Financier | Commitments |
---|---|
Local Communities | 15.00 |
IDA Credit | 154.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 95.00 |
Borrower/Recipient | 75.00 |
P090592
Closed
Srinivasa Podipireddy
DEA, Ministry of Finance
June 17, 2005
(as of board presentation)
December 14, 2006
March 26, 2007
US$ 339.00 million
Department of Water Supply and Sanitation
2007
US$ 154.00 million
B
June 24, 2015
December 31, 2014
BANK APPROVED
Financier | Commitments |
---|---|
Local Communities | 15.00 |
IDA Credit | 154.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 95.00 |
Borrower/Recipient | 75.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 154.00 |
IBRD + IDA Commitment | 154.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 339.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 15, 2019 | IDA-42510 | Loan Repay | 3,092,579.50 |
Nov 15, 2018 | IDA-42510 | Loan Repay | 3,080,565.00 |
Nov 15, 2018 | IDA-42510 | Int Charges | 377,362.25 |
Nov 15, 2018 | IDA-42510 | Int Charges | 377,362.25 |
May 15, 2018 | IDA-42510 | Int Charges | 402,265.90 |
May 15, 2018 | IDA-42510 | Int Charges | 402,265.90 |
May 15, 2018 | IDA-42510 | Loan Repay | 28,318.50 |
Nov 15, 2021 | IDA-42510 | Int Charges | 323,760.75 |
Nov 15, 2021 | IDA-42510 | Int Charges | 323,760.75 |
May 15, 2021 | IDA-42510 | Int Charges | 4,436.66 |
May 15, 2021 | IDA-42510 | Int Charges | 4,436.66 |
May 15, 2021 | IDA-42510 | Loan Repay | 1,637,080.60 |
May 15, 2021 | IDA-42510 | Int Charges | 323,622.50 |
May 15, 2021 | IDA-42510 | Int Charges | 323,622.50 |
Nov 15, 2020 | IDA-42510 | Int Charges | 334,930.66 |
Nov 15, 2020 | IDA-42510 | Int Charges | 334,930.66 |
Nov 15, 2020 | IDA-42510 | Loan Repay | 47,412.77 |
Nov 15, 2020 | IDA-42510 | Loan Repay | 1,568,184.50 |
May 15, 2020 | IDA-42510 | Int Charges | 3,355.63 |
May 15, 2020 | IDA-42510 | Int Charges | 3,355.63 |
May 15, 2020 | IDA-42510 | Loan Repay | 3,093,976.00 |
May 15, 2020 | IDA-42510 | Int Charges | 336,469.88 |
May 15, 2020 | IDA-42510 | Int Charges | 336,469.88 |
Nov 15, 2022 | IDA-42510 | Loan Repay | 66,239.14 |
Nov 15, 2022 | IDA-42510 | Loan Repay | 2,928,912.80 |
Nov 15, 2022 | IDA-42510 | Int Charges | 239,423.42 |
Nov 15, 2022 | IDA-42510 | Int Charges | 239,423.42 |
May 15, 2022 | IDA-42510 | Int Charges | 300,992.38 |
May 15, 2022 | IDA-42510 | Int Charges | 300,992.38 |
May 15, 2022 | IDA-42510 | Loan Repay | 1,485,231.60 |
May 15, 2022 | IDA-42510 | Loan Repay | 29,036.72 |
Nov 15, 2021 | IDA-42510 | Int Charges | 13,729.50 |
Nov 15, 2021 | IDA-42510 | Int Charges | 13,729.50 |
Nov 15, 2021 | IDA-42510 | Loan Repay | 1,598,654.10 |
Dec 14, 2006 | IDA-42510 | Loan Commitment | 154,000,000.00 |
May 15, 2024 | IDA-42510 | Int Charges | 19,049.38 |
May 15, 2024 | IDA-42510 | Int Charges | 19,049.38 |
May 15, 2024 | IDA-42510 | Loan Repay | 3,011,880.50 |
May 15, 2024 | IDA-42510 | Int Charges | 259,776.95 |
May 15, 2024 | IDA-42510 | Int Charges | 259,776.95 |
May 15, 2023 | IDA-42510 | Int Charges | 257,607.50 |
May 15, 2023 | IDA-42510 | Int Charges | 257,607.50 |
May 15, 2023 | IDA-42510 | Int Charges | 53,673.02 |
May 15, 2023 | IDA-42510 | Int Charges | 53,673.02 |
May 15, 2023 | IDA-42510 | Loan Repay | 3,055,898.50 |
Nov 15, 2023 | IDA-42510 | Int Charges | 28,534.35 |
Nov 15, 2023 | IDA-42510 | Int Charges | 28,534.35 |
Nov 15, 2023 | IDA-42510 | Loan Repay | 3,018,777.00 |
Nov 15, 2023 | IDA-42510 | Int Charges | 252,599.17 |
Nov 15, 2023 | IDA-42510 | Int Charges | 252,599.17 |
Dec 15, 2014 | IDA-42510 | Loan Disb | 7,000,000.00 |
Dec 11, 2014 | IDA-42510 | Loan Disb | 1,752,205.20 |
