IQ - Emergency Road Rehabilitation

Development Objective

The objective of the proposed Emergency Road Rehabilitation Project is to improve the condition of road assets by rehabilitating highly damaged segments of the country's highway and rural road networks, reestablishing critical river crossings, and restoring the capacity to manage and maintain road assets.

Key Details

Project Details

  • P087735

  • Closed

  • Ibrahim Dajani

  • N/A

  • Iraq

  • December 22, 2005

  • (as of board presentation)

    June 29, 2006

  • October 15, 2007

  • US$ 135.00 million

  • A

  • Not Applicable

  • June 30, 2014

  • BANK APPROVED

  • March 11, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 135.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 135.00
IBRD + IDA Commitment 135.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 135.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 15, 2023 IDA-42120 Loan Repay 2,417,083.80
Sep 15, 2023 IDA-42120 Int Charges 248,306.80
Sep 15, 2023 IDA-42120 Int Charges 248,306.80
Mar 15, 2023 IDA-42120 Int Charges 259,948.10
Mar 15, 2023 IDA-42120 Loan Repay 1,565.27
Mar 15, 2023 IDA-42120 Loan Repay 2,474,131.00
Mar 15, 2023 IDA-42120 Int Charges 3,521.69
Mar 15, 2023 IDA-42120 Int Charges 3,521.69
Mar 15, 2023 IDA-42120 Int Charges 259,948.10
May 20, 2014 IDA-42120 Loan Disb 189,087.00
Jun 2, 2014 IDA-42120 Loan Disb 204,239.00
Jun 11, 2014 IDA-42120 Loan Disb 919,615.00
Mar 15, 2014 IDA-42120 Int Charges 376,340.50
Mar 15, 2014 IDA-42120 Int Charges 376,340.50
Mar 15, 2014 IDA-42120 Int Charges 6,489.24
Mar 15, 2014 IDA-42120 Int Charges 6,489.24
May 13, 2014 IDA-42120 Loan Disb 5,916.46
May 12, 2014 IDA-42120 Loan Disb 638,308.00
Jan 27, 2014 IDA-42120 Loan Disb 108,278.00
Mar 13, 2014 IDA-42120 Loan Disb 170,603.98
Apr 16, 2014 IDA-42120 Loan Disb 436,000.00
Mar 15, 2016 IDA-42120 Int Charges 385,920.53
Mar 15, 2016 IDA-42120 Int Charges 385,920.53
Mar 15, 2016 IDA-42120 Int Charges 3,550.23
Mar 15, 2016 IDA-42120 Int Charges 3,550.23
Sep 15, 2015 IDA-42120 Int Charges 15,674.75
Sep 15, 2015 IDA-42120 Int Charges 15,674.75
Sep 15, 2015 IDA-42120 Int Charges 374,196.62
Sep 15, 2015 IDA-42120 Int Charges 374,196.62
Sep 22, 2014 IDA-42120 Loan Disb 223,599.00
Nov 10, 2014 IDA-42120 Loan Cancel 27,665,032.00
Mar 15, 2015 IDA-42120 Int Charges 367,984.38
Mar 15, 2015 IDA-42120 Int Charges 367,984.38
Mar 15, 2015 IDA-42120 Int Charges 11,472.84
Jan 30, 2014 IDA-42120 Loan Disb 1,725,047.00
Feb 12, 2014 IDA-42120 Loan Disb 129,323.00
Sep 15, 2013 IDA-42120 Int Charges 6,209.90
Sep 15, 2013 IDA-42120 Int Charges 6,209.90
