Financier | Commitments |
---|---|
Borrower/Recipient | 91.83 |
International Bank for Reconstruction and Development | 15.00 |
P088996
Closed
Guillermo Hernandez Gonzalez
Government of Mexico, Secretaría de Hacienda y Credito Publico, Unidad de Asuntos Internacionales
June 7, 2006
(as of board presentation)
January 17, 2008
July 16, 2009
US$ 106.83 million
Secretaría de Energía
2008
US$ 15.00 million
B
Not Applicable
October 30, 2015
BANK APPROVED
November 1, 2023
Financier | Commitments |
---|---|
Borrower/Recipient | 91.83 |
International Bank for Reconstruction and Development | 15.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 15.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 15.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 106.83 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 1, 2020 | IBRD-75010 | Int Charges | 51,075.17 |
May 1, 2017 | IBRD-75010 | Loan Repay | 758,275.40 |
Nov 1, 2019 | IBRD-75010 | Int Charges | 78,963.66 |
Nov 1, 2019 | IBRD-75010 | Loan Repay | 758,275.40 |
May 1, 2022 | IBRD-75010 | Int Charges | 3,739.04 |
May 1, 2022 | IBRD-75010 | Loan Repay | 758,275.40 |
Nov 1, 2021 | IBRD-75010 | Int Charges | 5,932.70 |
Nov 1, 2021 | IBRD-75010 | Loan Repay | 758,275.40 |
May 1, 2021 | IBRD-75010 | Int Charges | 8,238.00 |
May 1, 2021 | IBRD-75010 | Loan Repay | 758,275.40 |
Nov 1, 2022 | IBRD-75010 | Loan Repay | 759,424.90 |
Nov 1, 2022 | IBRD-75010 | Int Charges | 8,345.24 |
Jan 17, 2008 | IBRD-75010 | Loan Commitment | 15,000,000.00 |
Nov 1, 2017 | IBRD-75010 | Int Charges | 73,763.40 |
Nov 1, 2017 | IBRD-75010 | Loan Repay | 758,275.40 |
May 1, 2019 | IBRD-75010 | Loan Repay | 758,275.40 |
May 1, 2019 | IBRD-75010 | Int Charges | 94,566.42 |
Nov 1, 2018 | IBRD-75010 | Int Charges | 98,380.06 |
Nov 1, 2018 | IBRD-75010 | Loan Repay | 758,275.40 |
May 1, 2018 | IBRD-75010 | Int Charges | 71,303.44 |
May 1, 2018 | IBRD-75010 | Loan Repay | 758,275.40 |
Nov 1, 2020 | IBRD-75010 | Int Charges | 21,322.44 |
Nov 1, 2020 | IBRD-75010 | Loan Repay | 758,275.40 |
Nov 1, 2014 | IBRD-75010 | Int Charges | 1,411.55 |
Nov 1, 2014 | IBRD-75010 | Int Charges | 5,055.78 |
Nov 1, 2014 | IBRD-75010 | Loan Repay | 93,812.85 |
May 1, 2015 | IBRD-75010 | Int Charges | 23,046.99 |
May 1, 2015 | IBRD-75010 | Loan Repay | 604,299.56 |
Apr 24, 2015 | IBRD-75010 | Loan Disb | 313,560.70 |
Feb 4, 2015 | IBRD-75010 | Loan Disb | 1,172,969.00 |
Dec 17, 2014 | IBRD-75010 | Loan Disb | 4,067,336.80 |
Dec 17, 2014 | IBRD-75010 | Loan Disb | 2,927,482.00 |
May 1, 2014 | IBRD-75010 | Int Charges | 110.29 |
May 1, 2014 | IBRD-75010 | Loan Repay | 1,875.00 |
Mar 12, 2014 | IBRD-75010 | Loan Disb | 1,563,568.80 |
Nov 1, 2013 | IBRD-75010 | Int Charges | 132.90 |
Nov 1, 2013 | IBRD-75010 | Loan Repay | 1,875.00 |
Nov 1, 2016 | IBRD-75010 | Int Charges | 60,466.86 |
Nov 1, 2016 | IBRD-75010 | Loan Repay | 758,275.40 |
May 1, 2016 | IBRD-75010 | Int Charges | 42,716.90 |
May 1, 2016 | IBRD-75010 | Loan Repay | 758,275.40 |
Feb 23, 2016 | IBRD-75010 | Loan Disb | 544,383.94 |
Feb 29, 2016 | IBRD-75010 | Loan Cancel | 3,049,110.00 |
Nov 1, 2015 | IBRD-75010 | Int Charges | 34,145.05 |
Nov 1, 2015 | IBRD-75010 | Loan Repay | 630,147.75 |
Jan 22, 2016 | IBRD-75010 | Loan Disb | 592,007.94 |
Nov 1, 2015 | IBRD-75010 | Int Charges | 38.41 |
Aug 17, 2015 | IBRD-75010 | Loan Disb | 73,968.42 |
Nov 20, 2015 | IBRD-75010 | Loan Disb | 658,112.50 |
May 1, 2017 | IBRD-75010 | Int Charges | 71,377.88 |
May 1, 2020 | IBRD-75010 | Loan Repay | 758,275.40 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2015-10-30 |
Project Management | Moderately Satisfactory | 2015-10-30 |
Financial Management | Moderately Satisfactory | 2015-10-30 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2015-10-30 |
Progress towards achievement of PDO | Moderately Satisfactory | 2015-10-30 |
Counterpart Funding | Highly Satisfactory | 2015-10-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2015-10-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 08-31-2016 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 12-30-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Substantial | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Total RET energy consumption per household in MWh/year | Value | 0 | 1,370 | 2,077 |
Date | November 8, 2012 | October 30, 2015 | October 30, 2015 | |
Comment |
Installed capacity | Value | 0 | 2037 | 6,205 |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |
Number of HH electrified with RET. | Value | 0 | 1846 | 4,432 |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |
Costs per New Connection (USD/HH). | Value | 1,371 | 1492.5 | 1,097 |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |
Incremental increase in MWh/year of electricity consumed for productive uses in targeted communities (MWh/year). | Value | 0 | 527 | 5,768 |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |
Number of new social/productive activities and micro-businesses developed. | Value | 0 | 185 | 2179 |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |
People provided with access to electricity by hold connections-Other RE: Off-grid | Value | 0.00 | 7384.00 | 17578.00 |
Date | October 30, 2015 | October 30, 2015 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Issuance of technical guidelines. | Value | None | Seven bidding processes (including technical speci | Technical specifications for four bidding document |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |
PPMT/SPICs/PAC/PC/TSMG operational. | Value | None | No longer applicable | No longer applicable |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |
Design bidding documents. | Value | None | Seven bidding documents have been designed. | Four bidding documents. |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |
Baseline Impact Evaluation. | Value | None | Three assessments | Three assessments |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |
Medium Term Impact Evaluation Assessment. | Value | None | 2 | 1 |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |
Emissions Reduction (thousand tones CO2e) | Value | 0 | 99 | 241 |
Date | July 22, 2008 | October 30, 2015 | October 30, 2015 | |
Comment |