Abstract*

The project will adopt three key features in terms of the lending instrument: (a) a programmatic approach; (b) a Program-Based Sector-wide Approach (SWAp); and (c) mechanisms to pace disbursements against conditional cash transfers under the Bolsa Familia Program (BFP) in line with technical improvements. These three features will help foster an effective link between the implementation of the BFP while helping strengthen the program through crucial...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The broad objectives of the Government's Bolsa Família Program (BFP) are to reduce poverty and inequality and promote human capital investments among poor families (including indigenous and quilombola populations) through the provision of direct monetary transfers to poor families and incentives for investing in human capital. The main objectives of this first phase APL include strengthening the Bolsa Familia program's BFPs ability to reduce poverty and inequality by: (a) consolidating conditional cash transfer programs and reducing gaps and duplications in coverage; (b) strengthening the system for identifying the target population; (c) developing a monitoring and evaluation system for the BFP; and (d) strengthening the basic institutional functioning of the program.

Key Details

Project Details

  • P087713

  • Closed

  • Manuel Salazar Ferro

  • N/A

  • Brazil

  • January 5, 2004

  • (as of board presentation)

    June 17, 2004

  • June 15, 2005

  • US$ 1572.20 million

  • C

  • Not Applicable

  • December 31, 2009

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Inter-American Development Bank 1000.00
International Bank for Reconstruction and Development 572.20
Borrower/Recipient 5622.70

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 572.20
IDA Commitment N/A
IBRD + IDA Commitment 572.20
Lending Instrument
Grant Amount 1000.00
Total Project Cost** 7194.90

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 17, 2004 IBRD-72340 Loan Commitment 572,200,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Satisfactory 2009-12-09
Procurement Moderately Satisfactory 2009-12-09
Progress towards achievement of PDO Satisfactory 2009-12-09
Financial Management Satisfactory 2009-12-09
Counterpart Funding Satisfactory 2009-12-09
Project Management Moderately Satisfactory 2009-12-09
Monitoring and Evaluation Satisfactory 2009-12-09
Overall Implementation Progress (IP) Satisfactory 2009-12-09

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-29-2010
OutcomesSubstantial
Risk to Development OutcomeNegligible
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceHighly Satisfactory
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-20-2012PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeNegligible To LowN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceHighly SatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualityExemplaryN/a
M&e QualityHighN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Coverage of extreme poorValueNone receivingAchieved. 11.1 mn families receiving benefits (10At least 2/3 of extreme poor families receiving BF
    DateSeptember 30, 2003April 18, 2008December 31, 2008
    Comment
  • Targeting accuracyValue66% of benefits of pre-reform programs were receivPNAD 2006 reveals that 90% of BFP benefits were reMore than 66% of transfers going to households in
    DateJanuary 1, 2003April 17, 2008December 31, 2008
    Comment
  • Improve school attendance of poorValue70% of municipalities reporting school attendance First semester 2009, information available on 85% At least 80% of primary-age children in extremely
    DateOctober 1, 2004June 30, 2009November 30, 2005
    Comment
  • Improve health care access of poorValue75-77% of children 0-6 years of age in the impact Over 90% of the families with info on health condiAt least 95% of beneficiary children with health c
    DateNovember 30, 2005May 22, 2009December 31, 2006
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Pre-reform programs consolidated into BFP (Component One).ValueBE=5.1 mn familiesBA=1.7 mn familiesPCA = 0.8 mn fBE = 179 remaining families; BA = 2 PCA = 14,646 APre-reform programs eliminated (former beneficiari
    DateSeptember 30, 2003June 30, 2009December 31, 2006
    Comment
  • Administrative cost efficiency improved (Component One).ValueCentral Government admin costs = 5.3% of total proTarget exceeded. Central Government admin costs = Transactions costs for transfer payments reduced b
    DateDecember 31, 2002November 30, 2009November 30, 2005
    Comment
  • Instruments for implementing eligibility criteria for BF beneficiaries revised* (Component Two).ValueExisting criteria based on unverified self-reporteWith empirical evidence of strong targeting outcomRevised instruments for verifying eligibility crit
    DateNovember 1, 2003June 2, 2009December 31, 2006
    Comment
  • Cadastro Unico questionnaires strengthened* (Component Two).ValueExisting questionnaires weak (incomplete income quIBGE/MDS complete revision of new questionnaires, New Cadastro Unico questionnaires developed and pr
    DateNovember 1, 2003April 18, 2009December 31, 2005
    Comment
  • Procedures for implementing Cadastro Unico strengthened and communicated* (Component Two).ValueNeed to clarify and communicate roles, norms for vCompleted. Aide Memoire documents the various decNormative acts and operational guidelines for Cada
    DateNovember 1, 2003June 27, 2006June 27, 2006
    Comment
  • Data collection strategy strengthened* (Component Two).ValueCurrent system is static (does not allow for updatDecree for cadastro mgt published 06/26/2007 and cExpansion and recertification data collection stra
    DateNovember 1, 2003April 18, 2008December 31, 2006
    Comment
  • Duplications purged* (Component Two).ValueNo systematic checks for duplications.Completed. MDS has developed systematic internal Elimination of all detectable duplications in the
    DateNovember 1, 2003April 18, 2008December 31, 2005
    Comment
  • Recertification policy established (Component Two).ValuePolicy for periodicity of recertification not esta2-year periodicity of recertification policy estabPolicy for periodicity for updating Cadastro Unico
    DateNovember 1, 2003June 2, 2009June 27, 2006
    Comment
  • Cadastro Unico being used as policy management tool* (Component Two).ValueMDS and municipalities lack access to actual CadasCompleted/exceeded. MDS and 100% of municipalitiesCadastro Unico users (MDS and at least 50% of muni
    DateNovember 1, 2003June 2, 2009June 27, 2006
    Comment
  • Real-time monitoring of program strengthened* (Component Three).ValueCurrent MIS covers well the physical-financial aspMIS operating for all elements (cadastro in real tAdequate MIS for BFP developed and operating
    DateMay 31, 2004April 18, 2009December 31, 2005
    Comment
  • Federal oversight mechanisms for decentralized implementation developed and operational* (Component Three).ValueProgram lacks instruments for federal oversight.Significant progress. Since January 2005, CGU regQuality Control Reviews of BF processes implemente
    DateMay 31, 2004April 18, 2008December 31, 2005
    Comment
  • Impact of BFP evaluated* (Component Three).ValueOther than ex-ante simulations (BE) and evaluationAnalysis for baseline household survey covering 15Household surveys for impact evaluation conducted;
    DateMay 31, 2004May 18, 2009December 31, 2006
    Comment
  • Institutional roles clarified* (Component Four).ValueProgram not regulated (lacks regulamento and operaCompleted. Aide Memoire references specific decreMatrix of key functional and institutional respons
    DateJanuary 31, 2004June 27, 2006June 30, 2005
    Comment
  • Communications strengthened* (Component Four).ValueProgram beneficiaries lack information about theirBeneficiary booklet content designed, printed and Beneficiary information booklets (cadernetas) desi
    DateMay 31, 2004June 27, 2006June 27, 2006
    Comment
  • System for verifying conditionalities operating* (Component Four).ValueProgram not systematically verifying compliance wi51% of 12.3 million children w/ education conditioSystem for verifying conditionalities (health, edu
    DateMay 31, 2004March 31, 2008December 31, 2005
    Comment