Lao Environment and Social Project

Abstract*

The Lao Environment and Social Project (LENS) for Lao PDR aims to strengthen the management of environmental and social issues associated with the sustainable use of natural resources. The project has three components: 1) The Policy Implementation and Capacity Enhancement component, which strengthens institutions and instruments for assessment, monitoring, and compliance for environmental and social sustainability, and broadens the constituency for...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To strengthen the management of environmental and social issues associated with the sustainable use of natural resources in Lao PDR.

Key Details

Project Details

  • P090693

  • Closed

  • Jean-Michel Pavy

  • N/A

  • US$ 7.00 million

  • B

  • Not Applicable

  • June 30, 2013

  • BANK APPROVED

  • December 3, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 3.00
Borrower/Recipient 0.80
IDA GRANT FOR DEBT VULNERABLE 4.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 7.00
IBRD + IDA Commitment 7.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 7.80

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 30, 2005 IDA-H1770 Loan Commitment 4,000,000.00
Jan 12, 2010 IDA-H5400 Loan Commitment 3,000,000.00
Nov 5, 2013 IDA-H5400 Loan Cancel 8,470.29
Nov 5, 2013 IDA-H5400 Loan Disb -6,798.37
Oct 31, 2013 IDA-H1770 Loan Cancel 3.95

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2013-07-11
Monitoring and Evaluation Satisfactory 2013-07-11
Progress towards achievement of PDO Moderately Satisfactory 2013-07-11
Financial Management Moderately Satisfactory 2013-07-11
Procurement Satisfactory 2013-07-11
Project Management Moderately Satisfactory 2013-07-11
Overall Implementation Progress (IP) Moderately Satisfactory 2013-07-11

