Emergency School Construction and Rehabilitation Project

Development Objective

The revised objective of the project is to improve conditions of learning of students in primary and scondary schools in Iraq through the construction of new schools, the extension of existing schools, and the rehabilitation of schools in need of urgent repair.

Key Details

Project Details

  • P087907

  • Closed

  • Amira Mohamed Ibrahim Kazem

  • N/A

  • Iraq

  • October 8, 2004

  • (as of board presentation)

    October 8, 2004

  • October 14, 2004

  • US$ 60.00 million

  • B

  • Not Applicable

  • June 30, 2013

  • BANK APPROVED

  • July 16, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Iraq Reconstruction Trust Fund 60.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 60.00
Total Project Cost** 60.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2013-08-14
Procurement Satisfactory 2013-08-14
Monitoring and Evaluation Moderately Satisfactory 2013-08-14
Overall Implementation Progress (IP) Moderately Satisfactory 2013-08-14
Progress towards achievement of PDO Moderately Satisfactory 2013-08-14
Financial Management Moderately Satisfactory 2013-08-14
Counterpart Funding Satisfactory 2013-08-14

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-17-2013
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-14-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of students benefiting from improved conditions of learning in new school buildingsValue0.0028231.0023040.00
    DateOctober 24, 2004June 30, 2013June 30, 2013
    Comment
  • Number of students benefiting from improved learning conditions in additions of six-classroom blocks (incl. toilets) in 20 Baghdad schools.Value0.003329.004800.00
    DateJuly 20, 2010June 30, 2013June 30, 2013
    Comment
  • Number of students benefiting from improved conditions in learning in rehabilitated schoolsValue0.0082193.0044848.00
    DateOctober 24, 2004June 30, 2013June 30, 2013
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of schools rehabilitatedValue0.00133.00133.00
    DateOctober 24, 2004June 30, 2013June 30, 2013
    Comment
  • Number of new schools completedValue0.0048.0048.00
    DateOctober 24, 2004June 30, 2013June 30, 2013
    Comment
  • Number of additions built (6-classroom blocks incl. toilets)Value0.0018.0020.00
    DateJuly 20, 2010June 30, 2013June 30, 2013
    Comment