Biodiversity Conservation and Rural Livelihoods Improvement

Abstract*

The objective of the Biodiversity Conservation and Rural Livelihoods Improvement Project for India is to develop and promote new models of conservation at the landscape scale through enhanced capacity and institution building for mainstreaming biodiversity conservation outcomes. There are four components to the project. The first component of the project is demonstration of landscape conservation approaches in two pilot sites: this component will...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To develop and promote new models of conservation at the landscape scale1 through enhanced capacity and institution building for mainstreaming biodiversity conservation outcomes. Achieving this objective would involve the demonstration and scaling up of landscape conservation approaches. This would specifically involve tools and techniques improvements, and knowledge and capacity building tosupport multi-stakeholder partnerships to mainstream biodiversity conservation. It would also involve improving rural livelihoods, enhancing learning, and replicating successful participatory conservation models at the landscape scale.

Key Details

Project Details

  • P088520

  • Closed

  • Anupam Joshi , Jiang Ru

  • Ministry of Environment and Forests

  • India

  • July 22, 2004

  • (as of board presentation)

    May 17, 2011

  • July 13, 2011

  • US$ 22.88 million

  • Wildlife Institute of India,Gir Lion Society,KMTR Tiger Foundation,Satpura Tiger Foundation Madhya Pradesh,Periyar Tiger Foundation,BCRLIP Landscape Society LRK,Satpura Tiger Foundation Maharashtra,BCRLIP Landscape Society Askot

  • South Asia

  • 2011

  • US$ 15.36 million

  • B

  • July 8, 2024

  • March 31, 2018

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Communities 0.93
IDA Credit 15.36
Borrower/Recipient 6.59

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 15.36
IBRD + IDA Commitment 15.36
Lending Instrument
Grant Amount N/A
Total Project Cost** 22.88

