Abstract*

The objective of the Brazil Rio Grande do Norte Integrated Water Resources Management project is to promote economic, social, and environmentally sustainable development through the implementation of an integrated water resources management system. Mostly by focusing on institutional strengthening and rehabilitation of key bulk water infrastructure, the proposed project will seek to consolidate this system, which the state has often overlooked in...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The higher level objective of the project is to promote economic, social, and environmentally sustainable development through the implementation of an integrated water resources management system. Mostly by focusing on institutional strengthening and rehabilitation of key bulk water infrastructure, the proposed project will seek to consolidate this system, which the state has often overlooked in the past in favor of larger infrastructure investments. The specific project development objective is to implement an integrated water resources management system that will support more environmentally sustainable use of water resources while also increasing access of poor families to reliable potable water and decreasing operational and maintenance costs of water allocation and distribution systems.

Key Details

Project Details

  • P089929

  • Closed

  • Paula Pedreira de Freitas de Oliveir

  • State of Rio Grande do Norte

  • Brazil

  • August 3, 2004

  • (as of board presentation)

    September 18, 2007

  • August 18, 2008

  • US$ 59.80 million

  • Secretariat of Environment and Water Resources

  • Latin America and Caribbean

  • 2008

  • US$ 35.90 million

  • B

  • Not Applicable

  • September 30, 2014

  • BANK APPROVED

  • June 25, 2015

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 23.90
International Bank for Reconstruction and Development 35.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 35.90
IDA Commitment N/A
IBRD + IDA Commitment 35.90
Lending Instrument
Grant Amount N/A
Total Project Cost** 59.80

