Skip to Main Navigation

IN Punjab Rural Water Supply and Sanitation

Abstract*

The Punjab Rural Water Supply and Sanitation Project objective is to assist the Government of Punjab (GoP) in increasing access of rural communities to improved and sustainable rural water supply and sanitation (RWSS) services. There are three componebts of the project. The first component will finance the establishment and operating costs of the program institutions and training, consultancies, and goods and equipment. The second component will finance...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Increase access of rural communities to improved and sustainable Rural Water Supply and Sanitation Services

Key Details

Project Details

  • P090592

  • Closed

  • Srinivasa Podipireddy

  • DEA, Ministry of Finance

  • India

  • June 17, 2005

  • (as of board presentation)

    December 14, 2006

  • March 26, 2007

  • US$ 339.00 million

  • Department of Water Supply and Sanitation

  • South Asia

  • 2007

  • US$ 154.00 million

  • B

  • June 24, 2015

  • December 31, 2014

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Communities 15.00
IDA Credit 154.00
Local Govts. (Prov., District, City) of Borrowing Country 95.00
Borrower/Recipient 75.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 154.00
IBRD + IDA Commitment 154.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 339.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 15, 2019 IDA-42510 Loan Repay 3,092,579.50
Nov 15, 2018 IDA-42510 Loan Repay 3,080,565.00
Nov 15, 2018 IDA-42510 Int Charges 377,362.25
Nov 15, 2018 IDA-42510 Int Charges 377,362.25
May 15, 2018 IDA-42510 Int Charges 402,265.90
May 15, 2018 IDA-42510 Int Charges 402,265.90
May 15, 2018 IDA-42510 Loan Repay 28,318.50
Nov 15, 2021 IDA-42510 Int Charges 323,760.75
Nov 15, 2021 IDA-42510 Int Charges 323,760.75
May 15, 2021 IDA-42510 Int Charges 4,436.66
May 15, 2021 IDA-42510 Int Charges 4,436.66
May 15, 2021 IDA-42510 Loan Repay 1,637,080.60
May 15, 2021 IDA-42510 Int Charges 323,622.50
May 15, 2021 IDA-42510 Int Charges 323,622.50
Nov 15, 2020 IDA-42510 Int Charges 334,930.66
Nov 15, 2020 IDA-42510 Int Charges 334,930.66
Nov 15, 2020 IDA-42510 Loan Repay 47,412.77
Nov 15, 2020 IDA-42510 Loan Repay 1,568,184.50
May 15, 2020 IDA-42510 Int Charges 3,355.63
May 15, 2020 IDA-42510 Int Charges 3,355.63
May 15, 2020 IDA-42510 Loan Repay 3,093,976.00
May 15, 2020 IDA-42510 Int Charges 336,469.88
May 15, 2020 IDA-42510 Int Charges 336,469.88
Nov 15, 2022 IDA-42510 Loan Repay 66,239.14
Nov 15, 2022 IDA-42510 Loan Repay 2,928,912.80
Nov 15, 2022 IDA-42510 Int Charges 239,423.42
Nov 15, 2022 IDA-42510 Int Charges 239,423.42
May 15, 2022 IDA-42510 Int Charges 300,992.38
May 15, 2022 IDA-42510 Int Charges 300,992.38
May 15, 2022 IDA-42510 Loan Repay 1,485,231.60
May 15, 2022 IDA-42510 Loan Repay 29,036.72
Nov 15, 2021 IDA-42510 Int Charges 13,729.50
Nov 15, 2021 IDA-42510 Int Charges 13,729.50
Nov 15, 2021 IDA-42510 Loan Repay 1,598,654.10
Dec 14, 2006 IDA-42510 Loan Commitment 154,000,000.00
May 15, 2024 IDA-42510 Int Charges 19,049.38
May 15, 2024 IDA-42510 Int Charges 19,049.38
May 15, 2024 IDA-42510 Loan Repay 3,011,880.50
May 15, 2024 IDA-42510 Int Charges 259,776.95
May 15, 2024 IDA-42510 Int Charges 259,776.95
May 15, 2023 IDA-42510 Int Charges 257,607.50
