Financier | Commitments |
---|---|
Borrower/Recipient | 161.68 |
IDA Credit | 225.00 |
P091077
Closed
Haileyesus Mengesha
Ministry of Finance and Economic Development
February 21, 2007
(as of board presentation)
May 31, 2007
August 21, 2007
US$ 386.68 million
Ethiopian Roads Authority
2007
US$ 225.00 million
A
Not Applicable
June 30, 2015
BANK APPROVED
July 15, 2021
Financier | Commitments |
---|---|
Borrower/Recipient | 161.68 |
IDA Credit | 225.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 225.00 |
IBRD + IDA Commitment | 225.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 386.68 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 15, 2022 | IDA-43150 | Loan Repay | 1,929,494.50 |
May 15, 2022 | IDA-43150 | Int Charges | 672,871.30 |
May 15, 2022 | IDA-43150 | Int Charges | 672,871.30 |
May 31, 2007 | IDA-43150 | Loan Commitment | 225,000,000.00 |
May 21, 2024 | IDA-43150 | Int Charges | 640,519.90 |
May 21, 2024 | IDA-43150 | Int Charges | 640,519.90 |
May 21, 2024 | IDA-43150 | Int Charges | 21,905.67 |
May 21, 2024 | IDA-43150 | Int Charges | 21,905.67 |
May 21, 2024 | IDA-43150 | Loan Repay | 1,963,279.20 |
May 21, 2024 | IDA-43150 | Int Charges | 818.03 |
May 21, 2024 | IDA-43150 | Int Charges | 818.03 |
Dec 5, 2023 | IDA-43150 | Int Charges | 22,710.41 |
Dec 5, 2023 | IDA-43150 | Int Charges | 22,710.41 |
Dec 5, 2023 | IDA-43150 | Loan Repay | 1,970,317.20 |
Dec 5, 2023 | IDA-43150 | Int Charges | 628,220.50 |
Dec 5, 2023 | IDA-43150 | Int Charges | 628,220.50 |
May 15, 2023 | IDA-43150 | Int Charges | 641,032.30 |
May 15, 2023 | IDA-43150 | Int Charges | 641,032.30 |
Nov 15, 2013 | IDA-43150 | Int Charges | 2,469.10 |
Feb 21, 2014 | IDA-43150 | Loan Disb | 1,745,764.10 |
Mar 13, 2014 | IDA-43150 | Loan Disb | 7,412,425.50 |
May 15, 2014 | IDA-43150 | Int Charges | 9,975.40 |
May 15, 2014 | IDA-43150 | Int Charges | 9,975.40 |
May 15, 2014 | IDA-43150 | Int Charges | 800,197.90 |
May 15, 2014 | IDA-43150 | Int Charges | 800,197.90 |
Apr 4, 2014 | IDA-43150 | Loan Disb | 5,996,198.00 |
May 12, 2014 | IDA-43150 | Loan Disb | 618,782.20 |
Jan 16, 2014 | IDA-43150 | Loan Disb | 261,169.75 |
Jan 16, 2014 | IDA-43150 | Loan Disb | 9,363,668.00 |
Sep 26, 2013 | IDA-43150 | Loan Disb | 5,728,494.00 |
Nov 15, 2014 | IDA-43150 | Int Charges | 690.15 |
Nov 15, 2014 | IDA-43150 | Int Charges | 690.15 |
Nov 15, 2014 | IDA-43150 | Int Charges | 811,438.44 |
Nov 15, 2014 | IDA-43150 | Int Charges | 811,438.44 |
Dec 19, 2014 | IDA-43150 | Loan Disb | 813,048.75 |
Aug 23, 2013 | IDA-43150 | Loan Disb | 1,972,881.00 |
Jul 22, 2013 | IDA-43150 | Loan Disb | 6,290,007.50 |
Nov 15, 2015 | IDA-43150 | Int Charges | 24,491.06 |
Nov 15, 2015 | IDA-43150 | Int Charges | 769,992.60 |
Nov 15, 2015 | IDA-43150 | Int Charges | 769,992.60 |
Dec 8, 2015 | IDA-43150 | Loan Disb | -264,195.38 |
