Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 1.50 |
P090884
Closed
David A. Bontempo
N/A
June 24, 2005
(as of board presentation)
March 2, 2006
March 16, 2006
US$ 1.50 million
N/A
2006
US$ 1.50 million
C
January 15, 2013
June 30, 2008
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 1.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 1.50 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 1.50 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 1.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 3, 2006 | IBRD-73640 | Loan Commitment | 1,500,000.00 |
INDICATOR | ICR REVIEW: 07-28-2007 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Not Rated | N/a |
Risk To Development Outcome | Not Rated | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Non-evaluable | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Permanent Institutional capacity for policy making of Leader Axis in MoA, and other local bodies involved. | Value | Limited Institutional capacity | Project just beginning - too early to evaluate | Key staff in central MoAg, as well as local admini |
Date | February 1, 2006 | July 1, 2006 | December 3, 2007 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Staff of MoA and its subordinate organizations, and of local level institutions have the capacity to develop efficient system of implementing Leader Axis | Value | Limited capacity | Project just beginning - too early to evaluate | Newly trained staff are in post and contributing t |
Date | February 1, 2006 | July 1, 2006 | December 3, 2007 | |
Comment |