Nepal - Biogas Program

Development Objective

The project development objectives for this Carbon Finance operation are: - increased access to modern household cooking fuel from renewable energy sources - reduced global emissions of carbon dioxide, a greenhouse gas

Key Details

Project Details

  • P090038

  • Closed

  • Sandrine Boukerche , Yevgen Yesyrkenov

  • AEPC

  • Nepal

  • January 24, 2005

  • (as of board presentation)

    June 2, 2006

  • May 3, 2006

  • US$ 64.40 million

  • N/A

  • South Asia

  • 2006

  • US$ 21.00 million

  • C

  • Not Applicable

  • June 30, 2017

  • BANK APPROVED

  • December 19, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
PROTOTYPE CARBON FUND 7.00
Local Sources of Borrowing Country 37.80
Borrower/Recipient 5.60
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) 9.10
NETHERLANDS, Govt. of THE (Except for MOFA/Min of Dev. Coop 4.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 21.00
Total Project Cost** 64.40

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2014-05-14
Overall Low 2014-05-14
Project Management Satisfactory 2014-05-14
Counterpart Funding Satisfactory 2014-05-14
Monitoring and Evaluation Satisfactory 2014-05-14
Overall Implementation Progress (IP) Satisfactory 2014-05-14

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Emissions reductions generated.Value0.00520601.00One million tons
    DateJuly 1, 2006February 24, 2014December 31, 2015
    CommentNo issuance of ERs has been made.Claim of additional 41,776 ERs from bundle 4 is expected to be approved by the CDM Executive Board soon. Additional monitoringreports for all the bundles to claim 182 thousand ERs are currently under verification.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • ERs DeliveredValue0.00612374.001000000.00
    DateJuly 1, 2006February 24, 2014July 30, 2015
    CommentThe payment against delivery of ERs has reached up to US$ 3.55 million, which is more than 50% of the agreed amount under ERPA.