May 15, 2015 | IDA-43150 | Int Charges | 19,769.32 |
May 15, 2015 | IDA-43150 | Int Charges | 19,769.32 |
May 15, 2015 | IDA-43150 | Int Charges | 742,353.40 |
May 15, 2015 | IDA-43150 | Int Charges | 742,353.40 |
Nov 15, 2013 | IDA-43150 | Int Charges | 690,346.00 |
Nov 15, 2013 | IDA-43150 | Int Charges | 690,346.00 |
Nov 19, 2013 | IDA-43150 | Loan Disb | 3,952,522.20 |
Nov 15, 2013 | IDA-43150 | Int Charges | 2,469.10 |
Nov 18, 2016 | IDA-43150 | Int Charges | 9,201.25 |
Nov 18, 2016 | IDA-43150 | Int Charges | 9,201.25 |
Nov 18, 2016 | IDA-43150 | Int Charges | 753,343.20 |
Nov 18, 2016 | IDA-43150 | Int Charges | 753,343.20 |
Dec 8, 2015 | IDA-43150 | Loan Disb | 264,195.38 |
Dec 16, 2015 | IDA-43150 | Loan Cancel | 737,590.70 |
Dec 14, 2015 | IDA-43150 | Loan Disb | -252,475.28 |
Dec 14, 2015 | IDA-43150 | Loan Disb | -3,117.29 |
Nov 15, 2015 | IDA-43150 | Int Charges | 24,491.06 |
Nov 15, 2017 | IDA-43150 | Int Charges | 785,075.30 |
Nov 15, 2017 | IDA-43150 | Int Charges | 785,075.30 |
Nov 15, 2017 | IDA-43150 | Int Charges | 11,893.35 |
Nov 15, 2017 | IDA-43150 | Int Charges | 11,893.35 |
Nov 15, 2017 | IDA-43150 | Loan Repay | 2,093,534.20 |
May 15, 2017 | IDA-43150 | Int Charges | 724,865.20 |
May 15, 2017 | IDA-43150 | Int Charges | 724,865.20 |
May 15, 2017 | IDA-43150 | Int Charges | 25,016.39 |
May 15, 2017 | IDA-43150 | Int Charges | 25,016.39 |
May 15, 2016 | IDA-43150 | Int Charges | 15,165.50 |
May 15, 2016 | IDA-43150 | Int Charges | 15,165.50 |
May 15, 2016 | IDA-43150 | Int Charges | 759,396.30 |
May 15, 2016 | IDA-43150 | Int Charges | 759,396.30 |
Nov 15, 2018 | IDA-43150 | Int Charges | 752,346.70 |
Nov 15, 2018 | IDA-43150 | Int Charges | 752,346.70 |
May 15, 2018 | IDA-43150 | Int Charges | 785,629.75 |
May 15, 2018 | IDA-43150 | Int Charges | 785,629.75 |
May 15, 2018 | IDA-43150 | Loan Repay | 22,237.16 |
May 15, 2018 | IDA-43150 | Loan Repay | 2,093,937.20 |
May 15, 2019 | IDA-43150 | Loan Repay | 2,005,568.80 |
May 15, 2019 | IDA-43150 | Loan Repay | 42,611.12 |
Nov 15, 2019 | IDA-43150 | Loan Repay | 2,016,326.00 |
Nov 15, 2019 | IDA-43150 | Int Charges | 0.01 |
Nov 15, 2019 | IDA-43150 | Int Charges | 0.01 |
Nov 15, 2019 | IDA-43150 | Int Charges | 730,473.25 |
Nov 15, 2019 | IDA-43150 | Int Charges | 730,473.25 |
Nov 15, 2018 | IDA-43150 | Loan Repay | 1,996,265.60 |
Nov 15, 2018 | IDA-43150 | Loan Repay | 50,936.30 |
May 15, 2021 | IDA-43150 | Int Charges | 6,457.39 |
May 15, 2021 | IDA-43150 | Int Charges | 6,457.39 |
May 15, 2021 | IDA-43150 | Loan Repay | 2,131,702.50 |
May 15, 2021 | IDA-43150 | Int Charges | 722,961.44 |
May 15, 2021 | IDA-43150 | Int Charges | 722,961.44 |
Nov 15, 2020 | IDA-43150 | Int Charges | 735,191.56 |
Nov 15, 2020 | IDA-43150 | Int Charges | 735,191.56 |
Nov 15, 2020 | IDA-43150 | Loan Repay | 37,755.90 |
Nov 15, 2020 | IDA-43150 | Loan Repay | 2,065,972.40 |