Sep 15, 2013 IDA-42120 Int Charges 337,975.03
Sep 15, 2013 IDA-42120 Int Charges 337,975.03
Sep 30, 2013 IDA-42120 Loan Disb 729,000.00
Sep 16, 2013 IDA-42120 Loan Disb 72,729.00
Nov 6, 2013 IDA-42120 Loan Disb 624,872.00
Dec 10, 2013 IDA-42120 Loan Disb 102,771.99
Dec 9, 2013 IDA-42120 Loan Disb 729,000.00
Jan 14, 2014 IDA-42120 Loan Disb 147,558.00
Oct 11, 2013 IDA-42120 Loan Disb 779,386.00
Nov 4, 2013 IDA-42120 Loan Disb 15,342.00
Oct 15, 2013 IDA-42120 Loan Disb 67,149.00
Sep 5, 2013 IDA-42120 Loan Disb 52,261.99
Sep 5, 2013 IDA-42120 Loan Disb 1,188,297.00
Sep 5, 2013 IDA-42120 Loan Disb 56,161.99
Sep 5, 2013 IDA-42120 Loan Disb 168,076.00
Sep 15, 2014 IDA-42120 Int Charges 5,756.65
Sep 15, 2014 IDA-42120 Int Charges 5,756.65
Sep 15, 2014 IDA-42120 Int Charges 389,226.62
Sep 15, 2014 IDA-42120 Int Charges 389,226.62
Sep 16, 2014 IDA-42120 Loan Disb 2,122,109.00
Aug 6, 2014 IDA-42120 Loan Disb 567,259.00
Jun 30, 2014 IDA-42120 Loan Disb 729,000.00
Sep 15, 2014 IDA-42120 Loan Disb 364,499.00
Mar 18, 2014 IDA-42120 Loan Disb 729,000.00
Sep 15, 2023 IDA-42120 Loan Repay 35,329.08
Nov 25, 2022 IDA-42120 Loan Repay 2,374,271.00
Nov 25, 2022 IDA-42120 Int Charges 264,705.75
Nov 25, 2022 IDA-42120 Int Charges 264,705.75
Mar 15, 2015 IDA-42120 Int Charges 11,472.84
Mar 15, 2017 IDA-42120 Int Charges 367,064.10
Mar 15, 2017 IDA-42120 Int Charges 367,064.10
Oct 18, 2017 IDA-42120 Loan Repay 2,617,440.50
Oct 18, 2017 IDA-42120 Int Charges 333,354.72
Oct 18, 2017 IDA-42120 Int Charges 333,354.72
Sep 15, 2017 IDA-42120 Loan Repay 3,533.38
Mar 15, 2017 IDA-42120 Int Charges 13,183.73
Mar 15, 2017 IDA-42120 Int Charges 13,183.73
Mar 15, 2017 IDA-42120 Loan Repay 2,509,840.00
Sep 15, 2016 IDA-42120 Int Charges 376,942.66
Sep 15, 2016 IDA-42120 Int Charges 376,942.66
Sep 15, 2016 IDA-42120 Int Charges 2,882.02
Sep 15, 2016 IDA-42120 Int Charges 2,882.02
Sep 15, 2016 IDA-42120 Loan Repay 2,604,145.00
Mar 15, 2019 IDA-42120 Loan Repay 2,589,360.50
Mar 15, 2019 IDA-42120 Int Charges 339,853.56
Mar 15, 2019 IDA-42120 Int Charges 339,853.56
Mar 15, 2019 IDA-42120 Int Charges 1,508.76
Mar 15, 2019 IDA-42120 Int Charges 1,508.76
Sep 15, 2018 IDA-42120 Loan Repay 2,608,589.80
Sep 15, 2018 IDA-42120 Int Charges 350,639.66
Sep 15, 2018 IDA-42120 Int Charges 350,639.66
Sep 15, 2018 IDA-42120 Int Charges 42,159.10
Sep 15, 2018 IDA-42120 Int Charges 42,159.10
Mar 15, 2018 IDA-42120 Int Charges 41,380.37
Mar 15, 2018 IDA-42120 Loan Repay 2,702,671.50
Mar 15, 2018 IDA-42120 Int Charges 1,855.60
Mar 15, 2018 IDA-42120 Int Charges 1,855.60
Mar 15, 2018 IDA-42120 Int Charges 331,316.03
