Skip to Main Navigation

AF: Urban Water Sector Project

Development Objective

The objective of the restructured project is to assist the Recipient to develop the capacity of the AUWSSC for operational management and investment planning and implementation.

Key Details

Project Details

  • P087860

  • Closed

  • Deepali Tewari

  • N/A

  • Afghanistan

  • February 17, 2006

  • (as of board presentation)

    May 25, 2006

  • December 27, 2006

  • US$ 18.00 million

  • B

  • Not Applicable

  • June 30, 2014

  • BANK APPROVED

  • May 1, 2015

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 18.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 18.00
IBRD + IDA Commitment 18.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 18.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 25, 2006 IDA-H2250 Loan Commitment 40,000,000.00
Jul 9, 2014 IDA-H2250 Loan Disb 1,657,506.20
Jun 2, 2014 IDA-H2250 Loan Disb 367,725.44
May 29, 2014 IDA-H2250 Loan Disb 340,844.80
Jun 4, 2014 IDA-H2250 Loan Disb 169,729.05
Jun 2, 2014 IDA-H2250 Loan Disb 245,148.31
Jun 24, 2014 IDA-H2250 Loan Disb 1,349,640.50
Jun 24, 2014 IDA-H2250 Loan Disb 927,514.25
May 13, 2014 IDA-H2250 Loan Disb 1,309,718.80
May 12, 2014 IDA-H2250 Loan Disb 244,409.20
May 21, 2014 IDA-H2250 Loan Disb 397,233.00
Dec 11, 2013 IDA-H2250 Loan Disb 490,301.00
Apr 2, 2014 IDA-H2250 Loan Disb 216,403.50
Dec 2, 2013 IDA-H2250 Loan Disb 215,506.75
Feb 18, 2014 IDA-H2250 Loan Disb 193,699.42
Dec 30, 2013 IDA-H2250 Loan Disb 977,903.90
Dec 30, 2013 IDA-H2250 Loan Disb 612,876.25
Sep 24, 2013 IDA-H2250 Loan Disb 323,632.72
Jan 7, 2015 IDA-H2250 Loan Disb -213,198.05
Jan 7, 2015 IDA-H2250 Loan Cancel 512,868.12
Nov 12, 2014 IDA-H2250 Loan Disb 707,150.00
Oct 29, 2014 IDA-H2250 Loan Disb 226,062.60
Sep 17, 2014 IDA-H2250 Loan Disb 654,140.94
Dec 29, 2014 IDA-H2250 Loan Disb 146,645.81
Jun 23, 2014 IDA-H2250 Loan Disb 341,526.97
Jun 25, 2014 IDA-H2250 Loan Disb 567,629.06

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2014-06-30
Counterpart Funding Satisfactory 2014-06-30
Overall Implementation Progress (IP) Moderately Satisfactory 2014-06-30
Progress towards achievement of PDO Moderately Satisfactory 2014-06-30
Financial Management Moderately Satisfactory 2014-06-30
Monitoring and Evaluation Moderately Satisfactory 2014-06-30
Project Management Moderately Satisfactory 2014-06-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-24-2014
OutcomesModerately Satisfactory
Risk to Development OutcomeHigh
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-09-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of water utilities that the project is supportingValue1.001.001.00
    DateOctober 10, 2011October 15, 2013June 30, 2014
    CommentAfter restructuring of the project in 2011, AUWSSC, the only urban water utility in Afg which is being supported by the project.Its creation was approved through a Presidential decree in 2006, and the articles of incorporation approved by the Cabinet andpublished in the Official Gazette in 2007. AUWSSC was officially incorporated and registered with the Afghanistan InvestmentSupport Agency on 11 Aug2007. Upon its creation, it assumed operations in 16 towns.Since corporatization, AUWSSC's operations have expanded from 14 towns to 32 towns between 2010 and 2012, and AUWSSC is currentlyoperating in 42 towns through its six Strategic Business Units (SBUs) and sub-SBUs.The target, to support AUWSSC has already been achieved.
  • AUWSSC is fully corporatized and took over operations in urban areas.Value000000000000000000000000
    DateOctober 10, 2011
    CommentPresidential Decree to create AUWSSC was signed on Jan 25, 2006.
  • Number of household connections in Kabul provided by small scale local providersValue200.00312200.00500.00
    DateOctober 10, 2011June 15, 2015June 30, 2014
    CommentThis baseline number was arbitrary as there was little information available - the Min of Urb Dev is responsible for issuinglicenses to private operators.A study completed by AImplementation of one community water scheme in Kabul by AUWSSC financed from this project are expected toaugment the water supply for 1000 connections with the potential to increase the number of connection by 300. Implementation of asecond scheme planned had to be dropped due to delays in procurement.No end target was established, as only a study financed by AuSAid was in the work plan. The procurement plan was amended inDecember 2013 to include implementation of a community water augmentation scheme - this is under implementation.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average per connection collections per yearValue1179.001822.000.00
    DateOctober 1, 2010June 15, 2015June 30, 2014
    Comment142,691 connections were provided by AUWSSC and AFA 228.4 million revenues earned in SY1390 (2011). The average revenue perconnection at the end of 2011 was Afs 1179. - Afs1822.No new data since last ISR.No end target was established, as multiple donors are investing in capital works that they will execute themselves, and thetimeline of these investments was unpredictable
  • Financial statements of AUWSSC is produced and auditedValueYesYesYes
    DateOctober 1, 2010June 15, 2015June 30, 2014
    CommentAt the time of project restructuring, corporate financial statements prepared by another donor, could not be certified by thedonorfor audit, and had to be re-done. AUWSSC then re-prepared the Corporate Financial Statements for 1388 (2009) and 1389 (2010).Auditsof these were completed mid year 2012.Corporate financial statements for AUWSSC have been prepared for 2011 and 2012 and are being audited. There has been a delay intheaudits, due to a delay in the appointment of the external auditor.Verification of expenditures has been completed by the auditors for 2011, 2012, and 2013. This verification was on the criticalpath of disbursements and the auditors contract was amended to bring the verification forward for the years in question, with thepreparation of reports to follow. The audit reports will therefore be now done in due course.
  • Accounts ReceivableValue3.503.002.00
    DateOctober 1, 2010October 15, 2013June 17, 2014
    CommentNo progress since the previous ISR. Target will not be met.During the closing mission, data was used to compute the progress AUWSSC has made in terms of the revenues owed to it divided bythe revenues for the year, multiplied by 12 months to get the number of months for which revenues were outstanding in any givenyear. In 2009, it was 7.4 months, 2010 7.3 months, 2011 it was 7.19 months, and 2012 it was 4.48 months - highlighting a consistentimprovement in the Accounts Receivable.
  • Working ratioValue1.171.001.00
    DateOctober 1, 2010October 15, 2013June 17, 2014
    Comment
  • Average per connection collectionValue988.000.000.00
    DateOctober 1, 2010October 15, 2013June 17, 2014
    Comment
  • Percentage of samples tested meeting residual chlorine standardsValue0.0080.000.00
    DateOctober 1, 2010June 15, 2014June 30, 2014
    CommentData was available for the number of water quality samples tested in 2009 (668 samples), 2010 (668 samples), and 2011 (533samples.All SBUs except Kandahar undertook sample tests and a total of 1869 tests were undertaken over this period. However, nodata is available on the percentage of this sample that met residual chlorine standards.Procurement of chlorine included in the revised procurement plan had to be dropped due to delays. In addition the Grant funds are100% committed.No end target was established.