Financier | Commitments |
---|---|
IDA GRANT FOR POST-CONFLICT | 101.80 |
P086874
Closed
Maurizia Tovo
N/A
September 9, 2004
(as of board presentation)
August 26, 2004
July 26, 2005
US$ 101.80 million
N/A
2005
US$ 101.80 million
B
Not Applicable
June 30, 2013
BANK APPROVED
August 27, 2013
Financier | Commitments |
---|---|
IDA GRANT FOR POST-CONFLICT | 101.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 101.80 |
IBRD + IDA Commitment | 101.80 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 101.80 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 30, 2013 | IDA-H5520 | Loan Disb | -10,684.14 |
Oct 30, 2013 | IDA-H5520 | Loan Disb | -73,187.41 |
Oct 29, 2013 | IDA-H7200 | Loan Disb | -187,846.64 |
Nov 1, 2013 | IDA-H7200 | Loan Cancel | 186,356.27 |
Sep 30, 2013 | IDA-H1200 | Loan Disb | -29,802.89 |
Nov 1, 2013 | IDA-H5520 | Loan Cancel | 83,230.91 |
Mar 30, 2010 | IDA-H5520 | Loan Commitment | 35,000,000.00 |
Jun 24, 2014 | IDA-H1200 | Loan Disb | -56,306.40 |
Jun 24, 2014 | IDA-H1200 | Loan Disb | -35,006.60 |
Jun 24, 2014 | IDA-H1200 | Loan Cancel | 121,301.23 |
Aug 26, 2004 | IDA-H1200 | Loan Commitment | 60,000,000.00 |
Jun 28, 2011 | IDA-H7200 | Loan Commitment | 6,800,000.00 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2013-01-21 |
Overall Safeguards Rating | Satisfactory | 2013-01-21 |
Progress towards achievement of PDO | Satisfactory | 2013-01-21 |
Financial Management | Moderately Satisfactory | 2013-01-21 |
Monitoring and Evaluation | Moderately Satisfactory | 2013-01-21 |
Project Management | Satisfactory | 2013-01-21 |
Overall | Low | 2013-01-21 |
Counterpart Funding | Satisfactory | 2013-01-21 |
Overall Implementation Progress (IP) | Satisfactory | 2013-01-21 |
Overall Safeguards Rating | Satisfactory | 2013-01-21 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-30-2013 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Substantial |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 06-23-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Female beneficiaries | Value | 0.00 | 53.00 | 0.00 |
Date | February 1, 2005 | September 30, 2012 | March 31, 2013 | |
Comment |
Average increase in enrollment in FSRDC built/rehabilitated classrooms | Value | 0.00 | 65.00 | 35.00 |
Date | December 31, 2004 | December 31, 2010 | March 31, 2013 | |
Comment | As of December 2010 the average increase in enrollment in FRSDC built/rehabilitated classrooms were 65 percent. According to themost recent M/E report with data from December 2010, the enrollment increased from 34% in 2008, 50% in 2009 and 65% in 2010. InManiema, the increase in enrollment was even 100% and in Equateur it was 95%. |
Average increase in medical consultations in FSRDC built/rehabilitated health centers | Value | 0.00 | 72.00 | 50.00 |
Date | February 1, 2005 | December 31, 2010 | March 31, 2013 | |
Comment | The average increase in medical consultations in FSRDC built/rehabilitated centers was in December 2010, 72 percent. |
Number of people in rural areas provided with access to Improved Water Sources under the project | Value | 0.00 | 180000.00 | 0.00 |
Date | February 1, 2005 | October 31, 2012 | March 31, 2013 | |
Comment | The number of beneficiaries is likely to be an underestimate as it does not include the total village or neighborhood population.Correct estimates will be provided with the next ISR. |
Traders with access to stalls and/or storage facilities rehabilitated by the project | Value | 0.00 | 20741.00 | 0.00 |
Date | February 1, 2005 | October 31, 2012 | March 31, 2013 | |
Comment | A total of 67 markets were built or rehabilitated, and an additional 29 market sub-projects are ongoing. | No end target established |
Reduction in average travel time of motorized vehicles on rehabilitated roads | Value | 0.00 | 210.00 | 30.00 |
Date | February 1, 2005 | December 31, 2010 | March 31, 2013 | |
Comment | By end December 2010, the reduction in average time travel of motorized vehicles was 210 percent |
Direct project beneficiaries | Value | 0.00 | 1136132.00 | 487500.00 |
Date | February 1, 2005 | September 30, 2012 | March 31, 2013 | |
Comment | This indicator will have to be reviewed as until now it has been underestimated, because it counted as beneficiaries only membersof project committees rather than the whole community. It has been agreed that for most types of sub-projects, the whole communityshould be considered beneficiary (e.g., water supply, health, sanitation, transport). NB: The percentage of female beneficiaries(a sub-indicator) is estimated on the basis of census figures; the previous ISR erroneously report the estimated number rather thanthe percentage. |
Sub-projects that are operational and well maintained within a year of completion | Value | 0.00 | 95.00 | 90.00 |
Date | February 1, 2005 | March 31, 2012 | March 31, 2013 | |
Comment | These are preliminary results. Final results will be available on Dec 31, 2012. |
Village committees operational after one year of completion of project | Value | 0.00 | 90.00 | 90.00 |
Date | February 1, 2005 | March 31, 2012 | March 31, 2013 | |
Comment | These are preliminary results. Final results will be available on Dec 31, 2012. |
Person days provided in labor-intensive public works | Value | 0.00 | 331992.00 | 290000.00 |
Date | March 1, 2010 | September 30, 2012 | March 31, 2013 | |
