Financier | Commitments |
---|---|
Iraq Reconstruction Trust Fund | 60.00 |
P087907
Closed
Amira Mohamed Ibrahim Kazem
N/A
Iraq
October 8, 2004
(as of board presentation)
October 8, 2004
October 14, 2004
US$ 60.00 million
N/A
2005
US$ 60.00 million
B
Not Applicable
June 30, 2013
BANK APPROVED
July 16, 2024
Financier | Commitments |
---|---|
Iraq Reconstruction Trust Fund | 60.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 60.00 |
Total Project Cost** | 60.00 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2013-08-14 |
Procurement | Satisfactory | 2013-08-14 |
Monitoring and Evaluation | Moderately Satisfactory | 2013-08-14 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2013-08-14 |
Progress towards achievement of PDO | Moderately Satisfactory | 2013-08-14 |
Financial Management | Moderately Satisfactory | 2013-08-14 |
Counterpart Funding | Satisfactory | 2013-08-14 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-17-2013 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 04-14-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of students benefiting from improved conditions of learning in new school buildings | Value | 0.00 | 28231.00 | 23040.00 |
Date | October 24, 2004 | June 30, 2013 | June 30, 2013 | |
Comment |
Number of students benefiting from improved learning conditions in additions of six-classroom blocks (incl. toilets) in 20 Baghdad schools. | Value | 0.00 | 3329.00 | 4800.00 |
Date | July 20, 2010 | June 30, 2013 | June 30, 2013 | |
Comment |
Number of students benefiting from improved conditions in learning in rehabilitated schools | Value | 0.00 | 82193.00 | 44848.00 |
Date | October 24, 2004 | June 30, 2013 | June 30, 2013 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of schools rehabilitated | Value | 0.00 | 133.00 | 133.00 |
Date | October 24, 2004 | June 30, 2013 | June 30, 2013 | |
Comment |
Number of new schools completed | Value | 0.00 | 48.00 | 48.00 |
Date | October 24, 2004 | June 30, 2013 | June 30, 2013 | |
Comment |
Number of additions built (6-classroom blocks incl. toilets) | Value | 0.00 | 18.00 | 20.00 |
Date | July 20, 2010 | June 30, 2013 | June 30, 2013 | |
Comment |