Abstract*

This loan is the first of two single-tranche sector Development Policy Loans (DPLs). It supports the implementation of the first phase of Namibia's Education and Training Sector Improvement Program (ETSIPl). It is also the first International Bank for Reconstruction and Development (IBRD) lending operation for Namibia. ETSIPl is the first implementation phase of the government's 15-year strategic plan for the improvement of the education and training...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

DPL1 supports the development of: (i) specific policies and policy instruments to guide and give effect to planned sector reforms; (ii) legal instruments to enforce policy implementation; and (iii) institutional capacities required for effective implementation of planned sector reforms.

Key Details

Project Details

  • P086875

  • Closed

  • Milan Vodopivec

  • N/A

  • Namibia

  • May 18, 2007

  • (as of board presentation)

    May 24, 2007

  • December 20, 2007

  • US$ 44.97 million

  • N/A

  • Not Applicable

  • December 31, 2008

  • BANK APPROVED

  • August 5, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
US: Agency for International Development (USAID) 4.78
US, Govt. of 10.31
Bilateral Agencies (unidentified) 1.86
LUXEMBOURG: Miistry of Finance 1.86
NETHERLANDS: Min. of Foreign Affairs / Min. of Dev. Coop. 2.48
GERMANY, Govt. of (Except for BMZ) 3.72
EC: European Commission 9.35
UN Development Programme 2.81
Borrower/Recipient 14.87
International Bank for Reconstruction and Development 7.50
Local Sources of Borrowing Country 0.80
FINLAND: Ministry for Foreign Affairs 0.30

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 7.50
IDA Commitment N/A
IBRD + IDA Commitment 7.50
Lending Instrument
Grant Amount 37.47
Total Project Cost** 60.64

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 24, 2007 IBRD-74470 Loan Commitment 7,500,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Program Management Satisfactory 2009-01-20
Overall Implementation Progress (IP) Satisfactory 2009-01-20
Progress towards achievement of PDO Satisfactory 2009-01-20
Monitoring and Evaluation Moderately Satisfactory 2009-01-20

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 02-03-2012
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceNot Applicable
Implementing AgencyNot Applicable

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-20-2012PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Pro-poor and development-relevant expansion of access to post-basic education and training.Seven percentage point increase ingrade 11 intake.Value16,91117,375 (2.7 percentage point increase)Target was 18,208 or 7% point increase. Actual was
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Proportion of new grade 11 places created in the poorest regions.Value0 percent60 percent of the new 2007 places were created in 60 percent of new places in 2008 were created coll
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Percentage point increase in OVCs that successfully complete grade 12.Value0 percentThe EMIS is being upgraded to monitor progress.EMIS data are not yet linked to examinations data
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Increased pre-entry enrolment in mathematics, science and ICTs.Value0 percentNone enrolled as yet. The first 150 entrants expecTarget: 150 students enrolled with 50 in each: Mat
    DateApril 27, 2007August 14, 2008December 31, 2008
    Comment
  • 14 percentage point increase in grade 10 graduates who secure a VET place.Value3,0003,011Target was 3,990. Actual was 4716 or 57% point inc
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Specific policies, legal instruments and institutions that are vital to support planned sector reforms are developed, approved and under implementation.ValueOnly the HIV/AIDS and ICTs policies were in place Cabinet has aproved: sector policy on HIV/AIDS; seNTA Bill passed, NCHE Secretariat in place, pre-pr
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved internal efficiency.Grade 1 repetition rate.Value19.62007 indicators will be available by the first quaTarget was 16. Actual was 21.9 signaling a deterio
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Grade 5 repetition rate.Value22.12007 indicators will be available by the first quaTarget was 19. Actual was 25.7 signaling a deteri
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Grade 8 repetition rate.Value23.12007 indicators will be available by the first quaTarget was 20. Actual is 24.2 signaling a deterior
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Average basic education repetition rate.Value15.52007 indicators will be available by the first quaTarget was 14. Actual was 20, signaling a deterior
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Grade 10 push-out rate.Value472007 indicators will be available by the first quaTarget was 40. Actual was 39 signaling a substanti
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Primary learner to teacher ratio.Value31:12007 indicators will be available by the first quaTarget was 32:1. Actual is 32.
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Secondary learner to teacher ratio.Value25:12007 indicators will be available by the first quaTarget was 26:1. Actual is 26.
    DateApril 27, 2007December 14, 2007December 31, 2008
    Comment
  • Improved quality.Percentage of learners attaining a D grade or better in the national grade 10 examinations for.ValueMathematics 37.2, Science 41.1, English 43.02007 indicators will be available by the first quaTargets: Maths 42, Science 46, English 48.Actual
    DateApril 27, 2007December 31, 2007December 31, 2008
    Comment
  • Percentage of learners attaining a D grade or better in the national grade 12 examinations for.ValueMathematics 37.2, Science 41.3, English 34.72007 indicators will be available by the first quaTargets: Maths 42, Science 46, English 40.Actual
    DateApril 27, 2007December 31, 2007December 31, 2008
    Comment
  • Percentage average annual completion rate for vocational education and training.Value732007 indicators will be available by the first quaTarget: 78. Actual: 80.
    DateApril 27, 2007December 31, 2007December 31, 2008
    Comment