Financier | Commitments |
---|---|
IDA Grant | 190.00 |
P091092
Closed
Rebecca Gilsdorf , Patrick Ndolo
Ministry of Finance
March 6, 2006
(as of board presentation)
December 18, 2008
June 13, 2008
US$ 190.00 million
REGIDESO,Democratic Republic of Congo, Represented by the Ministry of Finance,COPIREP
2009
US$ 190.00 million
B
June 20, 2024
June 30, 2021
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 190.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 190.00 |
IBRD + IDA Commitment | 190.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 190.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 12, 2019 | IDA-D1020 | Loan Disb | 581,985.56 |
Apr 18, 2019 | IDA-D1020 | Loan Disb | 5,593,372.50 |
Jul 1, 2019 | IDA-D1020 | Loan Disb | 265,308.78 |
Jun 25, 2019 | IDA-H4350 | Loan Disb | -471,685.53 |
Apr 30, 2021 | IDA-D1020 | Loan Disb | 1,714,558.20 |
May 20, 2021 | IDA-D1020 | Loan Disb | 507,333.50 |
May 20, 2021 | IDA-D1020 | Loan Disb | 617,097.80 |
Jun 1, 2021 | IDA-D1020 | Loan Disb | 1,655,304.20 |
Apr 21, 2021 | IDA-D1020 | Loan Disb | 2,236,979.20 |
Jun 28, 2021 | IDA-D1020 | Loan Cancel | 42,143,700.00 |
May 20, 2021 | IDA-D1020 | Loan Disb | 696,255.60 |
Jun 9, 2021 | IDA-D1020 | Loan Disb | 885,142.00 |
Jun 9, 2021 | IDA-D1020 | Loan Disb | 576,434.75 |
Oct 25, 2021 | IDA-D1020 | Loan Disb | 310,396.22 |
Jun 14, 2022 | IDA-D1020 | Loan Cancel | 5,359,592.00 |
Mar 27, 2022 | IDA-D1020 | Loan Disb | 10,430.00 |
Aug 12, 2020 | IDA-D1020 | Loan Disb | 6,983,873.50 |
Mar 17, 2021 | IDA-D1020 | Loan Disb | 722,220.70 |
Dec 29, 2020 | IDA-D1020 | Loan Disb | 684,666.56 |
Mar 8, 2021 | IDA-D1020 | Loan Disb | 344,012.44 |
Jan 13, 2021 | IDA-D1020 | Loan Disb | 498,490.38 |
Mar 27, 2022 | IDA-D1020 | Loan Disb | -10,430.00 |
Dec 2, 2021 | IDA-D1020 | Loan Disb | -1,430,000.00 |
Jan 11, 2022 | IDA-D1020 | Loan Disb | -10,164.99 |
Jan 19, 2022 | IDA-D1020 | Loan Disb | -889,477.10 |
Jan 12, 2022 | IDA-D1020 | Loan Disb | -3,062,104.80 |
Jun 16, 2021 | IDA-D1020 | Loan Disb | 4,008,339.50 |
Feb 25, 2016 | IDA-D1020 | Loan Commitment | 166,000,000.00 |
Dec 18, 2008 | IDA-H4350 | Loan Commitment | 190,000,000.00 |
Jun 17, 2019 | IDA-D1020 | Loan Disb | 2,544,230.50 |
May 23, 2018 | IDA-D1020 | Loan Disb | 5,121,844.50 |
May 8, 2018 | IDA-D1020 | Loan Disb | 2,515,378.00 |
Jun 28, 2018 | IDA-D1020 | Loan Disb | 3,409,278.20 |
Dec 12, 2018 | IDA-D1020 | Loan Disb | 2,152,443.00 |
Mar 23, 2020 | IDA-D1020 | Loan Disb | 851,459.25 |
Feb 21, 2020 | IDA-D1020 | Loan Disb | 340,053.38 |
Feb 18, 2020 | IDA-D1020 | Loan Disb | 511,512.72 |
