Mexico (CRL) Integrated Energy Services

Abstract*

The objective of the Integrated Energy Services Project of Mexico is to increase access to efficient and sustainable integrated energy services in predominantly indigenous rural areas of Mexico and to achieve reduction of greenhouse gas emissions through the use of renewable energy in rural areas for the provision of electricity. The Project has five main components: (1) strengthening of strategy, policy, and regulatory frameworks, (2) investment...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Increase access to efficient and sustainable integrated energy services in predominantly indigenous rural areas of Mexico

Key Details

Project Details

  • P088996

  • Closed

  • Guillermo Hernandez Gonzalez

  • Government of Mexico, Secretaría de Hacienda y Credito Publico, Unidad de Asuntos Internacionales

  • Mexico

  • June 7, 2006

  • (as of board presentation)

    January 17, 2008

  • July 16, 2009

  • US$ 15.00 million

  • B

  • Not Applicable

  • October 30, 2015

  • BANK APPROVED

  • November 1, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 91.83
International Bank for Reconstruction and Development 15.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 15.00
IDA Commitment N/A
IBRD + IDA Commitment 15.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 106.83

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 1, 2020 IBRD-75010 Int Charges 51,075.17
May 1, 2017 IBRD-75010 Loan Repay 758,275.40
Nov 1, 2019 IBRD-75010 Int Charges 78,963.66
Nov 1, 2019 IBRD-75010 Loan Repay 758,275.40
May 1, 2022 IBRD-75010 Int Charges 3,739.04
May 1, 2022 IBRD-75010 Loan Repay 758,275.40
Nov 1, 2021 IBRD-75010 Int Charges 5,932.70
Nov 1, 2021 IBRD-75010 Loan Repay 758,275.40
May 1, 2021 IBRD-75010 Int Charges 8,238.00
May 1, 2021 IBRD-75010 Loan Repay 758,275.40
Nov 1, 2022 IBRD-75010 Loan Repay 759,424.90
Nov 1, 2022 IBRD-75010 Int Charges 8,345.24
Jan 17, 2008 IBRD-75010 Loan Commitment 15,000,000.00
Nov 1, 2017 IBRD-75010 Int Charges 73,763.40
Nov 1, 2017 IBRD-75010 Loan Repay 758,275.40
May 1, 2019 IBRD-75010 Loan Repay 758,275.40
May 1, 2019 IBRD-75010 Int Charges 94,566.42
Nov 1, 2018 IBRD-75010 Int Charges 98,380.06
Nov 1, 2018 IBRD-75010 Loan Repay 758,275.40
May 1, 2018 IBRD-75010 Int Charges 71,303.44
May 1, 2018 IBRD-75010 Loan Repay 758,275.40
Nov 1, 2020 IBRD-75010 Int Charges 21,322.44
Nov 1, 2020 IBRD-75010 Loan Repay 758,275.40
Nov 1, 2014 IBRD-75010 Int Charges 1,411.55
Nov 1, 2014 IBRD-75010 Int Charges 5,055.78
Nov 1, 2014 IBRD-75010 Loan Repay 93,812.85
May 1, 2015 IBRD-75010 Int Charges 23,046.99
May 1, 2015 IBRD-75010 Loan Repay 604,299.56
Apr 24, 2015 IBRD-75010 Loan Disb 313,560.70
Feb 4, 2015 IBRD-75010 Loan Disb 1,172,969.00
Dec 17, 2014 IBRD-75010 Loan Disb 4,067,336.80
Dec 17, 2014 IBRD-75010 Loan Disb 2,927,482.00
May 1, 2014 IBRD-75010 Int Charges 110.29
May 1, 2014 IBRD-75010 Loan Repay 1,875.00
Mar 12, 2014 IBRD-75010 Loan Disb 1,563,568.80
Nov 1, 2013 IBRD-75010 Int Charges 132.90
Nov 1, 2013 IBRD-75010 Loan Repay 1,875.00
Nov 1, 2016 IBRD-75010 Int Charges 60,466.86
Nov 1, 2016 IBRD-75010 Loan Repay 758,275.40
May 1, 2016 IBRD-75010 Int Charges 42,716.90
May 1, 2016 IBRD-75010 Loan Repay 758,275.40
Feb 23, 2016 IBRD-75010 Loan Disb 544,383.94
Feb 29, 2016 IBRD-75010 Loan Cancel 3,049,110.00
Nov 1, 2015 IBRD-75010 Int Charges 34,145.05
Nov 1, 2015 IBRD-75010 Loan Repay 630,147.75
Jan 22, 2016 IBRD-75010 Loan Disb 592,007.94
Nov 1, 2015 IBRD-75010 Int Charges 38.41
Aug 17, 2015 IBRD-75010 Loan Disb 73,968.42
Nov 20, 2015 IBRD-75010 Loan Disb 658,112.50
May 1, 2017 IBRD-75010 Int Charges 71,377.88
May 1, 2020 IBRD-75010 Loan Repay 758,275.40

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2015-10-30
Project Management Moderately Satisfactory 2015-10-30
Financial Management Moderately Satisfactory 2015-10-30
Monitoring and Evaluation Moderately Unsatisfactory 2015-10-30
Progress towards achievement of PDO Moderately Satisfactory 2015-10-30
Counterpart Funding Highly Satisfactory 2015-10-30
Overall Implementation Progress (IP) Moderately Satisfactory 2015-10-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 08-31-2016
OutcomesModerately Unsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-30-2016PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Total RET energy consumption per household in MWh/yearValue01,3702,077
    DateNovember 8, 2012October 30, 2015October 30, 2015
    Comment
  • Installed capacityValue020376,205
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment
  • Number of HH electrified with RET.Value018464,432
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment
  • Costs per New Connection (USD/HH).Value1,3711492.51,097
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment
  • Incremental increase in MWh/year of electricity consumed for productive uses in targeted communities (MWh/year).Value05275,768
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment
  • Number of new social/productive activities and micro-businesses developed.Value01852179
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment
  • People provided with access to electricity by hold connections-Other RE: Off-gridValue0.007384.0017578.00
    DateOctober 30, 2015October 30, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Issuance of technical guidelines.ValueNoneSeven bidding processes (including technical speciTechnical specifications for four bidding document
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment
  • PPMT/SPICs/PAC/PC/TSMG operational.ValueNoneNo longer applicableNo longer applicable
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment
  • Design bidding documents.ValueNoneSeven bidding documents have been designed.Four bidding documents.
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment
  • Baseline Impact Evaluation.ValueNoneThree assessmentsThree assessments
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment
  • Medium Term Impact Evaluation Assessment.ValueNone21
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment
  • Emissions Reduction (thousand tones CO2e)Value099241
    DateJuly 22, 2008October 30, 2015October 30, 2015
    Comment