Mar 15, 2018 IDA-42120 Int Charges 331,316.03
Mar 15, 2018 IDA-42120 Int Charges 41,380.37
Sep 15, 2020 IDA-42120 Loan Repay 6,896.44
Sep 15, 2020 IDA-42120 Int Charges 285,863.62
Sep 15, 2020 IDA-42120 Loan Repay 1,310,360.50
Sep 15, 2020 IDA-42120 Int Charges 285,863.62
Mar 15, 2021 IDA-42120 Loan Repay 1,328,266.20
Mar 15, 2021 IDA-42120 Int Charges 313,802.88
Mar 15, 2021 IDA-42120 Int Charges 313,802.88
Mar 15, 2021 IDA-42120 Int Charges 30,531.07
Mar 15, 2021 IDA-42120 Int Charges 30,531.07
Mar 15, 2020 IDA-42120 Loan Repay 2,538,693.00
Mar 15, 2020 IDA-42120 Int Charges 317,165.38
Mar 15, 2020 IDA-42120 Int Charges 317,165.38
Mar 15, 2020 IDA-42120 Loan Repay 24,260.00
Sep 15, 2019 IDA-42120 Int Charges 325,593.30
Sep 15, 2019 IDA-42120 Int Charges 325,593.30
Sep 15, 2019 IDA-42120 Loan Repay 6,230.37
Sep 15, 2019 IDA-42120 Loan Repay 2,547,442.80
Sep 15, 2022 IDA-42120 Loan Repay 59,167.73
Mar 15, 2022 IDA-42120 Int Charges 2,851.27
Mar 15, 2022 IDA-42120 Int Charges 2,851.27
Mar 15, 2022 IDA-42120 Loan Repay 2,565,128.80
Mar 15, 2022 IDA-42120 Int Charges 288,576.97
Mar 15, 2022 IDA-42120 Int Charges 288,576.97
Sep 15, 2021 IDA-42120 Loan Repay 2,637,963.50
Sep 15, 2021 IDA-42120 Int Charges 305,338.03
Sep 15, 2021 IDA-42120 Int Charges 305,338.03
Sep 15, 2021 IDA-42120 Loan Repay 13,957.07
Jun 29, 2006 IDA-42120 Loan Commitment 135,000,000.00
Mar 15, 2024 IDA-42120 Int Charges 241,445.62
Mar 15, 2024 IDA-42120 Int Charges 241,445.62
Mar 15, 2024 IDA-42120 Loan Repay 2,403,068.20
Mar 15, 2024 IDA-42120 Loan Repay 73,297.42
Jul 31, 2013 IDA-42120 Loan Disb 1,491,440.00
Aug 12, 2013 IDA-42120 Loan Disb 27,666.47
Jun 25, 2013 IDA-42120 Loan Disb -613,403.00
Nov 3, 2014 IDA-42120 Loan Disb 5,000.00
Oct 6, 2014 IDA-42120 Loan Disb -6,125.01
Oct 2, 2014 IDA-42120 Loan Disb 798,366.00
Nov 5, 2014 IDA-42120 Loan Disb 193,190.02
Nov 5, 2014 IDA-42120 Loan Disb 151,875.00
Nov 10, 2014 IDA-42120 Loan Disb 2,148,093.00
Dec 13, 2013 IDA-42120 Loan Disb 342,652.00
Dec 4, 2013 IDA-42120 Loan Disb 56,462.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2014-07-01
Project Management Satisfactory 2014-07-01
Financial Management Satisfactory 2014-07-01
Overall Implementation Progress (IP) Moderately Satisfactory 2014-07-01
Progress towards achievement of PDO Moderately Unsatisfactory 2014-07-01
Overall Safeguards Rating Moderately Satisfactory 2014-07-01
Procurement Satisfactory 2014-07-01
Monitoring and Evaluation Moderately Satisfactory 2014-07-01
Overall Moderately Ineffective 2014-07-01
Overall Safeguards Rating Moderately Satisfactory 2014-07-01