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 15, 2024 IBRD-74880 Int Charges 171.12
May 15, 2024 IBRD-74880 Int Charges 30,541.19
May 15, 2024 IBRD-74880 Loan Repay 1,005,594.25
Nov 17, 2015 IBRD-74880 Int Charges 44,875.56
Nov 17, 2015 IBRD-74880 Loan Repay 1,061,803.00
Feb 27, 2015 IBRD-74880 Loan Cancel 10,056,640.00
May 26, 2017 IBRD-74880 Loan Repay 1,061,803.00
May 26, 2017 IBRD-74880 Int Charges 502.29
May 26, 2017 IBRD-74880 Int Charges 104,733.80
Nov 28, 2016 IBRD-74880 Int Charges 83,233.51
Nov 28, 2016 IBRD-74880 Loan Repay 1,061,803.00
Nov 27, 2017 IBRD-74880 Int Charges 483.42
Nov 27, 2017 IBRD-74880 Int Charges 113,012.92
Nov 27, 2017 IBRD-74880 Loan Repay 1,061,803.00
May 15, 2019 IBRD-74880 Loan Repay 1,061,803.00
May 15, 2019 IBRD-74880 Int Charges 944.12
May 15, 2019 IBRD-74880 Int Charges 170,512.66
Nov 26, 2018 IBRD-74880 Int Charges 1,061.21
Nov 26, 2018 IBRD-74880 Int Charges 167,033.56
Nov 26, 2018 IBRD-74880 Loan Repay 1,061,803.00
May 29, 2018 IBRD-74880 Int Charges 591.07
May 29, 2018 IBRD-74880 Int Charges 115,684.98
May 29, 2018 IBRD-74880 Loan Repay 1,061,803.00
May 29, 2020 IBRD-74880 Int Charges 94,920.79
May 29, 2020 IBRD-74880 Int Charges 174.32
May 29, 2020 IBRD-74880 Loan Repay 1,061,803.00
Nov 18, 2019 IBRD-74880 Int Charges 142,928.58
Nov 18, 2019 IBRD-74880 Loan Repay 1,061,803.00
Nov 15, 2020 IBRD-74880 Int Charges 301.43
Nov 15, 2020 IBRD-74880 Int Charges 31,598.50
Nov 15, 2020 IBRD-74880 Loan Repay 1,061,803.00
May 15, 2021 IBRD-74880 Int Charges 11,172.41
May 15, 2021 IBRD-74880 Loan Repay 1,061,803.00
Nov 15, 2022 IBRD-74880 Loan Repay 1,018,431.94
Nov 15, 2022 IBRD-74880 Int Charges 43,371.09
Nov 15, 2022 IBRD-74880 Loan Repay 43,371.09
May 15, 2022 IBRD-74880 Int Charges 8.26
May 15, 2022 IBRD-74880 Int Charges 7,438.03
May 15, 2022 IBRD-74880 Loan Repay 1,054,356.80
May 15, 2022 IBRD-74880 Loan Repay 7,446.29
Nov 16, 2021 IBRD-74880 Loan Repay 1,054,019.50
Nov 16, 2021 IBRD-74880 Loan Repay 7,783.60
Nov 16, 2021 IBRD-74880 Int Charges 7,783.60
May 15, 2023 IBRD-74880 Int Charges 81,502.05
May 15, 2023 IBRD-74880 Loan Repay 980,301.00
May 15, 2023 IBRD-74880 Loan Repay 81,502.05
Nov 16, 2023 IBRD-74880 Int Charges 57,907.82
Nov 16, 2023 IBRD-74880 Loan Repay 1,061,803.00
Sep 18, 2007 IBRD-74880 Loan Commitment 35,900,000.00
May 15, 2024 IBRD-74880 Loan Repay 30,712.31
Nov 15, 2014 IBRD-74880 Int Charges 38,696.07
Nov 15, 2014 IBRD-74880 Loan Repay 1,050,011.40
Nov 25, 2014 IBRD-74880 Loan Disb 330,058.94
Jul 2, 2014 IBRD-74880 Loan Disb 728,199.50
May 15, 2014 IBRD-74880 Int Charges 42,008.36
May 15, 2014 IBRD-74880 Loan Repay 983,147.44
Feb 7, 2014 IBRD-74880 Loan Disb 496,401.10
Nov 15, 2013 IBRD-74880 Int Charges 47,736.75
Nov 15, 2013 IBRD-74880 Loan Repay 938,571.00
Nov 21, 2013 IBRD-74880 Loan Disb 438,116.10
Aug 20, 2013 IBRD-74880 Loan Disb 2,133,925.20
May 15, 2015 IBRD-74880 Loan Repay 1,061,803.00
May 15, 2015 IBRD-74880 Int Charges 38,577.20
Aug 21, 2014 IBRD-74880 Loan Disb 606,409.40
Feb 27, 2015 IBRD-74880 Loan Disb -106,311.24
May 15, 2016 IBRD-74880 Int Charges 38.34
May 15, 2016 IBRD-74880 Int Charges 59,232.67
May 15, 2016 IBRD-74880 Loan Repay 1,061,803.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Satisfactory 2014-10-19
Progress towards achievement of PDO Moderately Satisfactory 2014-10-19
Counterpart Funding Moderately Unsatisfactory 2014-10-19
Financial Management Highly Satisfactory 2014-10-19
Overall Implementation Progress (IP) Moderately Unsatisfactory 2014-10-19
Overall Moderately Low 2014-10-19
Monitoring and Evaluation Satisfactory 2014-10-19
Procurement Moderately Satisfactory 2014-10-19
Project Management Moderately Unsatisfactory 2014-10-19
Overall Safeguards Rating Satisfactory 2014-10-19

