Brasilia Environmentally Sustainable Project

Abstract*

The Brasilia Environmentally Sustainable Project will meet the growing needs of the Federal District and the Brasilia Metropolitan Region to reduce regional inequalities and ensure quality water resources. The project consists of the following components: Component 1) will support institutional strengthening and technical assistance for the enhancement of the technical and institutional environment. Component 2) will reduce poverty and promote social...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project's Development Objective is to reduce regional inequalities and ensure quality water resources to meet the growing needs of the Federal District and the Brasilia Metropolitan Region, through environmental planning and management activities, integrated with poverty reduction interventions and environmental rehabilitation in the most critical river basins. Specifically, the expected outcomes of the project are: (a) improved water quality of the Vicente Pires and Descoberto Rivers; (b) improved living conditions in targeted low-income settlements by providing integrated urban environmental services; and (c) strengthened technical and institutional capacity, contributing to development of the Brasilia metropolitan region.

Key Details

Project Details

  • P089440

  • Closed

  • Sameh Wahba Tadros

  • N/A

  • Brazil

  • September 8, 2004

  • (as of board presentation)

    August 25, 2005

  • May 16, 2006

  • US$ 57.64 million

  • A

  • Not Applicable

  • December 31, 2011

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 57.64
Borrower/Recipient 59.51

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 57.64
IDA Commitment N/A
IBRD + IDA Commitment 57.64
Lending Instrument
Grant Amount N/A
Total Project Cost** 117.15

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 25, 2005 IBRD-73260 Loan Commitment 57,643,000.00
Sep 15, 2016 IBRD-73260 Loan Repay 1,910,213.20
Mar 15, 2022 IBRD-73260 Int Charges 3,756.99
Sep 15, 2021 IBRD-73260 Int Charges 8,497.02
Sep 15, 2021 IBRD-73260 Loan Repay 1,910,213.20
Mar 15, 2021 IBRD-73260 Int Charges 15,158.38
Mar 15, 2021 IBRD-73260 Loan Repay 1,910,213.20
Sep 15, 2020 IBRD-73260 Int Charges 38,449.70
Sep 15, 2020 IBRD-73260 Loan Repay 1,910,213.20
Mar 15, 2020 IBRD-73260 Int Charges 110,568.13
Mar 15, 2020 IBRD-73260 Loan Repay 1,910,213.20
Sep 15, 2019 IBRD-73260 Loan Repay 1,910,213.20
Sep 15, 2019 IBRD-73260 Int Charges 171,008.52
Mar 15, 2016 IBRD-73260 Int Charges 99,011.18
Mar 15, 2016 IBRD-73260 Loan Repay 1,910,213.20
Sep 15, 2015 IBRD-73260 Int Charges 88,706.26
Sep 15, 2015 IBRD-73260 Loan Repay 1,910,213.20
Mar 15, 2015 IBRD-73260 Int Charges 83,433.16
Mar 15, 2015 IBRD-73260 Loan Repay 1,910,213.20
Sep 15, 2014 IBRD-73260 Int Charges 0.01
Sep 15, 2014 IBRD-73260 Int Charges 90,478.72
Sep 15, 2014 IBRD-73260 Loan Repay 1,910,213.20
Mar 15, 2014 IBRD-73260 Int Charges 102,726.87
Mar 15, 2014 IBRD-73260 Loan Repay 1,910,213.20
Sep 15, 2013 IBRD-73260 Int Charges 121,111.88
Sep 15, 2013 IBRD-73260 Loan Repay 1,910,213.20
Mar 15, 2019 IBRD-73260 Loan Repay 1,910,213.20
Mar 15, 2019 IBRD-73260 Int Charges 188,988.52
Sep 15, 2018 IBRD-73260 Int Charges 198,622.80
Sep 15, 2018 IBRD-73260 Loan Repay 1,910,213.20
Mar 15, 2018 IBRD-73260 Int Charges 147,445.56
Mar 15, 2018 IBRD-73260 Loan Repay 1,910,213.20
Sep 15, 2017 IBRD-73260 Int Charges 163,662.12
Sep 15, 2017 IBRD-73260 Loan Repay 1,910,213.20
Mar 15, 2017 IBRD-73260 Int Charges 158,150.60
Mar 15, 2017 IBRD-73260 Loan Repay 1,910,213.20
Sep 15, 2016 IBRD-73260 Int Charges 135,655.70
Mar 15, 2022 IBRD-73260 Loan Repay 1,868,110.10