May 15, 2023 IDA-42510 Int Charges 257,607.50
May 15, 2023 IDA-42510 Int Charges 53,673.02
May 15, 2023 IDA-42510 Int Charges 53,673.02
May 15, 2023 IDA-42510 Loan Repay 3,055,898.50
Nov 15, 2023 IDA-42510 Int Charges 28,534.35
Nov 15, 2023 IDA-42510 Int Charges 28,534.35
Nov 15, 2023 IDA-42510 Loan Repay 3,018,777.00
Nov 15, 2023 IDA-42510 Int Charges 252,599.17
Nov 15, 2023 IDA-42510 Int Charges 252,599.17
Dec 15, 2014 IDA-42510 Loan Disb 7,000,000.00
Dec 11, 2014 IDA-42510 Loan Disb 1,752,205.20
Jun 18, 2014 IDA-42510 Loan Disb 2,709,218.00
May 15, 2014 IDA-42510 Int Charges 446,268.80
May 15, 2014 IDA-42510 Int Charges 446,268.80
May 15, 2014 IDA-42510 Int Charges 7,348.05
May 15, 2014 IDA-42510 Int Charges 7,348.05
Mar 24, 2014 IDA-42510 Loan Disb 3,531,201.80
Nov 15, 2013 IDA-42510 Int Charges 579.04
Nov 15, 2013 IDA-42510 Int Charges 579.04
Nov 15, 2013 IDA-42510 Int Charges 378,667.60
Nov 15, 2013 IDA-42510 Int Charges 378,667.60
Oct 3, 2013 IDA-42510 Loan Disb 5,827,652.50
Nov 22, 2013 IDA-42510 Loan Disb 3,796,080.00
Jan 16, 2014 IDA-42510 Loan Disb 3,965,344.80
Feb 11, 2014 IDA-42510 Loan Disb 4,142,662.20
Jul 10, 2013 IDA-42510 Loan Disb 4,701,423.00
Nov 15, 2014 IDA-42510 Int Charges 1,199.19
Nov 15, 2014 IDA-42510 Int Charges 1,199.19
Nov 15, 2014 IDA-42510 Loan Repay 3,804,999.80
Nov 15, 2014 IDA-42510 Int Charges 456,314.62
Nov 15, 2014 IDA-42510 Int Charges 456,314.62
Nov 15, 2015 IDA-42510 Int Charges 128,759.26
Nov 15, 2015 IDA-42510 Int Charges 128,759.26
Nov 15, 2015 IDA-42510 Loan Repay 3,150,170.50
Nov 15, 2015 IDA-42510 Int Charges 446,605.94
Nov 15, 2015 IDA-42510 Int Charges 446,605.94
Jun 29, 2015 IDA-42510 Loan Disb 601,705.94
Jun 29, 2015 IDA-42510 Loan Disb 1,461,898.40
Jun 30, 2015 IDA-42510 Loan Cancel 17,254,702.00
May 15, 2015 IDA-42510 Int Charges 326,101.28
May 15, 2015 IDA-42510 Int Charges 326,101.28
May 6, 2015 IDA-42510 Loan Disb 128,568.04
May 15, 2015 IDA-42510 Loan Repay 103,760.65
May 15, 2015 IDA-42510 Loan Repay 3,576,181.80
Jun 29, 2015 IDA-42510 Loan Disb 472,853.90
Aug 11, 2014 IDA-42510 Loan Disb 1,171,012.20
May 15, 2017 IDA-42510 Loan Repay 96,124.20
May 15, 2017 IDA-42510 Int Charges 355,910.00
May 15, 2017 IDA-42510 Int Charges 355,910.00
May 15, 2017 IDA-42510 Loan Repay 3,022,819.50
Nov 15, 2016 IDA-42510 Int Charges 43,155.88
Nov 15, 2016 IDA-42510 Loan Repay 3,103,444.20
Nov 15, 2016 IDA-42510 Int Charges 418,964.94
Nov 15, 2016 IDA-42510 Int Charges 418,964.94
Nov 15, 2016 IDA-42510 Int Charges 43,155.88
May 15, 2016 IDA-42510 Loan Repay 71,114.86
May 15, 2016 IDA-42510 Loan Repay 3,140,257.50
May 15, 2016 IDA-42510 Int Charges 400,921.20
May 15, 2016 IDA-42510 Int Charges 400,921.20
May 15, 2018 IDA-42510 Loan Repay 3,222,314.80
Nov 15, 2018 IDA-42510 Loan Repay 64,120.51
Nov 15, 2017 IDA-42510 Int Charges 410,021.66
Nov 15, 2017 IDA-42510 Int Charges 410,021.66
Nov 15, 2017 IDA-42510 Int Charges 55,112.22
Nov 15, 2017 IDA-42510 Int Charges 55,112.22
Nov 15, 2017 IDA-42510 Loan Repay 3,215,856.00
Nov 15, 2019 IDA-42510 Int Charges 348,550.84
Nov 15, 2019 IDA-42510 Int Charges 348,550.84
Nov 15, 2019 IDA-42510 Loan Repay 3,102,907.00
Nov 15, 2019 IDA-42510 Loan Repay 25,482.10
May 15, 2019 IDA-42510 Int Charges 365,744.28
May 15, 2019 IDA-42510 Int Charges 365,744.28
May 15, 2019 IDA-42510 Loan Repay 53,608.06

