Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 6.35 |
Borrower/Recipient | 3.72 |
Bilateral Agencies (unidentified) | 1.60 |
NETHERLANDS: Min. of Foreign Affairs / Min. of Dev. Coop. | 0.93 |
P090037
Closed
Anatol Gobjila
N/A
December 14, 2004
(as of board presentation)
December 15, 2005
March 9, 2006
US$ 12.60 million
N/A
2006
US$ 8.88 million
A
Not Applicable
December 31, 2010
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 6.35 |
Borrower/Recipient | 3.72 |
Bilateral Agencies (unidentified) | 1.60 |
NETHERLANDS: Min. of Foreign Affairs / Min. of Dev. Coop. | 0.93 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 8.88 |
Total Project Cost** | 12.60 |
Name | Review | Date |
---|---|---|
Summary Global Objective Rating | Satisfactory | 2011-01-01 |
Financial Management | Satisfactory | 2011-01-01 |
Monitoring and Evaluation | Satisfactory | 2011-01-01 |
Overall Implementation Progress (IP) | Satisfactory | 2011-01-01 |
Procurement | Satisfactory | 2011-01-01 |
Counterpart Funding | Satisfactory | 2011-01-01 |
Project Management | Satisfactory | 2011-01-01 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-24-2011 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 01-31-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Dismantling of 17,300 obsolete capacitors containing PCBs, packing in closed containers, shipping and destruction. | Value | 0 capacitors dismantled | 16,800 capacitors dismantled and destroyed. | 17,300 capacitors dismantled and destroyed |
Date | December 15, 2005 | December 13, 2010 | December 13, 2010 | |
Comment | Activity completed. The difference in actual quantities and the indicator stems from the fact that the latter was based onestimates. The exact quantity could only be determined once excavation and clean-up works have commenced. |
Excavation of 2,000 capacitors and contaminated soil in Vulcanesti Power Stations. | Value | 0 capacitors and no soil excavated | 1800 capacitors excavated and destroyed. Clean-up | 2000 capacitors excavated and destroyed. |
Date | December 15, 2005 | December 13, 2010 | December 13, 2010 | |
Comment | Activity completed. The difference in actual quantities and the indicator stems from the fact that the latter was based onestimates. The exact quantity could only be determined once excavation and clean-up works have commenced. |
Guidelines issued on POPs contaminated site management issues. | Value | no guidelines | Guidelines and handbook for POPs management have b | guidelines and handbook for POPs management |
Date | December 15, 2005 | December 13, 2010 | December 13, 2010 | |
Comment |
POPs information management and reporting system in place. | Value | no information management and reporting system in | The design of the information management and repor | Information management and reporting system in pla |
Date | December 15, 2005 | December 13, 2010 | December 13, 2010 | |
Comment | The design will be completed before December 31, 2010 |
PCB inventory registration system and national database in place | Value | No PCB inventory registration system or national d | PCB inventory and database complete | PCB inventory and database complete |
Date | December 15, 2005 | December 13, 2010 | December 13, 2010 | |
Comment | Additional inventory activities are being carried out outside of the scope of the Project with country resources. |
Destruction of approximately 1,060 tons of PCB containing capacitors. | Value | 0 tons destroyed | 934.2 tons of PCB containing capacitors destroyed. | 1060 tons of PCB containing capacitors destroyed |
Date | December 15, 2005 | December 13, 2010 | December 13, 2010 | |
Comment | Activity completed. The difference in actual quantities and the indicator stems from the fact that the latter was based onestimates. The exact quantity could only be determined once excavation and clean-up works have commenced. |
Destruction of 1,150 tons of POPs containing and contaminated obsolete pesticides. | Value | 0 tons destroyed | 1293 tons destroyed. | 1.150 tons destroyed |
Date | December 15, 2005 | December 13, 2010 | December 13, 2010 | |
Comment | Activity completed. |
Modern regulatory system established for the management and control of POPs and other toxic and harmful chemicals and wastes | Value | no regulatory system | Drafting of legislation, by-laws and regulations ( | functioning regulatory system |
Date | December 15, 2005 | December 13, 2010 | December 31, 2010 | |
Comment |