Financier | Commitments |
---|---|
PROTOTYPE CARBON FUND | 0.30 |
Borrower/Recipient | 10.70 |
P088752
Closed
Sebastian Martin Scholz
N/A
October 27, 2004
(as of board presentation)
June 30, 2005
July 28, 2005
US$ 11.00 million
N/A
2005
US$ 0.30 million
B
Not Applicable
December 31, 2016
BANK APPROVED
December 19, 2024
Financier | Commitments |
---|---|
PROTOTYPE CARBON FUND | 0.30 |
Borrower/Recipient | 10.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 0.30 |
Total Project Cost** | 11.00 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2011-06-20 |
Monitoring and Evaluation | Unsatisfactory | 2011-06-20 |
Progress towards achievement of PDO | Highly Unsatisfactory | 2011-06-20 |
Counterpart Funding | Highly Unsatisfactory | 2011-06-20 |
Project Management | Unsatisfactory | 2011-06-20 |
Financial Management | Satisfactory | 2011-06-20 |
Overall Implementation Progress (IP) | Highly Unsatisfactory | 2011-06-20 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Greenhouse gas (GHG) emissions reductions of about 39 kton CO2eq/year, average over the period 2007-2020, are achieved at the plant, starting in 2007; | Value | Treatment plant has not been modernized. | Project significantly delayed, which led to closur | Treatment plant in operation. Project supposed to |
Date | April 28, 2006 | May 23, 2011 | December 31, 2009 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Achievement of commissioning | Value | No | No | Yes |
Date | April 28, 2006 | May 23, 2011 | May 31, 2009 | |
Comment | commissioning not achieved | commissioning has not been achieved yet; significant delays led to project closure. | commissioning achieved, plant operating |