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2015
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-30-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualityUnsatisfactoryN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Water resources monitoring and information network.ValueNetwork weak with few available informationFully operational netork.Fully operational network.
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentIndicator slightly revised during Project restructuring in August 2012.Network operational - 33 posts purchased and 15 installed. 18 to be installed by SEMARH until November. The network wasrestructured in partnership with the National Water Agency (ANA).Indicator remains the same. End target date revised only.
  • Monsenhor Expedito pipeline and distribution systems water losses controlled, macro and micro-measured.ValueNo control, macro or micro-measurementSystem macro and micro-measured. 25,000 micrometerSystem controlled macro and micro-measured
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentThe activities financed by the Project were part of the Company's strategy for loss control. Other activities were carried out bythe Company in this system and others.
  • Access to reliable potable waterValueIncremental indicator. Baseline zero.2,670 additional families - 12,925 people.3,000 additional families
    DateNovember 29, 2007September 29, 2014September 30, 2014
    Comment29 systems implemented by the Project are under operation. 4 systems are not operating due to either lack of water resources orproblems in construction.Indicator remains the same. End target date revised only.
  • Improved community water points constructed or rehabilitated under the projectValue0.0029.0033.00
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentIncremental indicator. Baseline is zero.29 systems benefited 12,925 people or 2,670 additional families. 4 systems are not operating due to either lack of water resourcesor problems in construction.33 systems will benefit 14,599 people or 3,591 families.Indicator remains the same. End target date revised only.
  • Management Plan of Cruzeta irrigation perimeter prepared with participation of APICRUZ and being implemented.ValueNo Plan.Plan under preparation by SEMARH, completion expecPlan prepared and being implemented.
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentIndicator was revised during Project restructuring in August 2012.Plan completion depends on current discussions with DNOCS and ANA about the management of the reservoir.Indicator remains the same. End target date revised only.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • State water resources legislation revisedValueExisting legislationLegislation revised and approved by the State AsseLegislation revised and adopted.
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentFew progress made in terms of adopting the new legislation.Indicator remains the same. End target date revised only.
  • Implementation of SEMARH and IGARN Strategic Planning, in accordance with the approved legislation.ValueStrategic planning in preparationSEMARH and IGARN worked on a first draft of the reStrategic planning implemented
    DateNovember 29, 2007September 29, 2014September 30, 2014
    Comment
  • Diagnosis of the State Water Resources Plan revised.ValueExisting state water resources planDiagnosis report prepared by the consulting firm wDiagnosis revised
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentConsulting firm performance was poor. The contract was canceled and no product was approved.
  • # of monitoring posts operatingValue032 posts operating50
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentIncluding 17 installed by ANA. 15 posts purchased by the Project installed. The remaining 18 are being installed by SEMARH untilNovember.Indicator remains the same. End target date revised only.
  • # of communities with water and sanitation systems adequately sustainedValue02933
    DateNovember 29, 2007September 29, 2014September 30, 2014
    Comment29 benefiting 12,925 people or 2,670 families.33 systems will benefit 14,599 people or 3,591 families.Indicator remains the same. End target date revised only.
  • # of families using improved water supply systemsValueIncremental indicator. Baseline is zero2,6703,000
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentIndicator remains the same. End target date revised only.
  • # of small desalinization units rehabilitated and being usedValue012760
    DateNovember 29, 2007September 29, 2014September 30, 2014
    Comment127 desalinization units belonging from SEMARH and other state institutions have been rehabilitated benefiting more than 20,000families.Indicator remains the same. End target date revised only.
  • # of technical and financial reports submitted on timeValue0All technical and financial reports submitted on tsemesterly and quarterly
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentIndicator remains the same. End target date revised only.
  • Dissemination Plan completed and Public Communication Actions implementedValue011
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentDissemination Plan completed. Several publications prepared used for dissemination of Project activities. The project website isoperational and updated.Indicator remains the same. End target date revised only.
  • River Basin Committees created and strengthened.Value0.001.001.00
    DateNovember 29, 2007September 29, 2014September 30, 2014
    CommentIncremental indicator. Baseline is zero.
  • Number of producers who benefited from hidroenvironmental works at Cobra River Basin.Value0.0075.0070.00
    DateMarch 29, 2007September 29, 2014September 30, 2014
    CommentIncremental indicator. Baseline is zero.Indirectly, 3,167 inhabitants in 7 municipalities were benefited by the activities.