Feb 18, 2020 | IDA-D1020 | Loan Disb | 496,724.72 |
Dec 27, 2019 | IDA-D1020 | Loan Disb | 5,941,580.00 |
Jan 2, 2020 | IDA-D1020 | Loan Disb | 1,182,218.80 |
Jan 30, 2020 | IDA-D1020 | Loan Disb | 531,533.06 |
Jan 7, 2020 | IDA-D1020 | Loan Disb | -1,182,198.80 |
Feb 5, 2020 | IDA-D1020 | Loan Disb | 450,823.25 |
Feb 26, 2020 | IDA-D1020 | Loan Disb | 791,344.00 |
Dec 19, 2019 | IDA-D1020 | Loan Disb | 531,533.06 |
Jun 7, 2019 | IDA-D1020 | Loan Disb | 1,866,481.60 |
Jun 17, 2019 | IDA-D1020 | Loan Disb | 1,902,901.20 |
Jun 14, 2019 | IDA-D1020 | Loan Disb | 492,716.30 |
Jun 14, 2019 | IDA-D1020 | Loan Disb | 3,079,576.80 |
May 28, 2019 | IDA-D1020 | Loan Disb | 316,012.88 |
Oct 1, 2019 | IDA-D1020 | Loan Disb | 819,495.60 |
Aug 16, 2019 | IDA-D1020 | Loan Disb | 2,792,503.80 |
Nov 25, 2019 | IDA-D1020 | Loan Disb | 268,174.94 |
Sep 12, 2019 | IDA-D1020 | Loan Disb | 1,090,812.40 |
Aug 26, 2019 | IDA-D1020 | Loan Disb | 294,255.30 |
Oct 15, 2018 | IDA-D1020 | Loan Disb | 1,563,706.10 |
Jan 24, 2019 | IDA-D1020 | Loan Disb | 4,525,829.00 |
Dec 9, 2020 | IDA-D1020 | Loan Disb | 695,579.80 |
Dec 9, 2020 | IDA-D1020 | Loan Disb | 408,291.03 |
Nov 30, 2020 | IDA-D1020 | Loan Disb | 778,910.70 |
Apr 22, 2020 | IDA-D1020 | Loan Disb | 810,885.70 |
May 13, 2020 | IDA-D1020 | Loan Disb | 1,298,312.20 |
Jan 13, 2020 | IDA-D1020 | Loan Disb | -531,513.06 |
May 14, 2020 | IDA-D1020 | Loan Disb | 252,605.30 |
Apr 10, 2020 | IDA-D1020 | Loan Disb | 469,913.25 |
Jun 3, 2020 | IDA-D1020 | Loan Disb | 377,702.72 |
May 26, 2020 | IDA-H4350 | Loan Cancel | 721,304.75 |
Jun 24, 2020 | IDA-D1020 | Loan Disb | 1,195,292.20 |
Jun 24, 2020 | IDA-D1020 | Loan Disb | 664,758.94 |
Jul 9, 2020 | IDA-D1020 | Loan Disb | 643,978.80 |
Jul 9, 2020 | IDA-D1020 | Loan Disb | 683,097.90 |
Jul 20, 2020 | IDA-D1020 | Loan Disb | 607,691.00 |
May 26, 2020 | IDA-H4350 | Loan Disb | -258,693.02 |
Sep 8, 2020 | IDA-D1020 | Loan Disb | 838,238.30 |
Oct 26, 2020 | IDA-D1020 | Loan Disb | 495,550.40 |
Oct 1, 2020 | IDA-D1020 | Loan Disb | 647,957.10 |
Oct 8, 2019 | IDA-D1020 | Loan Disb | 282,452.20 |
Jul 30, 2019 | IDA-D1020 | Loan Disb | 393,582.47 |
Oct 18, 2019 | IDA-D1020 | Loan Disb | 390,974.72 |
Sep 20, 2019 | IDA-D1020 | Loan Disb | 332,241.90 |
Jul 22, 2019 | IDA-D1020 | Loan Disb | 1,053,771.10 |
Jul 18, 2019 | IDA-D1020 | Loan Disb | 598,690.30 |
Nov 12, 2019 | IDA-D1020 | Loan Disb | 719,419.06 |
Oct 15, 2019 | IDA-D1020 | Loan Disb | 1,175,544.20 |
Nov 12, 2019 | IDA-D1020 | Loan Disb | 711,518.20 |
Dec 10, 2019 | IDA-D1020 | Loan Disb | 353,117.03 |
Dec 10, 2019 | IDA-D1020 | Loan Disb | 339,644.78 |
