Financier | Commitments |
---|---|
Borrower/Recipient | 0.30 |
IDA Grant | 60.00 |
Local Sources of Borrowing Country | 17.11 |
P090967
Closed
Mohan Aryal
N/A
March 9, 2005
(as of board presentation)
February 22, 2007
July 27, 2007
US$ 77.41 million
N/A
2007
US$ 60.00 million
C
Not Applicable
June 30, 2014
BANK APPROVED
September 6, 2022
Financier | Commitments |
---|---|
Borrower/Recipient | 0.30 |
IDA Grant | 60.00 |
Local Sources of Borrowing Country | 17.11 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 60.00 |
IBRD + IDA Commitment | 60.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 77.41 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 12, 2014 | IDA-H2740 | Loan Disb | 3,160,204.50 |
Dec 19, 2013 | IDA-H2740 | Loan Disb | 1,567,764.10 |
Aug 12, 2013 | IDA-H2740 | Loan Disb | 2,563,833.00 |
Aug 12, 2013 | IDA-H2740 | Loan Disb | 847,926.06 |
Aug 1, 2013 | IDA-H2740 | Loan Disb | 545,375.06 |
Oct 31, 2014 | IDA-H2740 | Loan Cancel | 117,287.52 |
Aug 8, 2013 | IDA-H2740 | Loan Disb | 2,031,095.10 |
Oct 31, 2014 | IDA-H2740 | Loan Disb | 82,356.95 |
Jul 30, 2014 | IDA-H2740 | Loan Disb | 2,217,583.20 |
Jul 22, 2014 | IDA-H2740 | Loan Disb | 574,743.70 |
Aug 5, 2014 | IDA-H2740 | Loan Disb | 2,913,346.00 |
Apr 10, 2014 | IDA-H2740 | Loan Disb | 1,052,541.40 |
Jun 16, 2014 | IDA-H2740 | Loan Disb | 2,181,598.80 |
Feb 22, 2007 | IDA-H2740 | Loan Commitment | 60,000,000.00 |
Apr 16, 2014 | IDA-H2740 | Loan Disb | 1,314,312.60 |
Mar 7, 2014 | IDA-H2740 | Loan Disb | 973,060.56 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2014-06-24 |
Monitoring and Evaluation | Satisfactory | 2014-06-24 |
Overall Implementation Progress (IP) | Satisfactory | 2014-06-24 |
Financial Management | Moderately Satisfactory | 2014-06-24 |
Progress towards achievement of PDO | Satisfactory | 2014-06-24 |
Procurement | Satisfactory | 2014-06-24 |
Project Management | Satisfactory | 2014-06-24 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-30-2014 |
---|---|
Outcomes | |
Risk to Development Outcome | Moderately Satisfactory |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 08-28-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of Institutions accredited | Value | 0.00 | 12.00 | 6.00 |
Date | July 27, 2007 | May 30, 2014 | June 30, 2014 | |
Comment | Project effective from July 27, 2007 facilitated the establishment of an Accreditation system in Nepal | Target exceeded. |
Student pass rates at bachelors levels in participating institutions | Value | 32.60 | 29.33 | 36.00 |
Date | February 18, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | Figures from 2008/09 exam results | Will not meet the target. Lower rate due to very rapid expansion of HE system and highly centralized examinations |
Student pass rates at masters levels in participating institutions | Value | 22.30 | 24.83 | 26.00 |
Date | February 18, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | Figures from 2008/09 exam results | Average pass rate of 2011/12 |
Share of students enrolled in science, technology, management, and other employment/economic development focused programs in participating higher education institutions | Value | 34.63 | 38.40 | 39.00 |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | Figures from 2009/10 enrollment | The figure also includes (a) 1,589 students enrolled in the new window programs and (b) 3,177 students enrolled in the recentlytransformed to the semester system of TU central departments |
Total enrollment in participating higher education institutions | Value | 74012.00 | 93690.00 | 80000.00 |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | HE data refers to participating institutions as of 2009/2010 (47 community campuses, 10 TU constituent campuses & 3 smalluniversities | Target exceeded. Enrollment in 47 community campuses (Scheme A, B and C), 10 TU decentralized campuses, and 3 universities as inthe baseline data. |
Share of girls enrollment in participating higher education institutions | Value | 42.97 | 47.43 | 44.00 |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | Figures from 2009/10 enrollment | Target exceeded. |
Share of enrollment from dalits and educationally disadvantaged Janajatis in participating higher education institutions | Value | 12.88 | 18.87 | 13.50 |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | Figures from 2009/10 enrollment | Target exceeded. |
Total enrollment in participating higher secondary schools | Value | 48000.00 | 210100.00 | 163000.00 |
Date | July 27, 2007 | May 30, 2014 | June 30, 2014 | |
Comment | Total enrollment in community higher secondary schools (CHSSs) | Target exceeded. This figure is based on the latest DOE EMIS data (Flash I, 2013-14). | Target revised in the MTR. |
Share of girls enrollment in participating higher secondary schools | Value | 34.00 | 50.00 | 50.00 |