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-29-2013
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceSubstantial
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-09-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increase in the % of environment compliance certificates (ECCs) issued by WREA that are of adequate quality as judged by a third party annually starting June 2010Value60.0080.0080.00
    DateJune 30, 2010June 14, 2013June 30, 2013
    CommentOne CA singed in 2012 has included SESO, discussion going on. To date, means of five CAs signed since 2010, four or 80% hydropowerprojects have included SESO.Met
  • Increase in the % of complaints resolved in Bolikhamxay and Khammouane Provinces.Value0.0098.0098.00
    DateJune 4, 2010June 14, 2013June 30, 2013
    CommentData suggested that 96% (229 of 238) in BLKX and 100% (280) in Khammouane complaints have been resolved through this mechanismMet
  • Grievances registered related to delivery of project benefits addressed (%)Value50.0098.0098.00
    DateJune 4, 2010June 14, 2013June 30, 2013
    CommentIncrease in the % of complaints resolved in Bolikhamxay (96%) and Khammouane (100%) ProvincesMet.
  • Grievances related to delivery of project benefits that are addressed-(number)Value0.00509.00509.00
    DateJune 4, 2010June 14, 2013June 30, 2013
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • By December 31, 2010, database for tracking type and number of development projects in the Selected Provinces is established.Value0.002.002.00
    DateDecember 18, 2009June 14, 2013June 30, 2013
    CommentEstablished in two project provinces.Met
  • By December 31, 2012, a unit responsible for monitoring social impacts and a functional complaint handling mechanism are established in Bolikhamxay and Khammouane Provinces.Value0.002.002.00
    DateJune 30, 2010June 14, 2013June 30, 2013
    CommentSIMUs were established in BLKX and KM provinces. The provincial governor has issued legal letter to map SIMU under PoNRE.Met
  • By June 30, 2010, the River Basin Committee for NT-NKD is established.Value0.001.001.00
    DateOctober 11, 2010June 14, 2013June 30, 2013
    CommentMet. One RBC was established. Further capacity building is needed.Met
  • By December 31, 2012, an implementation model for a river basin organization in Lao PDR is developed.Value0.001.001.00
    DateOctober 11, 2010June 14, 2013June 30, 2013
    CommentNo model availableA model was established. It was indicated in the project completion report.Met
  • WREA has prepared guidelines for incorporating ECC measures in Concession Agreement for hydropower projects signed by Recipient after enactment of the Environment and Social Impact Assessment decreeValue0.001.001.00
    DateDecember 18, 2009June 14, 2013June 30, 2013
    CommentNo guidelineFour of five CAs signed since 2010 for ongoing hydropowere project has incorporated SESO. One is in progress.Met
  • Social safeguard training program is developed for agencies and provinces participating in the Project and at least 60 trainees aretrainedValue0.00150.00150.00
    DateDecember 18, 2009June 14, 2013June 30, 2013
    CommentTraining completed. More than 150 trainees were trained.Met
  • By December 31, 2012 national guideline for Ethnic Groups' consultation has been completed and the relevant agencies' staff have been trained on how to conduct such consultation.Value0.001.001.00
    DateDecember 18, 2009June 14, 2013June 30, 2013
    CommentNo guidelines; no staff trainedThe guideline is approved and and consultation is completed. Additional training will be provided to southern provinces.Met
  • By December 31, 2010, site plans for 6 protected areas are available and the site plans have identified priority actions.Value0.006.006.00
    DateDecember 18, 2009June 14, 2013June 30, 2013
    CommentNo site plans6 site plans completedMet
  • By December 31, 2012, at least 60% of the priority activities identified are being implemented in the 6 protected areas.Value0.0020.0020.00
    DateDecember 18, 2009June 14, 2013June 30, 2013
    CommentNo site plansThe implementation of is planned under the new LEnS II project.Not met, on going
  • By December 31, 2012, at least 10 conservation communities are established in NT-NKDValue0.0012.0012.00
    DateDecember 18, 2009June 14, 2013June 30, 2013
    CommentNo Community Conservation UnitCommunity Conservation Network was established in 12 communities.Met
  • EPF and WREA have received part of the NT2 revenue for financing their respective priority development projects by December 31, 2010.Value0.001.501.50
    DateDecember 18, 2009June 14, 2013June 30, 2013
    CommentNone receivedThe discussion is ongoing, but it could be only partially met by the end of the project. 3% (3billion LAK) of received forenvironment sector, which is 50% (1.5billion LAK) goes to MoNRE, but not received by EPF.Partially met
  • 80% of Sub-projects financed by the Original Grant have been completed satisfactorily by December 31, 2010.Value80.0099.0099.00
    DateMay 4, 2010June 14, 2013June 30, 2013
    CommentN/AOf 154 total subgrants signed under LENs, 152 subgrants (98.7%) were completed.Met
  • By December 31, 2012, EPF's annual administrative cost (about 33% of a Sub-grant amount) has been reduced to no more than 15% of anAdditional GrantValue33.0013.0015.00
    DateDecember 18, 2009June 14, 2013June 30, 2013
    Comment33%WMU budget is about $0.44 million (14.66%) for $3.0 million total grant.Met
  • 80% of Sub-projects financed by the Additional Grant have been completed satisfactorily by December 31, 2012.Value80.0084.0089.44
    DateDecember 18, 2009June 14, 2013June 30, 2013
    Comment0%Of 19 subgrants, 17 or 89.44% closed, two will be completed by the end of JuneMet
  • Areas brought under enhanced biodiversity protection (ha)Value0.00169000.00169000.00
    DateJune 4, 2010June 14, 2013June 30, 2013
    CommentNo management planManagement plans have been developed for six provincial protected areas in three project target provinces. The value in ha is168,993Ha.Met
  • Sub-projects with post-project community engagement or O&M arrangements (%)Value0.00173.00173.00
    DateJune 4, 2010June 14, 2013June 30, 2013
    CommentNo subprojects planned,173 sub-projects signed, 171 completed, two will be completed by June 30.Met
  • Sub-projects that are expected to have a mechanism for post-completion operationValue0.0017.0019.00
    DateJune 4, 2010June 14, 2013June 30, 2013
    Comment