PE Rural Electrification

Abstract*

The objective of the Rural Electrification Project is to increase access to efficient and sustainable electricity services in rural areas of Peru. The project's global environmental objective is to achieve reduction of greenhouse gas emissions through use of renewable energy in rural areas for provision of electricity. The Project has five main components: (a) investment in rural electrification sub-projects by private and state-owned enterprises...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the proposed Project is to increase access to efficient and sustainable electricity services in rural areas of Peru.

Key Details

Project Details

  • P090116

  • Closed

  • Janina Franco Salazar

  • N/A

  • Peru

  • August 9, 2004

  • (as of board presentation)

    March 7, 2006

  • August 10, 2006

  • US$ 50.00 million

  • B

  • Not Applicable

  • June 30, 2013

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 50.00
Borrower/Recipient 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 50.00
IDA Commitment N/A
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 15, 2014 IBRD-73660 Int Charges 142,959.34
Mar 7, 2006 IBRD-73660 Loan Commitment 50,000,000.00
Oct 23, 2013 IBRD-73660 Loan Disb -1,325.52
Oct 15, 2013 IBRD-73660 Int Charges 173,240.20
Oct 23, 2013 IBRD-73660 Loan Disb -51,171.24
Apr 15, 2014 IBRD-73660 Int Charges 2.88
Apr 15, 2014 IBRD-73660 Int Charges 152,162.70
Oct 15, 2015 IBRD-73660 Int Charges 164,161.60
Apr 29, 2015 IBRD-73660 Loan Cancel 442,258.00
Apr 15, 2015 IBRD-73660 Int Charges 142,178.16
Apr 29, 2015 IBRD-73660 Loan Disb -442,258.00
Oct 15, 2016 IBRD-73660 Loan Repay 14,668,981.00
Oct 15, 2016 IBRD-73660 Int Charges 257,257.28
Apr 15, 2016 IBRD-73660 Int Charges 191,389.45
Apr 15, 2016 IBRD-73660 Loan Repay 4,889,660.50
Apr 15, 2017 IBRD-73660 Int Charges 223,962.77
Apr 15, 2017 IBRD-73660 Loan Repay 29,337,962.00
Oct 31, 2013 IBRD-73660 Loan Cancel 52,496.76

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2013-07-07
Procurement Satisfactory 2013-07-07
Project Management Moderately Satisfactory 2013-07-07
Progress towards achievement of PDO Moderately Satisfactory 2013-07-07
Monitoring and Evaluation Moderately Satisfactory 2013-07-07
Overall Implementation Progress (IP) Moderately Satisfactory 2013-07-07
Counterpart Funding Satisfactory 2013-07-07

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-27-2013
OutcomesModerately Satisfactory
Risk to Development OutcomeNegligible
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceSubstantial
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-01-2017PROJECT PERFORMANCE ASSESSMENT REPORT: 06-17-2015
Outcome RatingSatisfactory Satisfactory
Risk To Development OutcomeNegligibleNegligible To Low
Bank PerformanceModerately SatisfactoryModerately Satisfactory
Borrower PerformanceSatisfactoryModerately Satisfactory
Government PerformanceNot RatedModerately Satisfactory
Implementing AgencyModerately SatisfactoryModerately Satisfactory
Icr QualityNot RatedSatisfactory
M&e QualitySubstantialSubstantial

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of new connections outside existing concession areasValue090,733 actually installed during construction,cap160,000
    DateFebruary 7, 2006June 15, 2013June 30, 2013
    CommentNote that until June 2012, the Bank team was reporting total capacity installed for new connections. In Oct 2012, the teamreported actual connections during construction. This ISR reports both. To be discussed in ICR.
  • Increase in MWh/year of electricity consumed for productive uses in target areas (MWh/Year)Value018,80018,000
    DateFebruary 7, 2006June 15, 2013June 30, 2013
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Investments by service providers in rural electrification outside concession (USD million)Value028.2523
    DateFebruary 7, 2006June 15, 2013June 30, 2013
    Comment
  • Issuance of norms, regulations and guidelines and their adoption for all rural electrification projects- for conventional grids- for renewable systemsValueNone-- conventional 75%renewable systems 100%100%
    DateFebruary 7, 2006June 15, 2013June 30, 2013
    CommentThe Project was key in obtaining regulatory approval for: (a) national tariffs for regulated service using PV systems; (b) accessto FOSE for regulated customers using PV systems: (c) Specific modifications to norms for rural grid extension.
  • Increase in number of enterprises adopting electricity using equipmentValue019,9009,000
    DateFebruary 7, 2006June 15, 2013June 30, 2013
    Comment
  • Number of proposals approved for financing- Conventional grids- Renewable systemsValue0Total: 63Conventional: 54Total: 81Conventional: 67Renewable: 14
    DateFebruary 7, 2006June 15, 2013June 30, 2013
    Comment
  • Increase in investment in electricity using equipment (US$ millions)Value0141.81
    DateFebruary 7, 2006June 15, 2013June 30, 2013
    Comment
  • Investments by service providers in rural electrification outside concession (USD million)Value028.2523
    DateFebruary 7, 2006June 15, 2013June 30, 2013
    Comment
  • Number of new connections served by renewable energyValue07,10020,000
    DateFebruary 7, 2006June 15, 2013June 30, 2013
    Comment