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 15, 2019 IDA-49430 Loan Repay 28,749.35
Apr 15, 2019 IDA-49430 Int Charges 3,671.00
Apr 15, 2019 IDA-49430 Int Charges 3,671.00
Apr 15, 2019 IDA-49430 Int Charges 3,587.46
Apr 15, 2019 IDA-49430 Int Charges 3,587.46
Oct 15, 2018 IDA-49430 Int Charges 2,169.74
Oct 15, 2018 IDA-49430 Int Charges 2,169.74
Oct 15, 2018 IDA-49430 Loan Repay 1,048.65
Oct 15, 2018 IDA-49430 Int Charges 140.96
Oct 15, 2018 IDA-49430 Int Charges 140.96
Oct 15, 2018 IDA-49430 Loan Disb -223,883.77
Oct 15, 2018 IDA-49430 Loan Repay 328,713.40
Oct 15, 2018 IDA-49430 Loan Repay 12,711.18
Apr 15, 2022 IDA-49430 Int Charges 3,337.16
Apr 15, 2022 IDA-49430 Int Charges 3,337.16
Apr 15, 2022 IDA-49430 Loan Repay 108.56
Apr 15, 2022 IDA-49430 Loan Repay 14,016.87
Oct 15, 2021 IDA-49430 Int Charges 3,502.96
Oct 15, 2021 IDA-49430 Int Charges 3,502.96
Oct 15, 2021 IDA-49430 Loan Repay 30.19
Oct 15, 2021 IDA-49430 Loan Repay 14,565.41
Apr 15, 2021 IDA-49430 Int Charges 4.61
Apr 15, 2021 IDA-49430 Int Charges 4.61
Apr 15, 2021 IDA-49430 Int Charges 3,544.44
Apr 15, 2021 IDA-49430 Int Charges 3,544.44
Oct 15, 2020 IDA-49430 Int Charges 20.90
Oct 15, 2020 IDA-49430 Int Charges 20.90
Oct 15, 2020 IDA-49430 Int Charges 3,476.60
Oct 15, 2020 IDA-49430 Int Charges 3,476.60
Apr 15, 2020 IDA-49430 Loan Repay 74.14
May 17, 2011 IDA-49430 Loan Commitment 15,360,000.00
Apr 15, 2024 IDA-49430 Loan Repay 520.74
Apr 15, 2024 IDA-49430 Loan Repay 26,695.73
Apr 15, 2024 IDA-49430 Int Charges 2,857.73
Apr 15, 2024 IDA-49430 Int Charges 2,857.73
Oct 15, 2023 IDA-49430 Int Charges 382.78
Oct 15, 2023 IDA-49430 Int Charges 382.78
Oct 15, 2023 IDA-49430 Loan Repay 27,083.12
Oct 15, 2023 IDA-49430 Int Charges 2,945.28
Oct 15, 2023 IDA-49430 Int Charges 2,945.28
Apr 15, 2023 IDA-49430 Loan Repay 1,012.94
Apr 15, 2023 IDA-49430 Loan Repay 26,993.75
Apr 15, 2023 IDA-49430 Int Charges 2,754.88
Apr 15, 2023 IDA-49430 Int Charges 2,754.88
Oct 15, 2022 IDA-49430 Loan Repay 440.14
Oct 15, 2022 IDA-49430 Loan Repay 25,952.01
Oct 15, 2022 IDA-49430 Int Charges 3,068.12
Oct 15, 2022 IDA-49430 Int Charges 3,068.12
Apr 15, 2014 IDA-49430 Int Charges 45.88
Apr 15, 2014 IDA-49430 Int Charges 45.88
Apr 15, 2014 IDA-49430 Int Charges 6,593.52
Apr 15, 2014 IDA-49430 Int Charges 6,593.52
Oct 15, 2013 IDA-49430 Int Charges 70.69
Oct 15, 2013 IDA-49430 Int Charges 70.69
Oct 15, 2013 IDA-49430 Int Charges 5,729.33
Oct 15, 2013 IDA-49430 Int Charges 5,729.33
Jan 6, 2014 IDA-49430 Loan Disb 56,912.99
Aug 7, 2013 IDA-49430 Loan Disb 242,792.83
Oct 15, 2014 IDA-49430 Int Charges 6,618.52
Oct 15, 2014 IDA-49430 Int Charges 6,618.52
Oct 15, 2014 IDA-49430 Int Charges 20.39
Oct 15, 2014 IDA-49430 Int Charges 20.39
Oct 15, 2016 IDA-49430 Loan Repay 337,766.80
Oct 15, 2016 IDA-49430 Int Charges 8,440.86
Oct 15, 2016 IDA-49430 Int Charges 8,440.86
Oct 15, 2016 IDA-49430 Int Charges 119.46
Oct 15, 2016 IDA-49430 Int Charges 119.46
May 25, 2016 IDA-49430 Loan Disb 41,410.80
Mar 14, 2016 IDA-49430 Loan Disb 189,179.98
Apr 15, 2016 IDA-49430 Int Charges 189.43
Apr 15, 2016 IDA-49430 Int Charges 189.43
Apr 15, 2016 IDA-49430 Int Charges 7,514.55
Apr 15, 2016 IDA-49430 Int Charges 7,514.55
Jan 8, 2016 IDA-49430 Loan Disb 3,801.70
Oct 15, 2015 IDA-49430 Int Charges 6,728.97
Oct 15, 2015 IDA-49430 Int Charges 6,728.97
Oct 15, 2015 IDA-49430 Int Charges 157.03
Oct 15, 2015 IDA-49430 Int Charges 157.03
Aug 10, 2015 IDA-49430 Loan Disb 92,624.01
Apr 15, 2015 IDA-49430 Int Charges 199.98
Apr 15, 2015 IDA-49430 Int Charges 199.98
Apr 15, 2015 IDA-49430 Int Charges 6,013.84
Apr 15, 2015 IDA-49430 Int Charges 6,013.84
Mar 31, 2015 IDA-49430 Loan Disb 115,845.89
Aug 19, 2015 IDA-49430 Loan Disb 102,305.77
Jun 17, 2014 IDA-49430 Loan Disb 49,954.00
Apr 4, 2014 IDA-49430 Loan Disb 19,041.00
Oct 15, 2018 IDA-49430 Loan Cancel 10,975,025.00
Apr 15, 2018 IDA-49430 Int Charges 1,922.00
Apr 15, 2018 IDA-49430 Int Charges 1,922.00
Apr 15, 2018 IDA-49430 Loan Repay 356,332.90
Apr 15, 2018 IDA-49430 Int Charges 7,492.82
Apr 15, 2018 IDA-49430 Int Charges 7,492.82
Oct 15, 2017 IDA-49430 Loan Repay 346,618.66
Oct 15, 2017 IDA-49430 Int Charges 6,170.46
Oct 15, 2017 IDA-49430 Int Charges 6,170.46
Oct 15, 2017 IDA-49430 Int Charges 2,299.51
Oct 15, 2017 IDA-49430 Int Charges 2,299.51
Apr 15, 2017 IDA-49430 Loan Repay 328,601.60
Apr 15, 2017 IDA-49430 Loan Repay 4,252.97
Jun 6, 2017 IDA-49430 Loan Disb 223,883.75
Jun 7, 2017 IDA-49430 Loan Disb 276,429.97
Mar 27, 2017 IDA-49430 Loan Disb 93,747.00
Apr 15, 2017 IDA-49430 Int Charges 5,128.00
Apr 15, 2017 IDA-49430 Int Charges 5,128.00
Jun 29, 2016 IDA-49430 Loan Disb 112,613.00
Nov 18, 2016 IDA-49430 Loan Disb 9,446.00
Apr 15, 2020 IDA-49430 Int Charges 1,217.18
Apr 15, 2020 IDA-49430 Int Charges 1,217.18
Apr 15, 2020 IDA-49430 Loan Repay 28,181.07
Apr 15, 2020 IDA-49430 Int Charges 0.59
Apr 15, 2020 IDA-49430 Int Charges 0.59
Apr 15, 2020 IDA-49430 Int Charges 2,279.40
Apr 15, 2020 IDA-49430 Int Charges 2,279.40
Oct 16, 2019 IDA-49430 Int Charges 100.89
Oct 16, 2019 IDA-49430 Int Charges 100.89
Oct 16, 2019 IDA-49430 Loan Repay 28,350.52
Oct 16, 2019 IDA-49430 Int Charges 3,614.67
Oct 16, 2019 IDA-49430 Int Charges 3,614.67

