Democratic Republic of Congo Emergency Social Action Project

Development Objective

The objective of the project is to improve access of the poor to social and economic services and increase the availability and management of development resources at the community level.

Key Details

Project Details

  • P086874

  • Closed

  • Maurizia Tovo

  • N/A

  • Congo, Democratic Republic of

  • September 9, 2004

  • (as of board presentation)

    August 26, 2004

  • July 26, 2005

  • US$ 101.80 million

  • B

  • Not Applicable

  • June 30, 2013

  • BANK APPROVED

  • August 27, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA GRANT FOR POST-CONFLICT 101.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 101.80
IBRD + IDA Commitment 101.80
Lending Instrument
Grant Amount N/A
Total Project Cost** 101.80

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 30, 2013 IDA-H5520 Loan Disb -10,684.14
Oct 30, 2013 IDA-H5520 Loan Disb -73,187.41
Oct 29, 2013 IDA-H7200 Loan Disb -187,846.64
Nov 1, 2013 IDA-H7200 Loan Cancel 186,356.27
Sep 30, 2013 IDA-H1200 Loan Disb -29,802.89
Nov 1, 2013 IDA-H5520 Loan Cancel 83,230.91
Mar 30, 2010 IDA-H5520 Loan Commitment 35,000,000.00
Jun 24, 2014 IDA-H1200 Loan Disb -56,306.40
Jun 24, 2014 IDA-H1200 Loan Disb -35,006.60
Jun 24, 2014 IDA-H1200 Loan Cancel 121,301.23
Aug 26, 2004 IDA-H1200 Loan Commitment 60,000,000.00
Jun 28, 2011 IDA-H7200 Loan Commitment 6,800,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2013-01-21
Overall Safeguards Rating Satisfactory 2013-01-21
Progress towards achievement of PDO Satisfactory 2013-01-21
Financial Management Moderately Satisfactory 2013-01-21
Monitoring and Evaluation Moderately Satisfactory 2013-01-21
Project Management Satisfactory 2013-01-21
Overall Low 2013-01-21
Counterpart Funding Satisfactory 2013-01-21
Overall Implementation Progress (IP) Satisfactory 2013-01-21
Overall Safeguards Rating Satisfactory 2013-01-21

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-30-2013
OutcomesSubstantial
Risk to Development OutcomeSubstantial
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceModerately Satisfactory
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-23-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Female beneficiariesValue0.0053.000.00
    DateFebruary 1, 2005September 30, 2012March 31, 2013
    Comment
  • Average increase in enrollment in FSRDC built/rehabilitated classroomsValue0.0065.0035.00
    DateDecember 31, 2004December 31, 2010March 31, 2013
    CommentAs of December 2010 the average increase in enrollment in FRSDC built/rehabilitated classrooms were 65 percent. According to themost recent M/E report with data from December 2010, the enrollment increased from 34% in 2008, 50% in 2009 and 65% in 2010. InManiema, the increase in enrollment was even 100% and in Equateur it was 95%.
  • Average increase in medical consultations in FSRDC built/rehabilitated health centersValue0.0072.0050.00
    DateFebruary 1, 2005December 31, 2010March 31, 2013
    CommentThe average increase in medical consultations in FSRDC built/rehabilitated centers was in December 2010, 72 percent.
  • Number of people in rural areas provided with access to Improved Water Sources under the projectValue0.00180000.000.00
    DateFebruary 1, 2005October 31, 2012March 31, 2013
    CommentThe number of beneficiaries is likely to be an underestimate as it does not include the total village or neighborhood population.Correct estimates will be provided with the next ISR.
  • Traders with access to stalls and/or storage facilities rehabilitated by the projectValue0.0020741.000.00
    DateFebruary 1, 2005October 31, 2012March 31, 2013
    CommentA total of 67 markets were built or rehabilitated, and an additional 29 market sub-projects are ongoing.No end target established
  • Reduction in average travel time of motorized vehicles on rehabilitated roadsValue0.00210.0030.00
    DateFebruary 1, 2005December 31, 2010March 31, 2013
    CommentBy end December 2010, the reduction in average time travel of motorized vehicles was 210 percent
  • Direct project beneficiariesValue0.001136132.00487500.00
    DateFebruary 1, 2005September 30, 2012March 31, 2013
    CommentThis indicator will have to be reviewed as until now it has been underestimated, because it counted as beneficiaries only membersof project committees rather than the whole community. It has been agreed that for most types of sub-projects, the whole communityshould be considered beneficiary (e.g., water supply, health, sanitation, transport). NB: The percentage of female beneficiaries(a sub-indicator) is estimated on the basis of census figures; the previous ISR erroneously report the estimated number rather thanthe percentage.
  • Sub-projects that are operational and well maintained within a year of completionValue0.0095.0090.00
    DateFebruary 1, 2005March 31, 2012March 31, 2013
    CommentThese are preliminary results. Final results will be available on Dec 31, 2012.
  • Village committees operational after one year of completion of projectValue0.0090.0090.00
    DateFebruary 1, 2005March 31, 2012March 31, 2013
    CommentThese are preliminary results. Final results will be available on Dec 31, 2012.
  • Person days provided in labor-intensive public worksValue0.00331992.00290000.00
    DateMarch 1, 2010September 30, 2012March 31, 2013
    CommentThis indicator includes the person-days created with a $5M SPF grant also executed by the FSRDC using the same approach. Shouldperson-days created with the SPF grant be excluded, the total number would be 107,041