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2015-02-04
Overall Implementation Progress (IP) Satisfactory 2015-02-04
Project Management Satisfactory 2015-02-04
Procurement Satisfactory 2015-02-04
Monitoring and Evaluation Moderately Satisfactory 2015-02-04
Progress towards achievement of PDO Satisfactory 2015-02-04
Financial Management Satisfactory 2015-02-04

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-24-2015
OutcomesModerately Satisfactory
Risk to Development OutcomeNegligible
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-22-2016PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeNegligible To LowN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • % of habitations in the rural areas of the state (and each district) who are FCValueFC - estimated 41% adapted from the habitation sur89%77%
    DateAugust 1, 2008December 30, 2014December 31, 2014
    Comment
  • % of rural households in the state (and each district) with access to safe and adequate water throughout the yearValue30.3%63.8%90%
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • % of participating habitations having satisfactorily performing community sanitation facilitiesValueNil81.7%90%
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Number of other water service providers that the project is supportingValue0.002005.001200.00
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Improved community water points constructed or rehabilitated under the projectValue0.00688.00214.00
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • New piped household water connections that are resulting from the project interventionValue0.00400648.00348300.00
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Piped household water connections that are benefiting from rehabilitation works undertaken by the projectValue0.0098045.0039300.00
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Number of people in rural areas provided with access to Improved Water Sources under the projectValue0.002458203.002280000.00
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component 1: Program Management: Participating habitations for schemes under SWAp as a % of total habitations with a NC or PC status (cumulative habitations covered)ValueNot applicable58%26%
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Component 1: Program Management: Participating habitations for performance improvements of existing SV/MV schemes as a % of total habitations planned to be covered (cumulative habitations covered)ValueNot applicable. New Scheme database291%100%
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Component 1: Program Management: % of resources disbursed to participating GPs that are utilized in time in relation to implementation phase of scheme cycleValueNot applicable. New scheme databasena100%
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Component 2: Community Development Support: % of participating GPs/GPWSCs with high or medium rating for operational sustainabilityof their schemesValueEstablish baseline in the first year.70.58%90%
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Component 2: Community Development Support: % of participating GPWSCs meeting the full O&M costs through user chargesValueNot applicabale71.31%100%
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Component 3: Infrastructure Development: % of water schemes under SWAp completed within planned time and costsValueNot applicable.85%100%
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Component 3: Infrastructure Development: % of participating GPWSCs achieving planned performance improvements measured 6 months after completionValueNot applicable95%95%
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment
  • Component 3 : Infrastructure Development: % of new community sanitation schemes completed within planned time and costsValueNot applicable97%95%
    DateJanuary 1, 2007December 30, 2014December 31, 2014
    Comment