling its mandate and all key functions. |
Loma mountains National Park established and operational | Value | No | Yes | Yes |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | No Loma Mountain National Park. | Loma Mountain National Park has been proclaimed as a National Park, and is working as a National Park. | Loma Mountain National Park is operational. |
Direct Project Beneficiaries (number) of which female (%) | Value | 34% | 45% | 50% |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | 34% female beneficiaries in LAIR and SAP | 45% female beneficiaries have benefited in LAIR and SAP | 52% female beneficiaries have benefited in LAIR and SAP |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Revised 161kV Transmission line RAP implemented | Value | No | Yes | Yes |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | Revised RAP for 161 kV Transmission line not implemented. | RAP is largely implemented, and a Completion Report is being prepared. | Revised RAP is fully implemented. |
Amount of replacement land provided (ha) | Value | 198.00 | 198.00 | 198.00 |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | No replacement land yet. | Replacement land provided. | Completed. |
RAP implemented in accordance with schedule | Value | No | Yes | Yes |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | RAP implementation is behind schedule. | RAP Completion Reports are being finalized. | RAP implementation is completed. |
Completion of the Stabilized Agriculture Program (SAP) | Value | No | Yes | Yes |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | SAP not completed. | SAP programs are largely completed. | Completed. |
Completion of the Livelihood Assistance and Income Restoration Programs | Value | No | Yes | Yes |
Date | September 28, 2011 | April 15, 2013 | June 30, 2013 | |
Comment | LAIR not completed. | LAIR programs are largely completed. | Completed. |
Legal ACT passed to create BWMA and BCA | Value | No | Yes | Yes |
Date | September 28, 2011 | April 15, 2013 | June 30, 2013 | |
Comment | Legal Act not passed. | BWMA and BCA has been established. | BWMA and BCA have been established through legal Act.. |
Bumbuna Watershed Management Plan developed and adopted | Value | No | Yes | Yes |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | Bumbuna Watershed Management Plan not developed. | Bumbuna Watershed Management Plan has been developed. | Bumbuna Watershed Management Plan developed and adopted. |
Sustainable Financing Mechanism in place for BWMA and Loma Mountains National Park | Value | No | Yes (Partial) | No |
Date | September 28, 2011 | April 15, 2013 | June 30, 2013 | |
Comment | No sustainable financing for BWMA and LMNP. | Sustainable financing mechanism for BWMA and LMNP is still being worked out. These costs are included in the PPA but funds are notbeing allocated. | Sustainable financing for BWMA and LMNP Has not been put in place. |
BWMA regularly reports on state of environment in watershed | Value | No | Yes | Yes |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | No regular reports. | BWMA continues to prepare monitoring reports. | Regular reporting has been done. |
Draft Loma National Park Management Plan prepared | Value | No | Yes | Yes |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | No LMNP Management Plan | LMNP Management Plan completed and is being disclosed. | LMNP Environment and Social Management Plan (ESMP) has been disclosed and implemented. |
Provisional warning system downstream installed | Value | No | Yes (Partial) | No |
Date | September 28, 2010 | April 15, 2013 | June 30, 2013 | |
Comment | Not installed | Equipment has arrived and is being cleared at the Port. Residual civil works underway. Installation is expected by end-May 2013. | Sirens have not been installed, but the equipment is at site. |