Guangxi Integrated Forestry Development and Conservation Project

Abstract*

The overall project development objective of the Guangxi Integrated Forestry Development and Conservation Project is to improve the effectiveness of forest management and institutional arrangements in timber production, watershed protection and nature reserves management in selected areas of the Guangxi Zhuang Autonomous Region (GZAR). The global development objective of the project is to improve the conservation of the globally significant biodiversity...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The overall project development objective is to improve the effectiveness of forest management and institutional arrangements in timber production, watershed protection and nature reserves management in selected areas of the Guangxi Zhuang Autonomous Region (GZAR).

Key Details

Project Details

  • P088964

  • Closed

  • Jin Liu

  • N/A

  • China

  • September 24, 2004

  • (as of board presentation)

    December 14, 2006

  • April 30, 2007

  • US$ 197.58 million

  • Guangxi Regional Forestry Department

  • East Asia and Pacific

  • 2007

  • US$ 100.00 million

  • B

  • N/A

  • April 30, 2020

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Sources of Borrowing Country 32.33
Borrower/Recipient 30.02
Local Farmer Organizations 35.23
International Bank for Reconstruction and Development 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 100.00
IDA Commitment N/A
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 197.58

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 15, 2016 IBRD-48440 Int Charges 499,805.88
Jul 15, 2016 IBRD-48440 Loan Repay 2,690,000.00
Jan 15, 2016 IBRD-48440 Int Charges 342,035.53
Jan 15, 2016 IBRD-48440 Loan Repay 2,615,000.00
Jul 15, 2015 IBRD-48440 Int Charges 294,674.03
Jul 15, 2015 IBRD-48440 Loan Repay 2,540,000.00
Jan 15, 2017 IBRD-48440 Int Charges 552,593.44
Jan 15, 2017 IBRD-48440 Loan Repay 2,765,000.00
Jan 15, 2018 IBRD-48440 Loan Repay 2,930,000.00
Jul 15, 2017 IBRD-48440 Int Charges 668,799.00
Jul 15, 2017 IBRD-48440 Loan Repay 2,845,000.00
Jul 15, 2019 IBRD-48440 Loan Repay 3,190,000.00
Jan 15, 2019 IBRD-48440 Int Charges 1,020,776.00
Jan 15, 2019 IBRD-48440 Loan Repay 3,100,000.00
Jul 15, 2018 IBRD-48440 Int Charges 817,746.20
Jul 15, 2018 IBRD-48440 Loan Repay 3,010,000.00
Jan 15, 2018 IBRD-48440 Int Charges 706,337.60
Jan 15, 2020 IBRD-48440 Int Charges 831,876.50
Jan 15, 2020 IBRD-48440 Loan Repay 3,280,000.00
Jul 15, 2019 IBRD-48440 Int Charges 1,072,818.40
Jul 15, 2021 IBRD-48440 Int Charges 192,488.48
Jul 15, 2021 IBRD-48440 Loan Repay 3,575,000.00
Jan 15, 2021 IBRD-48440 Int Charges 228,443.66
Jan 15, 2021 IBRD-48440 Loan Repay 3,475,000.00
Jul 15, 2020 IBRD-48440 Int Charges 676,971.75
Jul 15, 2020 IBRD-48440 Loan Repay 3,375,000.00
Jan 15, 2023 IBRD-48440 Int Charges 770,532.30
Jan 15, 2023 IBRD-48440 Int Charges 48,942.21
Jan 15, 2023 IBRD-48440 Loan Repay 3,890,000.00
Jan 15, 2022 IBRD-48440 Int Charges 160,264.00
Jan 15, 2022 IBRD-48440 Loan Repay 3,675,000.00
Jul 15, 2022 IBRD-48440 Int Charges 201,395.20
Jul 15, 2022 IBRD-48440 Loan Repay 3,780,000.00
Dec 14, 2006 IBRD-48440 Loan Commitment 100,000,000.00
Jul 15, 2024 IBRD-48440 Int Charges 867,414.10
Jul 15, 2024 IBRD-48440 Int Charges 6,731.89
Jul 15, 2024 IBRD-48440 Loan Repay 4,240,000.00
Jan 15, 2024 IBRD-48440 Int Charges 15,143.84
Jan 15, 2024 IBRD-48440 Loan Repay 4,120,000.00
Jan 15, 2024 IBRD-48440 Int Charges 991,519.25
Jul 15, 2023 IBRD-48440 Int Charges 51,726.60
Jul 15, 2023 IBRD-48440 Int Charges 936,012.40
Jul 15, 2013 IBRD-48440 Int Charges 481.67
Jul 15, 2013 IBRD-48440 Int Charges 159.47
Jul 15, 2023 IBRD-48440 Loan Repay 4,005,000.00
Jul 15, 2013 IBRD-48440 Int Charges 360,699.10
Jul 15, 2013 IBRD-48440 Loan Repay 2,265,000.00
Jan 15, 2015 IBRD-48440 Int Charges 280,953.70
Jan 15, 2015 IBRD-48440 Loan Repay 2,470,000.00
Jul 15, 2014 IBRD-48440 Int Charges 274,697.66
Jul 15, 2014 IBRD-48440 Loan Repay 2,400,000.00
Jan 15, 2014 IBRD-48440 Int Charges 315,035.60
Jan 15, 2014 IBRD-48440 Loan Repay 2,330,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Highly Satisfactory 2013-10-26
Procurement Satisfactory 2013-10-26
Financial Management Satisfactory 2013-10-26
Monitoring and Evaluation Satisfactory 2013-10-26
Overall Implementation Progress (IP) Satisfactory 2013-10-26
Counterpart Funding Satisfactory 2013-10-26
Project Management Satisfactory 2013-10-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-19-2013
OutcomesHighly Satisfactory
Risk to Development OutcomeNegligible
Bank PerformanceSubstantial
Borrower PerformanceHighly Satisfactory
Government PerformanceHighly Satisfactory
Implementing AgencyHighly Satisfactory