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Unsatisfactory 2011-12-26
Procurement Moderately Satisfactory 2011-12-26
Counterpart Funding Unsatisfactory 2011-12-26
Monitoring and Evaluation Moderately Unsatisfactory 2011-12-26
Overall Implementation Progress (IP) Moderately Unsatisfactory 2011-12-26
Overall Safeguards Rating Unsatisfactory 2011-12-26
Progress towards achievement of PDO Unsatisfactory 2011-12-26
Financial Management Satisfactory 2011-12-26
Overall Safeguards Rating Unsatisfactory 2011-12-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2012
OutcomesUnsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceUnsatisfactory
Government PerformanceUnsatisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-31-2013PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeHighN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Water quality of the Vicente Pires River improved and/or maintained to Class 2ValueNot Class 2No results so far.Class 2
    DateMay 24, 2006December 12, 2011March 31, 2012
    CommentAlthough CAESB performs constant monitoring of the quality of the water, so far there are no results to be reported as a result ofthe Project, since the works in Vicente Pires are not completed and will not be until Dec 2012.
  • Improved living conditions in Vila Estrutural by providing integrated urban environmental services measured by improvement in the sub-indicators of the area Social Environmental Indicator (ISA) and byValue0.000.0070.00
    DateMay 24, 2006December 12, 2011March 31, 2012
    CommentSet of 14 indicators. Report prepared.3 of 14 sub-indicators improved. Some data unavailable to report composite indicator. No results to be reported so far. GDF isconducting final survey with results expected 02/15/2012 with the final Progress Report and Assessment. They will be reflected inthe ICR.% improvement in the indicator compared to baseline70% of families satisfied with Program results.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 3.2 Vicente Pires: # households connected to sewerage systems.Value0 households connected.0 households connected5,700 households connected.
    DateMay 24, 2006December 12, 2011December 31, 2012
    CommentWorks underway. Collection system advanced but STP and lifting stations delayed. Expected for conclusion 12/2012.
  • ADASA strategic plan endorsedValueNo planNo plan (not started).Plan completed and endorsed
    DateDecember 17, 2010December 12, 2011December 31, 2012
    Comment
  • SLU restructuring proposal adopted by the GDFValueNo proposalUnder developmentProposal completed and adopted
    DateDecember 17, 2010December 12, 2011December 31, 2012
    Comment
  • New planning support instruments adopted by the GDFValue0.003.004.00
    DateDecember 17, 2010December 12, 2011December 31, 2012
    Comment3 instruments are at advanced dev stages: Economic-Ecologic Zoning, License Improvement, SS Regularization4 instruments adopted
  • Provision of additional educational and community facilities in Vila EstruturalValueNoneAll but one planned facilities completed, initiallAll planned facilities completed
    DateMay 24, 2006December 12, 2011March 31, 2012
    CommentGDF has delivered new facilities such as community restaurants, police station, daycare center, schools using own resources.
  • Number of scavengers benefiting from GDF-supported recycling programValue0.000.00800.00
    DateMay 24, 2006December 12, 2011March 31, 2012
    CommentNot yet started.
  • Environmental remediation activities of the unused areas of Joquei landfill launchedValueNo remediationNo remediation.1/3 of landfill remediated
    DateMay 24, 2006December 12, 2011March 31, 2012
    CommentLandfill still partially used because the bid process for the new landfill is delayed. Activity dropped from project by 06/2011.
  • Procurement process of the new sanitary landfill of the GDF finishedValueNo processProcess launched but not yet completed.Completed
    DateMay 24, 2006December 12, 2011March 31, 2012
    CommentConcession bid process initiated 3 times without satisfactory conclusion. GDF decided to build a public landfill. Detailed designsand bid docs preparation underway.
  • Number of people in urban areas provided with access to Improved Sanitation under the projectValue0.0026150.0026150.00
    DateMay 24, 2006December 13, 2011March 31, 2012
    CommentWorks completed / 7067 sewer connections performed. This CSI indicator was added in lieu of the previous customized one -Population connected to sewerage system in Vila Estrutural.
  • Roads rehabilitated, Non-ruralValue0.0056.900.00
    DateDecember 13, 2011
    CommentWorks almost completed. This indicator was added in lieu of the previous customized one - Percent of population with access topaved roads, stormwater drainage system in Vila Estrutural - as suggested by OPCS.