Jun 18, 2014 | IDA-42510 | Loan Disb | 2,709,218.00 |
May 15, 2014 | IDA-42510 | Int Charges | 446,268.80 |
May 15, 2014 | IDA-42510 | Int Charges | 446,268.80 |
May 15, 2014 | IDA-42510 | Int Charges | 7,348.05 |
May 15, 2014 | IDA-42510 | Int Charges | 7,348.05 |
Mar 24, 2014 | IDA-42510 | Loan Disb | 3,531,201.80 |
Nov 15, 2013 | IDA-42510 | Int Charges | 579.04 |
Nov 15, 2013 | IDA-42510 | Int Charges | 579.04 |
Nov 15, 2013 | IDA-42510 | Int Charges | 378,667.60 |
Nov 15, 2013 | IDA-42510 | Int Charges | 378,667.60 |
Oct 3, 2013 | IDA-42510 | Loan Disb | 5,827,652.50 |
Nov 22, 2013 | IDA-42510 | Loan Disb | 3,796,080.00 |
Jan 16, 2014 | IDA-42510 | Loan Disb | 3,965,344.80 |
Feb 11, 2014 | IDA-42510 | Loan Disb | 4,142,662.20 |
Jul 10, 2013 | IDA-42510 | Loan Disb | 4,701,423.00 |
Nov 15, 2014 | IDA-42510 | Int Charges | 1,199.19 |
Nov 15, 2014 | IDA-42510 | Int Charges | 1,199.19 |
Nov 15, 2014 | IDA-42510 | Loan Repay | 3,804,999.80 |
Nov 15, 2014 | IDA-42510 | Int Charges | 456,314.62 |
Nov 15, 2014 | IDA-42510 | Int Charges | 456,314.62 |
Nov 15, 2015 | IDA-42510 | Int Charges | 128,759.26 |
Nov 15, 2015 | IDA-42510 | Int Charges | 128,759.26 |
Nov 15, 2015 | IDA-42510 | Loan Repay | 3,150,170.50 |
Nov 15, 2015 | IDA-42510 | Int Charges | 446,605.94 |
Nov 15, 2015 | IDA-42510 | Int Charges | 446,605.94 |
Jun 29, 2015 | IDA-42510 | Loan Disb | 601,705.94 |
Jun 29, 2015 | IDA-42510 | Loan Disb | 1,461,898.40 |
Jun 30, 2015 | IDA-42510 | Loan Cancel | 17,254,702.00 |
May 15, 2015 | IDA-42510 | Int Charges | 326,101.28 |
May 15, 2015 | IDA-42510 | Int Charges | 326,101.28 |
May 6, 2015 | IDA-42510 | Loan Disb | 128,568.04 |
May 15, 2015 | IDA-42510 | Loan Repay | 103,760.65 |
May 15, 2015 | IDA-42510 | Loan Repay | 3,576,181.80 |
Jun 29, 2015 | IDA-42510 | Loan Disb | 472,853.90 |
Aug 11, 2014 | IDA-42510 | Loan Disb | 1,171,012.20 |
May 15, 2017 | IDA-42510 | Loan Repay | 96,124.20 |
May 15, 2017 | IDA-42510 | Int Charges | 355,910.00 |
May 15, 2017 | IDA-42510 | Int Charges | 355,910.00 |
May 15, 2017 | IDA-42510 | Loan Repay | 3,022,819.50 |
Nov 15, 2016 | IDA-42510 | Int Charges | 43,155.88 |
Nov 15, 2016 | IDA-42510 | Loan Repay | 3,103,444.20 |
Nov 15, 2016 | IDA-42510 | Int Charges | 418,964.94 |
Nov 15, 2016 | IDA-42510 | Int Charges | 418,964.94 |
Nov 15, 2016 | IDA-42510 | Int Charges | 43,155.88 |
May 15, 2016 | IDA-42510 | Loan Repay | 71,114.86 |
May 15, 2016 | IDA-42510 | Loan Repay | 3,140,257.50 |
May 15, 2016 | IDA-42510 | Int Charges | 400,921.20 |
May 15, 2016 | IDA-42510 | Int Charges | 400,921.20 |
May 15, 2018 | IDA-42510 | Loan Repay | 3,222,314.80 |
Nov 15, 2018 | IDA-42510 | Loan Repay | 64,120.51 |
Nov 15, 2017 | IDA-42510 | Int Charges | 410,021.66 |
Nov 15, 2017 | IDA-42510 | Int Charges | 410,021.66 |
Nov 15, 2017 | IDA-42510 | Int Charges | 55,112.22 |
Nov 15, 2017 | IDA-42510 | Int Charges | 55,112.22 |
Nov 15, 2017 | IDA-42510 | Loan Repay | 3,215,856.00 |
Nov 15, 2019 | IDA-42510 | Int Charges | 348,550.84 |
Nov 15, 2019 | IDA-42510 | Int Charges | 348,550.84 |
Nov 15, 2019 | IDA-42510 | Loan Repay | 3,102,907.00 |
Nov 15, 2019 | IDA-42510 | Loan Repay | 25,482.10 |
May 15, 2019 | IDA-42510 | Int Charges | 365,744.28 |
May 15, 2019 | IDA-42510 | Int Charges | 365,744.28 |
May 15, 2019 | IDA-42510 | Loan Repay | 53,608.06 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2015-02-04 |
Overall Implementation Progress (IP) | Satisfactory | 2015-02-04 |
Project Management | Satisfactory | 2015-02-04 |
Procurement | Satisfactory | 2015-02-04 |
Monitoring and Evaluation | Moderately Satisfactory | 2015-02-04 |