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Project-supported timber plantations achieve higher timber volume growth per hectare than non-project plantation areasValueN/A33.6%25%
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Percent increase in vegetation cover (VC) in targeted watershedsValue38%50%48%
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Number of employees of participating Forest Farms no longer on payrollValue0.002452.001600.00
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component two:Number of ha of multiple protection forests established andnumber of tons of carbon sequesteredValue018,010 ha of multiple protection forests establish18,000ha of multiple protectin forests established
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component three:Management effectiveness of five targeted nature reserves measured by average incremental scores on scorecard increasesValueScore of 437670
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component four:Provincial forest strategy formulated and adopted by Guangxi authorities.ValueN/AStrategy is formulated and adoptedStrategy is formulated and adopted
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component four:Number of forestry staff and households trained under the projectValue0 person-time204,000190,000
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Number of nature reserves within which key indicator species or limestone forest areas remain stable or increaseValue054
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Area restored or re/afforestedValue0.00214900.00200000.00
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component three: Project-supported nature reserves maintain a higher METT score than a sample of comparable non-project nature reservesValue0.0048.0015.00
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component three: Number of new sites with high biodiversity value identified and protection initiatedValue0.001.001.00
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component four: Number of guidelines and technical advisory bulletins developed and disseminatedValue0.0041.0020.00
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component three: Kilometric abundance score for four forest-dependent pheasants in Maoershan Nature ReserveValue0.471.011.0
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component three: Number of Francoisi leaf monkeys in Nong Gang Nature ReserveValue669880
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component three: Number of slipper orchids along 19 fixed transects in Mulun Nature ReserveValue849918No decline from previou year
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component three: Area affected by fires in Longshan Nature Reserve Donghong SectionValue19.70Less than 3 ha affected by fire since start Yr. 4
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component three: Forest dependency score for birds in Damingshan Nature ReserveValue3.08.44.0
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Component one: Number of participating farm households reached (‘000HH)Value0.00118.00112.00
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment
  • Area restoredValue0.00214900.00200000.00
    DateDecember 14, 2006December 31, 2012December 31, 2012
    Comment