Mar 27, 2020 | IDA-D1020 | Loan Disb | 533,037.90 |
Feb 3, 2020 | IDA-D1020 | Loan Disb | 1,182,218.80 |
Dec 27, 2019 | IDA-D1020 | Loan Disb | 415,675.00 |
Mar 30, 2020 | IDA-D1020 | Loan Disb | 567,199.10 |
Jun 16, 2021 | IDA-D1020 | Loan Disb | 292,156.84 |
Apr 2, 2021 | IDA-D1020 | Loan Disb | 1,003,947.80 |
Jul 9, 2013 | IDA-H4350 | Loan Disb | 2,807,773.50 |
Jan 22, 2014 | IDA-H4350 | Loan Disb | 3,711,391.80 |
Dec 2, 2013 | IDA-H4350 | Loan Disb | 5,842,642.50 |
Mar 12, 2014 | IDA-H4350 | Loan Disb | 2,950,637.80 |
Mar 27, 2014 | IDA-H4350 | Loan Disb | 5,694,421.00 |
May 27, 2014 | IDA-H4350 | Loan Disb | 4,623,078.00 |
Nov 4, 2013 | IDA-H4350 | Loan Disb | 1,633,180.50 |
Dec 19, 2013 | IDA-H4350 | Loan Disb | 6,038,162.50 |
Sep 24, 2013 | IDA-H4350 | Loan Disb | 275,016.97 |
Dec 12, 2013 | IDA-H4350 | Loan Disb | 3,735,591.00 |
Sep 20, 2013 | IDA-H4350 | Loan Disb | 397,496.44 |
Nov 13, 2014 | IDA-H4350 | Loan Disb | 6,036,158.00 |
Jan 15, 2015 | IDA-H4350 | Loan Disb | 6,000,000.00 |
Jul 23, 2013 | IDA-H4350 | Loan Disb | 1,909,202.60 |
Oct 28, 2015 | IDA-H4350 | Loan Disb | 1,194,607.80 |
Oct 28, 2015 | IDA-H4350 | Loan Disb | 798,818.00 |
Nov 2, 2015 | IDA-H4350 | Loan Disb | 589,120.25 |
Sep 18, 2015 | IDA-H4350 | Loan Disb | 2,559,050.50 |
Dec 16, 2015 | IDA-H4350 | Loan Disb | 1,243,371.40 |
Feb 19, 2015 | IDA-H4350 | Loan Disb | 1,333,440.20 |
Jul 28, 2014 | IDA-H4350 | Loan Disb | 551,711.00 |
Feb 3, 2015 | IDA-H4350 | Loan Disb | 633,258.75 |
Aug 29, 2014 | IDA-H4350 | Loan Disb | 404,466.00 |
Mar 17, 2015 | IDA-H4350 | Loan Disb | 3,021,188.20 |
Sep 2, 2014 | IDA-H4350 | Loan Disb | 3,727,446.20 |
Jun 16, 2015 | IDA-H4350 | Loan Disb | 2,215,714.50 |
Jun 9, 2015 | IDA-H4350 | Loan Disb | 1,126,196.50 |
Jun 17, 2015 | IDA-H4350 | Loan Disb | 2,168,206.50 |
Jun 27, 2014 | IDA-H4350 | Loan Disb | 8,861,504.00 |
Jun 18, 2014 | IDA-H4350 | Loan Disb | 7,041,180.00 |
Jul 8, 2014 | IDA-H4350 | Loan Disb | 446,216.10 |
Jun 16, 2014 | IDA-H4350 | Loan Disb | 2,435,802.00 |
Sep 25, 2014 | IDA-H4350 | Loan Disb | 553,606.50 |
Sep 12, 2014 | IDA-H4350 | Loan Disb | 498,273.10 |
Jul 1, 2016 | IDA-H4350 | Loan Disb | 192,590.90 |
Jun 14, 2016 | IDA-H4350 | Loan Disb | 2,053,808.90 |
Dec 30, 2015 | IDA-H4350 | Loan Disb | 3,700,000.00 |
Dec 16, 2015 | IDA-H4350 | Loan Disb | 1,258,267.20 |
Sep 28, 2015 | IDA-H4350 | Loan Disb | 1,804,532.20 |
Nov 6, 2015 | IDA-H4350 | Loan Disb | 1,874,128.00 |
Dec 22, 2015 | IDA-H4350 | Loan Disb | 640,421.60 |
Nov 9, 2015 | IDA-H4350 | Loan Disb | 559,945.50 |
Dec 22, 2015 | IDA-H4350 | Loan Disb | 3,136,492.50 |