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • FSRDC is represented and functions efficiently and autonomously in all provincesValueNoYesYes
    DateDecember 31, 2004October 31, 2012March 31, 2013
    CommentFSRDC has been able to continue operating also in the conflict-ridden east, as the demonstrated by the recent inauguration of ahealth center in North Kivu, with rebel leaders in attendance
  • Sub-projects completed, local implementing agencies employed and local enterprises contracted (see breakdown by sub-indicators)Value0.001015.000.00
    DateDecember 31, 2004October 31, 2012March 31, 2013
    CommentNo end target established
  • ALEsValue0.00157.00229.00
    DateDecember 31, 2004September 30, 2012March 31, 2013
    Comment
  • Sub-contractors based in remote and impoverished areasValue0.00176.0097.00
    DateDecember 31, 2004September 30, 2012March 31, 2013
    Comment
  • Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions.Value0.002628.000.00
    DateDecember 31, 2004October 31, 2012March 31, 2013
    CommentFor some reason this core indicator has disappeared from the results frameworkNo end target established
  • Sub-projectsValue0.00782.00915.00
    DateOctober 31, 2012March 31, 2013
    CommentOf which: 644 under the original project and 138 under the first Add Fin. An additional 246 sub-projects are ongoing.Target includes 550 sub-projects under the original project, 300 under the first Add Fin and 65 under the second Add Fin.
  • Health facilities constructed, renovated, and/or equipped (number)Value0.00101.000.00
    DateDecember 31, 2004October 31, 2012March 31, 2013
    CommentRefers to completed sub-projects only. An additional 18 are under construction.No end target established
  • Improved community water points constructed or rehabilitated under the projectValue0.00108.000.00
    DateDecember 31, 2004October 31, 2012March 31, 2013
    CommentRefers to completed sub-projects only. An additional 28 are under construction.No end target established
  • Roads rehabilitated, RuralValue0.00316.000.00
    DateDecember 31, 2004October 31, 2012March 31, 2013
    CommentAn additional 141 km have been rehabilitated with SPF funding. NB: the two Add Fin have concentrated on roads, which explains thephenomenal increase.No end target established
  • Market places constructed or rehabilitatedValue0.0067.000.00
    DateDecember 31, 2004October 31, 2012March 31, 2013
    CommentOf which 47 under the original project and 20 and the first Add FinNo end target established
  • Environment sub-projects implementedValue0.002.000.00
    DateDecember 31, 2004October 31, 2012March 31, 2013
    CommentThese are two anti-erosion sub-projects financed by the first Add FinNo end target established
  • Communities benefiting from at least one sub-projectValue0.00993.00915.00
    DateDecember 31, 2004September 30, 2012March 31, 2013
    CommentIncludes also communities where sub-projects are still ongoing. Communities where at least one sub-project has been completed are762.This includes 550 under the original rpoject, 300 under the first Additional Financing and 65 under the second Add Fin (the endtarget in the previous ISR did not include the second Add Fin)
  • Beneficiaries of public works programValue0.004820.003895.00
    DateMarch 1, 2010September 30, 2012March 31, 2013
    CommentThis includes 3,389 financed by the SPF grant and 1,431 financed by the first Additional Financing
  • Share of wage bill/total costValue0.0035.0035.00
    DateMarch 1, 2010March 31, 2012March 31, 2013
    CommentThe real target is AT LEAST 35%
  • Population indicating satisfaction with their participation in sub-project planningValue0.0091.0070.00
    DateDecember 31, 2004September 30, 2012March 31, 2013
    CommentParticipation rate at the planning stage is 91%. No information is available on satisfaction with participation in planning.
  • Village committees establishedValue0.00722.00850.00
    DateDecember 31, 2004September 30, 2012March 31, 2013
    CommentThis refers to the Maintenance Committees set up when a sub-project is completed
  • Communities trained in planning, implementing and managing the economic and social infrastructureValue0.00855.00850.00
    DateDecember 31, 2004September 30, 2012March 31, 2013
    Comment
  • Students receiving scholarshipValue0.007392.007392.00
    DateDecember 31, 2004March 1, 2010March 31, 2013
    Comment
  • Libraries established and maintained one year after completionValue0.00423.00423.00
    DateDecember 31, 2004March 1, 2010March 31, 2013
    Comment
  • Baseline and annual surveys provide regular monitoring and evaluation of project impactValueNoYesYes
    DateDecember 31, 2004October 31, 2012March 31, 2013
    CommentA survey was carried out in March 2012, but final results are not yet available
  • Operating costs are at or below 20% of total project investmentsValueNoYesYes
    DateDecember 31, 2004October 31, 2012March 31, 2013
    Comment7%