Date | July 3, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | Initial baseline, which was calculated from total enrollment in CHSSs. Girls average share in total (above figures) was equivalentto that of participating schools | Target reached and maintained. | Not less than 50%. The original target was 43%. |
Share of enrollment from dalits and educationally disadvantaged Janajatis in participating higher secondary schools | Value | 5.80 | 7.02 | 6.20 |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | Figures from 2009/10 enrollment | Target exceeded. The current figures are based on the latest DOE EMIS data (Flash I 2013-14), where highly marginalized janajatisare not reported. | Original target: Dalits:5%;Disadvantaged janajatis: 8%. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of TU autonomous campuses | Value | 0.00 | 4.00 | 3.00 |
Date | July 27, 2007 | May 30, 2014 | June 30, 2014 | |
Comment | Revised target met. | Original target of 6 was reduced to 3 when the project was restructured in March 2011. |
Number of TU decentralized campuses | Value | 38.00 | 49.00 | 45.00 |
Date | July 27, 2007 | May 30, 2014 | June 30, 2014 | |
Comment | Target met. This includes 4 autonomous campuses that completed the decentralization as a requirement for opting autonomy. | Original target of 48 was reduced to 45 when the project was restructured in March 2011. |
Number of community campuses getting project support | Value | 0.00 | 89.00 | 90.00 |
Date | July 27, 2007 | May 30, 2014 | June 30, 2014 | |
Comment | One campus dropped as it could not meet the criteria. | Original EOP target was 10. Target was revised due to high demand when the project was restructured in March 2011. |
Number of publications in refereed journals by the research grant recipients in approved research areas | Value | 0.00 | 27.00 | 20.00 |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | New indicator | Additional 45 have been published in professional journals, 6 have been presented in international conferences. Other publicationsare in pipeline. |
Number of new programs in science, technology, management, and other employment/economic development focused programs in participating institutions | Value | 0.00 | 28.00 | 20.00 |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | New indicator | Target exceeded. 31 Central Departments of TU have started 38 Master programs in semester system – features of these programs aresimilar to window programs. |
Number of students receiving financial assistance from the Fund at Higher Education level | Value | 0.00 | 7192.00 | 3500.00 |
Date | July 27, 2007 | May 30, 2014 | June 30, 2014 | |
Comment | Target exceeded. |
Number of students receiving financial assistance from the Fund at Higher Secondary Education level | Value | 0.00 | 7391.00 | 4300.00 |
Date | July 27, 2007 | May 30, 2014 | June 30, 2014 | |
Comment | Target exceeded. |
Enrollment in community higher secondary schools | Value | 48000.00 | 293075.00 | 256000.00 |
Date | July 27, 2007 | May 30, 2014 | January 15, 2014 | |
Comment | Target exceeded. These figures are from MOE/DOE latest EMIS (Flash I, 2013/14). | Target revised from 68000 in the MTR |
Share of enrollment in the science stream in participating community higher secondary schools | Value | 2.37 | 2.89 | 2.60 |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | New indicator. These figures are from 2009/10 enrollment data | Target met. Based on exam appeared data, share of science students enrollment at Higher Secondary level in total is around 14%,based on pass rate, the figure is around 22%. |
Quality Assurance and Accreditation System functional | Value | No | Yes | Yes |
Date | July 27, 2007 | May 30, 2014 | June 30, 2014 | |
Comment | QAA system within UGC is functional. UGC has submitted concept paper and draft Bill to MOE for the establishment of an independentNational Accreditation Board. |
Publication of EMIS reports based on functioning EMIS software/database with campus-level data | Value | No | Yes | Yes |
Date | July 27, 2007 | May 30, 2014 | June 30, 2014 | |
Comment | Sixth issue of EMIS Report published in May 2014; web-based Report of the same issue is also ready for publication. |
Admissions, exams, and publication of exam results at TU follow published calendar | Value | 0.00 | 57.00 | 100.00 |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | New indicator | Share (%) of TU centrally run programs that followed academic calendar. Some improvements observed because of the semester systemTU has started at the Central Department |
Autonomy packages for Decentralized Campuses developed by TU | Value | 0.00 | 9.00 | 10.00 |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | New indicator |
Comprehensive higher education policy developed and adopted by government | Value | Not developed | Policy submitted to MoE | Adopted |
Date | July 30, 2010 | May 30, 2014 | June 30, 2014 | |
Comment | New indicator | GON approval awaited |