Financier | Commitments |
---|---|
PROTOTYPE CARBON FUND | 0.54 |
P088934
Closed
Sebastian Martin Scholz
N/A
November 10, 2004
(as of board presentation)
December 7, 2004
January 1, 2006
US$ 0.54 million
Municipality of Olavarria
2005
US$ 0.54 million
B
Not Applicable
December 31, 2015
BANK APPROVED
December 19, 2024
Financier | Commitments |
---|---|
PROTOTYPE CARBON FUND | 0.54 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 0.54 |
Total Project Cost** | 0.54 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2011-06-25 |
Progress towards achievement of PDO | Highly Unsatisfactory | 2011-06-25 |
Procurement | Satisfactory | 2011-06-25 |
Monitoring and Evaluation | Highly Unsatisfactory | 2011-06-25 |
Overall Implementation Progress (IP) | Highly Unsatisfactory | 2011-06-25 |
Counterpart Funding | Satisfactory | 2011-06-25 |
Project Management | Highly Unsatisfactory | 2011-06-25 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Emission Reductions | Value | 0.00 | 0.00 | 131000.00 |
Date | July 1, 2005 | June 14, 2010 | June 30, 2015 | |
Comment | The project did not undertake initial verification of ERs. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Yearly Emissions Reductions | Value | 0.00 | 0.00 | 16776.00 |
Date | July 1, 2005 | June 14, 2010 | December 31, 2014 | |
Comment | The project did not undertake initial verification of ERs. |