Progress towards achievement of PDO | Satisfactory | 2015-02-04 |
Financial Management | Satisfactory | 2015-02-04 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-24-2015 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Negligible |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 06-22-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Negligible To Low | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% of habitations in the rural areas of the state (and each district) who are FC | Value | FC - estimated 41% adapted from the habitation sur | 89% | 77% |
Date | August 1, 2008 | December 30, 2014 | December 31, 2014 | |
Comment |
% of rural households in the state (and each district) with access to safe and adequate water throughout the year | Value | 30.3% | 63.8% | 90% |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
% of participating habitations having satisfactorily performing community sanitation facilities | Value | Nil | 81.7% | 90% |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Number of other water service providers that the project is supporting | Value | 0.00 | 2005.00 | 1200.00 |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 688.00 | 214.00 |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 400648.00 | 348300.00 |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Value | 0.00 | 98045.00 | 39300.00 |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Number of people in rural areas provided with access to Improved Water Sources under the project | Value | 0.00 | 2458203.00 | 2280000.00 |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component 1: Program Management: Participating habitations for schemes under SWAp as a % of total habitations with a NC or PC status (cumulative habitations covered) | Value | Not applicable | 58% | 26% |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Component 1: Program Management: Participating habitations for performance improvements of existing SV/MV schemes as a % of total habitations planned to be covered (cumulative habitations covered) | Value | Not applicable. New Scheme database | 291% | 100% |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Component 1: Program Management: % of resources disbursed to participating GPs that are utilized in time in relation to implementation phase of scheme cycle | Value | Not applicable. New scheme database | na | 100% |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Component 2: Community Development Support: % of participating GPs/GPWSCs with high or medium rating for operational sustainabilityof their schemes | Value | Establish baseline in the first year. | 70.58% | 90% |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Component 2: Community Development Support: % of participating GPWSCs meeting the full O&M costs through user charges | Value | Not applicabale | 71.31% | 100% |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Component 3: Infrastructure Development: % of water schemes under SWAp completed within planned time and costs | Value | Not applicable. | 85% | 100% |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Component 3: Infrastructure Development: % of participating GPWSCs achieving planned performance improvements measured 6 months after completion | Value | Not applicable | 95% | 95% |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |
Component 3 : Infrastructure Development: % of new community sanitation schemes completed within planned time and costs | Value | Not applicable | 97% | 95% |
Date | January 1, 2007 | December 30, 2014 | December 31, 2014 | |
Comment |