Apr 27, 2016 | IDA-H4350 | Loan Disb | 2,379,075.50 |
Jun 25, 2015 | IDA-H4350 | Loan Disb | 1,805,158.60 |
Jun 15, 2015 | IDA-H4350 | Loan Disb | 2,389,638.20 |
May 13, 2015 | IDA-H4350 | Loan Disb | 3,826,304.50 |
Jun 23, 2015 | IDA-H4350 | Loan Disb | 764,903.56 |
Mar 14, 2018 | IDA-D1020 | Loan Disb | 2,493,951.50 |
Apr 17, 2018 | IDA-D1020 | Loan Disb | 1,932,249.00 |
Apr 24, 2017 | IDA-D1020 | Loan Disb | 536,274.70 |
Jun 21, 2017 | IDA-D1020 | Loan Disb | 1,662,499.00 |
Dec 13, 2016 | IDA-D1020 | Loan Disb | 14,500,000.00 |
Feb 11, 2019 | IDA-D1020 | Loan Disb | 291,751.50 |
Nov 8, 2018 | IDA-D1020 | Loan Disb | 3,307,251.20 |
Oct 29, 2018 | IDA-D1020 | Loan Disb | 841,995.56 |
May 7, 2019 | IDA-D1020 | Loan Disb | 2,542,504.80 |
Jul 1, 2019 | IDA-D1020 | Loan Disb | 1,108,839.50 |
Jul 1, 2019 | IDA-D1020 | Loan Disb | 285,000.00 |
Mar 12, 2019 | IDA-D1020 | Loan Disb | 1,228,937.80 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2021-02-03 |
Progress towards achievement of PDO | Moderately Satisfactory | 2021-02-03 |
Financial Management | Moderately Satisfactory | 2021-02-03 |
Monitoring and Evaluation | Moderately Satisfactory | 2021-02-03 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2021-02-03 |
Procurement | Moderately Satisfactory | 2021-02-03 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-28-2022 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 3071430.00 | 2600000.00 |
Date | April 25, 2014 | June 30, 2021 | February 3, 2016 | |
Comment |
Operating cost coverage ratio in utilities targeted by the project | Value | 88.00 | 42.22 | 104.00 |
Date | November 18, 2008 | June 30, 2021 | March 31, 2013 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Secondary and tertiary water networks constructed | Value | 0.00 | 1236.00 | 1100.00 |
Date | November 18, 2008 | June 30, 2021 | December 21, 2018 | |
Comment |
Citizen engagement satisfactory complaints resolution by REGIDESO | Value | 26.00 | 83.47 | 0.00 |
Date | January 29, 2016 | June 30, 2021 | ||
Comment |
Water production capacity installed under the project | Value | 0.00 | 85920.00 | 69000.00 |
Date | November 28, 2008 | June 30, 2021 | December 21, 2018 | |
Comment |
Citizen engagement: Surveyed beneficiaries who know at least two of their responsibilities regarding their access to water | Value | 0.00 | 98.00 | 0.00 |
Date | January 29, 2016 | June 30, 2021 | ||
Comment |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 455.00 | 450.00 |
Date | November 18, 2008 | July 30, 2020 | February 3, 2016 | |
Comment |