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Moderately Unsatisfactory 2018-03-29
Project Management Unsatisfactory 2018-03-29
Procurement Unsatisfactory 2018-03-29
Financial Management Unsatisfactory 2018-03-29
Progress towards achievement of PDO Moderately Unsatisfactory 2018-03-29
Overall Implementation Progress (IP) Unsatisfactory 2018-03-29
Monitoring and Evaluation Unsatisfactory 2018-03-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-26-2018
OutcomesModerately Unsatisfactory
Risk to Development Outcome
Bank PerformanceModerately Unsatisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-14-2019PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Landscape conservation approach successfully adopted in two landscape sitesValue0.004.004.00
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • Institutional and methodological framework and guidelines for landscape conservation approaches developed and tested in high biodiversity landscapesValueNo framework for landscapeconservation existsFormal approval of guidelines and procedures by MOFramework under consultation for finalization
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • Forest area brought under management plansValue300000.00600000.00600000.00
    DateDecember 10, 2012March 31, 2018March 16, 2018
    Comment
  • Governmentt institutions provided with capacity building to improve management of forest resourcesValue0.006.006.00
    DateDecember 10, 2012March 31, 2018March 16, 2018
    Comment
  • Areas brought under enhanced biodiversity protection (ha)Value0.00500000.00550000.00
    DateDecember 10, 2012March 31, 2018March 16, 2018
    Comment
  • Population of key indicator species/umbrella species stable or improving within PAsValueNo regular surveys of key indicator species, excepRegular monitoring to assess population statusRegular monitoring of key indicator species undert
    DateDecember 10, 2012March 31, 2018March 16, 2018
    Comment
  • At least 600,000 hectares within landscapes more effectively managed for conservation outcomesValue300000.00600000.00600000.00
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • At least 50,000 ha of targeted production areas outside PAs managed for conservation outcomesValue0.0050000.0050000.00
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • Direct project beneficiariesValue0.005000.0025000.00
    DateDecember 10, 2012March 31, 2018March 16, 2018
    Comment
  • At least two protected areas covering 550,000 hectares with strengthened management and protection (40% increase in management effectiveness)Value0.0040.0020.00
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • At least 20% of target user groups adopt alternate and/or sustainable resource use practicesValue0.0020.0010.00
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • Key stakeholders from at least five national priority landscapes trained in landscape conservation approachesValue0.00250.001000.00
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • New areas outside protected areas managed as biodiversity-friendly (ha)Value0.0050000.0050000.00
    DateDecember 10, 2012March 31, 2018March 16, 2018
    Comment
  • National curriculum for landscape conservation developed and training institutionalized through five new annual training coursesValue0.005.005.00
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • At least 10 new documents on good practice prepared and knowledge dissemination events sponsoredValueA number of good practice notes from previous proj+10 new dissemination notes15
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • Adoption of landscape management approaches in two additional sites with project fundingValue0.002.002.00
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • At least 75% of targeted villages or user groups completed and successfully implementing micro-plans with conservation benefitsValue020% increase in incomes for VPs/user groups where Income increases reported for limited beneficiarie
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • At least 20% of targeted populations in landscapes have improved cash or non-cash improved incomes from project-supported interventionsValueCurrent baselines vary depending on source of inco10% increase in incomes for VPs/user groups where Income increases not measured and cannot be varifi
    DateDecember 10, 2012March 31, 2018March 16, 2018
    Comment
  • Adoption of landscape management approaches or specific elements of it in three additional sites with GOI fundingValue0Landscape conservation funded by GOI in 3 or more In 3 landscapes from State Government budget
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • Effective and well-staffed national coordination unit within MOEF actively supporting landscape approachesValue0.0011.005.00
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • On time completion of key project outputs against implementation planValueWeak capacityBi-annual progress reports, annual work plans apprConsolidated bi annual progress reports not submit
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • Design of landscape sites for Component 3Value0Landscape activities initiatedThis indicator was achieved as landscape activitie
    DateJuly 13, 2011March 31, 2018March 16, 2018
    Comment
  • Female beneficiariesValue0.002500.0014000.00
    DateDecember 10, 2012March 31, 2018March 16, 2018
    Comment