May 15, 2020 | IDA-43150 | Int Charges | 2,670.52 |
May 15, 2020 | IDA-43150 | Int Charges | 2,670.52 |
May 15, 2020 | IDA-43150 | Loan Repay | 2,014,190.00 |
May 15, 2020 | IDA-43150 | Int Charges | 717,555.20 |
May 15, 2020 | IDA-43150 | Int Charges | 717,555.20 |
Nov 15, 2021 | IDA-43150 | Int Charges | 19,989.29 |
Nov 15, 2021 | IDA-43150 | Int Charges | 19,989.29 |
Nov 15, 2021 | IDA-43150 | Loan Repay | 2,081,666.00 |
Nov 15, 2021 | IDA-43150 | Int Charges | 718,174.75 |
Nov 15, 2021 | IDA-43150 | Int Charges | 718,174.75 |
Nov 15, 2022 | IDA-43150 | Loan Repay | 96,503.86 |
Nov 15, 2022 | IDA-43150 | Loan Repay | 1,853,351.20 |
Nov 15, 2022 | IDA-43150 | Int Charges | 616,340.30 |
Nov 15, 2022 | IDA-43150 | Int Charges | 616,340.30 |
May 15, 2023 | IDA-43150 | Int Charges | 42,582.25 |
May 15, 2023 | IDA-43150 | Int Charges | 42,582.25 |
May 15, 2023 | IDA-43150 | Loan Repay | 1,989,401.40 |
May 15, 2022 | IDA-43150 | Loan Repay | 42,289.52 |
May 15, 2019 | IDA-43150 | Int Charges | 745,025.44 |
May 15, 2019 | IDA-43150 | Int Charges | 745,025.44 |
Nov 15, 2019 | IDA-43150 | Loan Repay | 20,267.11 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2015-06-18 |
Counterpart Funding | Satisfactory | 2015-06-18 |
Project Management | Moderately Satisfactory | 2015-06-18 |
Monitoring and Evaluation | Satisfactory | 2015-06-18 |
Overall Implementation Progress (IP) | Satisfactory | 2015-06-18 |
Progress towards achievement of PDO | Moderately Satisfactory | 2015-06-18 |
Financial Management | Moderately Satisfactory | 2015-06-18 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-31-2015 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 11-27-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Substantial | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Works contract completed within contract period and budget with satisfactory quality | Value | 0.00 | 67.00 | 100.00 |
Date | May 3, 2007 | June 11, 2015 | June 30, 2015 | |
Comment |
Road Fund revenue (million ETB) | Value | 258.20 | 1200.00 | 1075.00 |
Date | June 30, 2006 | June 11, 2015 | June 30, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehabilitated, Non-rural | Value | 0.00 | 509.00 | 509.00 |
Date | May 3, 2007 | June 11, 2015 | June 30, 2015 | |
Comment |
Safeguard QA in place | Value | No | Yes | Yes |
Date | May 3, 2007 | June 11, 2015 | June 30, 2015 | |
Comment |
Procurement QA in place | Value | No | Yes | Yes |
Date | May 3, 2007 | June 11, 2015 | June 30, 2015 | |
Comment |
Performance monitoring functioning | Value | No | Yes | Yes |
Date | May 3, 2007 | June 11, 2015 | June 30, 2015 | |
Comment |
Cost monitoring functioning | Value | No | Yes | Yes |
Date | May 3, 2007 | June 11, 2015 | June 30, 2015 | |
Comment |
DMO's fully commercialized | Value | No | Yes | Yes |
Date | May 3, 2007 | June 11, 2015 | June 30, 2015 | |
Comment |