Comment | This indicator includes the person-days created with a $5M SPF grant also executed by the FSRDC using the same approach. Shouldperson-days created with the SPF grant be excluded, the total number would be 107,041 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
FSRDC is represented and functions efficiently and autonomously in all provinces | Value | No | Yes | Yes |
Date | December 31, 2004 | October 31, 2012 | March 31, 2013 | |
Comment | FSRDC has been able to continue operating also in the conflict-ridden east, as the demonstrated by the recent inauguration of ahealth center in North Kivu, with rebel leaders in attendance |
Sub-projects completed, local implementing agencies employed and local enterprises contracted (see breakdown by sub-indicators) | Value | 0.00 | 1015.00 | 0.00 |
Date | December 31, 2004 | October 31, 2012 | March 31, 2013 | |
Comment | No end target established |
ALEs | Value | 0.00 | 157.00 | 229.00 |
Date | December 31, 2004 | September 30, 2012 | March 31, 2013 | |
Comment |
Sub-contractors based in remote and impoverished areas | Value | 0.00 | 176.00 | 97.00 |
Date | December 31, 2004 | September 30, 2012 | March 31, 2013 | |
Comment |
Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions. | Value | 0.00 | 2628.00 | 0.00 |
Date | December 31, 2004 | October 31, 2012 | March 31, 2013 | |
Comment | For some reason this core indicator has disappeared from the results framework | No end target established |
Sub-projects | Value | 0.00 | 782.00 | 915.00 |
Date | October 31, 2012 | March 31, 2013 | ||
Comment | Of which: 644 under the original project and 138 under the first Add Fin. An additional 246 sub-projects are ongoing. | Target includes 550 sub-projects under the original project, 300 under the first Add Fin and 65 under the second Add Fin. |
Health facilities constructed, renovated, and/or equipped (number) | Value | 0.00 | 101.00 | 0.00 |
Date | December 31, 2004 | October 31, 2012 | March 31, 2013 | |
Comment | Refers to completed sub-projects only. An additional 18 are under construction. | No end target established |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 108.00 | 0.00 |
Date | December 31, 2004 | October 31, 2012 | March 31, 2013 | |
Comment | Refers to completed sub-projects only. An additional 28 are under construction. | No end target established |
Roads rehabilitated, Rural | Value | 0.00 | 316.00 | 0.00 |
Date | December 31, 2004 | October 31, 2012 | March 31, 2013 | |
Comment | An additional 141 km have been rehabilitated with SPF funding. NB: the two Add Fin have concentrated on roads, which explains thephenomenal increase. | No end target established |
Market places constructed or rehabilitated | Value | 0.00 | 67.00 | 0.00 |
Date | December 31, 2004 | October 31, 2012 | March 31, 2013 | |
Comment | Of which 47 under the original project and 20 and the first Add Fin | No end target established |
Environment sub-projects implemented | Value | 0.00 | 2.00 | 0.00 |
Date | December 31, 2004 | October 31, 2012 | March 31, 2013 | |
Comment | These are two anti-erosion sub-projects financed by the first Add Fin | No end target established |
Communities benefiting from at least one sub-project | Value | 0.00 | 993.00 | 915.00 |
Date | December 31, 2004 | September 30, 2012 | March 31, 2013 | |
Comment | Includes also communities where sub-projects are still ongoing. Communities where at least one sub-project has been completed are762. | This includes 550 under the original rpoject, 300 under the first Additional Financing and 65 under the second Add Fin (the endtarget in the previous ISR did not include the second Add Fin) |
Beneficiaries of public works program | Value | 0.00 | 4820.00 | 3895.00 |
Date | March 1, 2010 | September 30, 2012 | March 31, 2013 | |
Comment | This includes 3,389 financed by the SPF grant and 1,431 financed by the first Additional Financing |
Share of wage bill/total cost | Value | 0.00 | 35.00 | 35.00 |
Date | March 1, 2010 | March 31, 2012 | March 31, 2013 | |
Comment | The real target is AT LEAST 35% |
Population indicating satisfaction with their participation in sub-project planning | Value | 0.00 | 91.00 | 70.00 |
Date | December 31, 2004 | September 30, 2012 | March 31, 2013 | |
Comment | Participation rate at the planning stage is 91%. No information is available on satisfaction with participation in planning. |
Village committees established | Value | 0.00 | 722.00 | 850.00 |
Date | December 31, 2004 | September 30, 2012 | March 31, 2013 | |
Comment | This refers to the Maintenance Committees set up when a sub-project is completed |
Communities trained in planning, implementing and managing the economic and social infrastructure | Value | 0.00 | 855.00 | 850.00 |
Date | December 31, 2004 | September 30, 2012 | March 31, 2013 | |
Comment |
Students receiving scholarship | Value | 0.00 | 7392.00 | 7392.00 |
Date | December 31, 2004 | March 1, 2010 | March 31, 2013 | |
Comment |
Libraries established and maintained one year after completion | Value | 0.00 | 423.00 | 423.00 |
Date | December 31, 2004 | March 1, 2010 | March 31, 2013 | |
Comment |
Baseline and annual surveys provide regular monitoring and evaluation of project impact | Value | No | Yes | Yes |
Date | December 31, 2004 | October 31, 2012 | March 31, 2013 | |
Comment | A survey was carried out in March 2012, but final results are not yet available |
Operating costs are at or below 20% of total project investments | Value | No | Yes | Yes |
Date | December 31, 2004 | October 31, 2012 | March 31, 2013 | |
Comment | 7% |