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-11-2014
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-27-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved capacity both at SCRB and KRG-GDRB measured by the development of road asset management tools and their effective use.ValueNo established road asset management systems at SCRoad Asset Management has been developed for KRG-Gcompleted
    DateJune 6, 2006May 27, 2014June 30, 2014
    CommentAsset management has been developed for the rural roads project in KRG.Asset management has been developed for the rural roads project in KRG.Asset management development is ongoing for SCRBAsset management has been developed for the rural roads project in KRG.
  • % of population in the targeted villages with access to an all-weather road.Value0%100% of targetted villages100%
    DateJune 6, 2006May 27, 2014June 30, 2014
    CommentPercent of population in the targeted villages have access to an all-weather road.Percent of population in the targeted villages have access to an all-weather road.Percent of population in the targeted villages have access to an all-weather road.
  • Average reduction in travel time for villagers to reach markets/services.Value0%30%50%
    DateJune 6, 2006June 17, 2014June 30, 2014
    Commentreduction in travel time.Travel time reduction was measured only for Altun-Kopri road . It is 30% reduction ( from 60 min to 40 min). Travel time reductionwill be measured for other roads during ICR preparation.travel time reduced by 50%

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Bridge replacements.Value034
    DateJune 6, 2006May 27, 2014June 30, 2014
    CommentOld decaying floating bridges in place.3 completed 1 under constructionAt least three bridges improved on critical road sections.
  • Road asset management.ValueNo road maintenance and management strategies. No 1Maintenance management capacities are satisfactory
    DateJune 6, 2006May 27, 2014June 30, 2014
    CommentCompleted for GDRBOngoing for SCRB
  • Transport Sector Master PlanValueNoNoYes
    DateJanuary 1, 2012May 27, 2014June 30, 2014
    CommentTransport Sector Master PlanTransport Sector Master Plan under implementationTransport Sector Master Plan completed
  • Roads rehabilitated, Non-ruralValue0.00174.50268.50
    DateJune 6, 2006May 27, 2014June 30, 2014
    CommentNo. of km of rehabilitated non-rural roadsNo. of km of rehabilitated non-rural roadsNo. of km of rehabilitated non-rural roads
  • Roads rehabilitated, RuralValue0.00121.50115.00
    DateJune 6, 2006May 27, 2014June 30, 2014
    CommentNo. of km of rural roads rehabilitated.The target of rural roads rehabilitated have been exceeded by 6.5 km.No. of km of rural roads rehabilitated.
  • Local Employment CreatedValue0310,000No Target
    DateDecember 6, 2006May 28, 2014June 30, 2014
    CommentNo. of temporary employment generatedNo. of temporary employment generatedNo. of temporary employment generated
  • Direct project beneficiariesValue0.00300000.000.00
    DateMay 27, 2014
    Commentmeasured as population with improved access due to the project in Central and Southern Governorates only.
  • PART A ( Central and Southern Governorates)Value0.00136.00230.00
    DateDecember 6, 2006May 27, 2014June 30, 2014
    CommentNo. of Km of roads rehabilitated15 additional km are expected to be completed by end of June 2014No. of Km of roads rehabilitated
  • PART B ( North Governorates, KRG)Value0.0038.5038.50
    DateDecember 6, 2006May 27, 2014June 30, 2014
    CommentNo. of Km of roads rehabilitatedWorks completed and road open to trafficWorks completed and road open to traffic
  • PART A ( Central and Southern Governorates)Value0.0040.0040.00
    DateJune 6, 2006December 11, 2013June 30, 2014
    CommentNo. of km of rural roads rehabilitated40 km of rural roads rehabilitated open to trafficNo. of km of rural roads rehabilitated open to traffic
  • PART B ( Northern Governorates, KRG)Value0.0081.5075.00
    DateDecember 6, 2006May 27, 2014June 30, 2014
    CommentNo. of km of rural roads rehabilitated open to trafficTarget has been exceeded by 6.5 km.No. of km of rural roads rehabilitated open to traffic
  • PART A ( Central and Southern Governorates)Value0
    DateJune 1, 2013
    Comment
  • PART B ( Northern Governorates, KRG)Value0
    DateJune 1, 2013
    Comment
  • Female beneficiariesValue0.0050.000.00