Number of water utilities that the project is supporting | Value | 1.00 | 1.00 | 0.00 |
Date | November 18, 2008 | June 30, 2021 | ||
Comment |
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 88811.00 | 73500.00 |
Date | November 18, 2008 | June 30, 2021 | December 21, 2018 | |
Comment |
Services contract is bid, signed and under implementation | Value | No | Yes | |
Date | November 18, 2008 | June 30, 2021 | ||
Comment |
Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Value | 0.00 | 153490.00 | 0.00 |
Date | November 18, 2008 | June 30, 2021 | ||
Comment |
Number of other water service providers that the project is supporting | Value | 0.00 | 0.00 | 0.00 |
Date | November 18, 2008 | June 30, 2021 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 3071430.00 | 2600000.00 |
Date | November 18, 2008 | June 30, 2021 | February 3, 2016 | |
Comment |
Preparation of water sanitation strategies and programm | Value | 0.00 | 12.00 | 4.00 |
Date | November 18, 2008 | June 30, 2021 | February 3, 2016 | |
Comment |
Female beneficiaries | Value | 0.00 | 946815.00 | 0.00 |
Date | November 18, 2008 | April 30, 2018 | ||
Comment |
Availability rate of production plants | Value | 87.60 | 94.60 | 0.00 |
Date | November 18, 2008 | June 30, 2021 | ||
Comment |
Non-revenue water | Value | 45.00 | 45.72 | 33.00 |
Date | November 18, 2008 | June 30, 2021 | March 31, 2013 | |
Comment |
Rate of inactive connections per city | Value | 36.00 | 30.95 | 0.00 |
Date | April 25, 2014 | June 30, 2021 | ||
Comment |
Metering distribution rate | Value | 33.00 | 70.74 | 90.00 |
Date | April 25, 2014 | June 30, 2021 | February 3, 2016 | |
Comment |
Bill collection rate from private connections | Value | 73.00 | 68.71 | 97.00 |
Date | April 25, 2014 | June 30, 2021 | February 3, 2016 | |
Comment |
Number of staff/1000 active connections (after severance plan) | Value | 17.70 | 8.11 | 10.20 |
Date | April 25, 2014 | June 30, 2021 | March 31, 2013 | |
Comment |
Rate of labor costs versus operational costs | Value | 40.00 | 36.00 | 28.00 |
Date | April 25, 2014 | June 30, 2021 | March 31, 2013 | |
Comment |
Submission of previous years' audit reports to clients by May 15 of following year (yes/no) | Value | NA | yes | yes |
Date | November 18, 2008 | June 30, 2021 | November 18, 2013 | |
Comment |
Proportion of volumes owed by "Instances Officielles" in total volumes owed | Value | 21.00 | 34.96 | 0.00 |
Date | April 25, 2014 | April 13, 2020 | ||
Comment |
Proportion of bills owed by "Instances Officielles" in total billing | Value | 42.00 | 35.93 | 0.00 |
Date | November 18, 2008 | June 30, 2021 | ||
Comment |