The objective of the Shanghai Agricultural and Non-Point Pollution Reduction Project for China is to demonstrate effective and innovative pollution reduction activities in Shanghai's rural areas in order to reduce the rural and agricultural pollution load (especially nutrients) in the surface water flowing to the East China Sea. There are four component to the project. Component one: livestock waste management technology demonstration. This component...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to demonstrate effective and innovative pollution reduction activities in Shanghai#s rural areas in order to reduce the rural/ agricultural pollution load (especially nutrients) to the East China Sea.

Key Details

Project Details

  • P090376

  • Closed

  • Gang Qin

  • Internatinal Department, Ministry of Finance

  • China

  • December 16, 2008

  • (as of board presentation)

    June 10, 2010

  • December 10, 2010

  • US$ 34.87 million

  • Shanghai APL Project Management Office

  • East Asia and Pacific

  • 2010

  • US$ 4.79 million

  • B

  • April 22, 2024

  • June 30, 2015

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 4.79
Local Govts. (Prov., District, City) of Borrowing Country 30.08

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 4.79
Total Project Cost** 34.87

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2015-07-14
Project Management Moderately Satisfactory 2015-07-14
Financial Management Satisfactory 2015-07-14
Summary Global Objective Rating Satisfactory 2015-07-14
Monitoring and Evaluation Satisfactory 2015-07-14
Overall Implementation Progress (IP) Moderately Satisfactory 2015-07-14

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-27-2015
OutcomesModerately Satisfactory
Risk to Development OutcomeNegligible
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-30-2016PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModestN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Technologies demonstrated in the project areas (number)Value0.006.006.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Client days of training provided (number)Value0.002870.002870.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Demonstration of pollution reduction technologiesValue0.006.006.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Reduced pollution of TN (total nitrogen) from subproject sites in Livestock Waste Mgmt Tech. Demo. componentValue0.00536.50425.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Reduced pollution of TP (total phosphorus) fro subproject sites in Livestock Waste Mgmt Tech component (tons/yr)Value0.00163.80129.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Reduced pollution of BOD (biological oxygen demand) from subproject sites in Livestock Waste Mgmt comp (tons/yr)Value0.002442.901983.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Reduced pollution of COD (chemical oxygen demand) from subproject sites in Livestock Waste comp (tons/yr)Value0.004828.504198.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Reduced pollution of NH3-N (Ammonia Nitrogen) from subproject sites in Wetland Demo component (tons/year)Value0.0016.602.29
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Reduced pollution of TP from subproject sites in Wetland Demo component (tons/year)Value0.002.200.70
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Reduced pollution of BOD from subproject sites in Wetland Demo component (tons/year)Value0.0090.7028.03
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Reduced pollution of COD from subproject sites in Wetland Demo component (tons/year)Value0.00173.4040.91
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Increased replication farm area using demonstrated technologies (cumulative) muValue0.0016000.0016000.00
    DateMay 31, 2009June 30, 2015June 30, 2015
    Comment
  • Development of a replication strategy for disseminating demonstrated technologiesValuenonefinalizedfinalized
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Average quantity of livestock solid & liquid waste treated at livestock farms in Jinshan, Shenye & Qianwei (tons/d)Value0.00360.00243.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Average volume of rural household wastewater treated at wetland WWTS in participating villages (m3/d)Value0.00199.00157.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Number of farmers receiving skills development programs on fertilizer, insecticides and pesticidesValue0.001100.001100.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Quantity of organid fertilizer used (tons/year)Value0.002400.002400.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Extent of low residue and low toxicity pesticides used (against total pesticides used at pilot sites)Value0.00100.0080.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Usage of green test control techniques (at pilot sites)Valuenone used100% of farmers are using green test techniques100% of farmers are using green test techniques
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Number of subprojects satisfactorily implemented (cumulative)Value0.007.007.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Number of training courses conductedValue0.0024.0024.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Number of farmers who participated in trainings and workshopsValue0.002870.002870.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Volume(mass) of BOD pollution load removed by treatment plant under the projectValue0.002533.602011.00
    DateMay 31, 2010June 30, 2015June 30, 2015
    Comment
  • Client days of training provided - Female (number)Value0.00574.00400.00
    DateMay 31, 2012June 30, 2015June 30, 2015
    Comment