Olavarria Landfill Gas Recovery Project

Abstract*

The Argentina Olavarria Landfill Gas Recovery Project helps mitigate climate change by financing the improvement of municipal solid waste management practice in the municipality of Olavarria and strengthening its commercial viability by leveraging additional revenue from carbon finance at the local landfill. To achieve these objectives, the project will capture and destroy methane currently generated at the landfill (Component 1). The project will...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project aims to capture and destroy the landfill gas (LFG) accumulating at the municipal landfill of the town of Olavarría through recovery and flaring. An active collection system will be installed at the landfill that will consist of gas extraction wells, collection piping, mechanical blowers, LFG condensate and flare systems, as well as a monitoring and control system. The resulting reductions in LFG emissions will be monitored, verified, certified, and sold as ERs to the CDCF administered by the World Bank. Part of the income from the sales of ERs will be used by the Municipality of Olavarría to install a safe and reliable distribution system for potable water in the rural village of Espigas, 80 km from Olavarría, as well as solar water heating systems in two local schools.

Key Details

Project Details

  • P088934

  • Closed

  • Sebastian Martin Scholz

  • N/A

  • Argentina

  • November 10, 2004

  • (as of board presentation)

    December 7, 2004

  • January 1, 2006

  • US$ 0.54 million

  • B

  • Not Applicable

  • December 31, 2015

  • BANK APPROVED

  • December 19, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
PROTOTYPE CARBON FUND 0.54

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 0.54
Total Project Cost** 0.54

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2011-06-25
Progress towards achievement of PDO Highly Unsatisfactory 2011-06-25
Procurement Satisfactory 2011-06-25
Monitoring and Evaluation Highly Unsatisfactory 2011-06-25
Overall Implementation Progress (IP) Highly Unsatisfactory 2011-06-25
Counterpart Funding Satisfactory 2011-06-25
Project Management Highly Unsatisfactory 2011-06-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Emission ReductionsValue0.000.00131000.00
    DateJuly 1, 2005June 14, 2010June 30, 2015
    CommentThe project did not undertake initial verification of ERs.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Yearly Emissions ReductionsValue0.000.0016776.00
    DateJuly 1, 2005June 14, 2010December 31, 2014
    CommentThe project did not undertake initial verification of ERs.