Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 29.30 |
Borrower/Recipient | 3.50 |
P091299
Closed
Angelica Nunez del Campo
N/A
October 13, 2004
(as of board presentation)
March 29, 2006
June 27, 2006
US$ 32.80 million
N/A
2006
US$ 29.30 million
B
September 24, 2015
December 31, 2013
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 29.30 |
Borrower/Recipient | 3.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 29.30 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 29.30 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 32.80 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 29, 2006 | IBRD-48190 | Loan Commitment | 29,300,000.00 |
Sep 9, 2013 | IBRD-48190 | Loan Disb | 2,071,826.20 |
Feb 15, 2023 | IBRD-48190 | Int Charges | 3,965.15 |
Feb 15, 2023 | IBRD-48190 | Int Charges | 27,218.76 |
Aug 15, 2023 | IBRD-48190 | Int Charges | 1,298.11 |
Feb 15, 2022 | IBRD-48190 | Int Charges | 12,769.18 |
Feb 15, 2022 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Aug 15, 2022 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Aug 15, 2022 | IBRD-48190 | Int Charges | 14,362.44 |
Aug 15, 2021 | IBRD-48190 | Int Charges | 17,709.07 |
Aug 15, 2021 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Feb 15, 2021 | IBRD-48190 | Int Charges | 25,920.08 |
Feb 15, 2021 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Aug 15, 2020 | IBRD-48190 | Int Charges | 80,763.02 |
Aug 15, 2020 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Feb 15, 2020 | IBRD-48190 | Int Charges | 109,636.20 |
Feb 15, 2020 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Aug 15, 2019 | IBRD-48190 | Int Charges | 158,565.45 |
Aug 15, 2019 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Aug 15, 2018 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Feb 15, 2019 | IBRD-48190 | Int Charges | 167,268.98 |
Feb 15, 2019 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Feb 15, 2018 | IBRD-48190 | Int Charges | 130,304.44 |
Feb 15, 2018 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Aug 15, 2018 | IBRD-48190 | Int Charges | 153,961.50 |
Aug 15, 2017 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Aug 15, 2017 | IBRD-48190 | Int Charges | 130,249.01 |
Feb 15, 2017 | IBRD-48190 | Int Charges | 129,651.30 |
Feb 15, 2017 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Feb 15, 2016 | IBRD-48190 | Int Charges | 80,395.22 |
Feb 15, 2016 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Aug 15, 2016 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Aug 15, 2016 | IBRD-48190 | Int Charges | 105,296.99 |
Mar 25, 2015 | IBRD-48190 | Loan Cancel | 31,870.41 |
Mar 25, 2015 | IBRD-48190 | Loan Disb | -31,870.41 |
Aug 15, 2015 | IBRD-48190 | Loan Repay | 1,218,010.10 |
Aug 15, 2015 | IBRD-48190 | Int Charges | 68,681.32 |
Aug 15, 2015 | IBRD-48190 | Int Charges | -0.01 |
Aug 15, 2015 | IBRD-48190 | Int Charges | 0.01 |
Feb 15, 2015 | IBRD-48190 | Int Charges | 65,786.14 |
Feb 15, 2015 | IBRD-48190 | Loan Repay | 1,220,000.00 |
Aug 15, 2014 | IBRD-48190 | Int Charges | 65,201.23 |
Aug 15, 2014 | IBRD-48190 | Loan Repay | 1,220,000.00 |
Aug 15, 2014 | IBRD-48190 | Int Charges | 293.26 |
Aug 15, 2014 | IBRD-48190 | Int Charges | 491.67 |
Dec 4, 2013 | IBRD-48190 | Loan Disb | 417,906.78 |
Feb 15, 2014 | IBRD-48190 | Int Charges | 1,706.33 |
Feb 15, 2014 | IBRD-48190 | Int Charges | 1,325.87 |
Feb 15, 2014 | IBRD-48190 | Int Charges | 73,927.49 |
Feb 15, 2014 | IBRD-48190 | Loan Repay | 1,220,000.00 |
Feb 15, 2014 | IBRD-48190 | Int Charges | 907.87 |
Dec 20, 2013 | IBRD-48190 | Loan Disb | 751,130.50 |
Aug 15, 2013 | IBRD-48190 | Int Charges | 6,368.82 |
Aug 15, 2013 | IBRD-48190 | Int Charges | 66,219.74 |
Aug 15, 2013 | IBRD-48190 | Loan Repay | 1,220,000.00 |
Feb 15, 2023 | IBRD-48190 | Loan Repay | 1,237,977.50 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2013-12-28 |
Monitoring and Evaluation | Satisfactory | 2013-12-28 |
Overall Implementation Progress (IP) | Satisfactory | 2013-12-28 |
Counterpart Funding | Satisfactory | 2013-12-28 |
Project Management | Satisfactory | 2013-12-28 |
Procurement | Satisfactory | 2013-12-28 |
Financial Management | Moderately Satisfactory | 2013-12-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-25-2014 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 03-31-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: 04-01-2019 |
---|---|---|
Outcome Rating | Moderately Satisfactory | Moderately Satisfactory |
Risk To Development Outcome | Significant | Substantial |
Bank Performance | Moderately Satisfactory | Moderately Satisfactory |
Borrower Performance | Satisfactory | Moderately Unsatisfactory |
Government Performance | Satisfactory | Not Rated |
Implementing Agency | Satisfactory | Moderately Satisfactory |
Icr Quality | Satisfactory | Not Rated |
M&e Quality | Modest | Modest |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Access to improved basic infrastructure and financial services and security of tenure for 60,000 inner city residents | Value | 0 | 61,953 | 60,000 |
Date | May 18, 2006 | September 30, 2013 | December 31, 2013 | |
Comment |
% of beneficiaries who feel safe or very safe | Value | 27.75% | n.a. | 75% |
Date | May 18, 2006 | September 30, 2013 | December 31, 2013 | |
Comment | Data will be included once the surveys and evaluation is conducted (end 2013) |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of subprojects in which CPTED principles are applied in infrastructure design | Value | 0.00 | 55.00 | 15.00 |
Date | September 30, 2013 | December 31, 2013 | ||
Comment |
Number of persons who participated in the programs or activities for community-based crime and violence prevention and reduction | Value | 0.00 | 35803.00 | 3270.00 |
Date | September 30, 2013 | December 31, 2013 | ||
Comment |
Number of persons who participated in education and employment programs or activities | Value | 0.00 | 31361.00 | 4785.00 |
Date | September 30, 2013 | December 31, 2013 | ||
Comment |
Number of persons who obtained certificates as a result of project programs | Value | 0.00 | 544.00 | 220.00 |
Date | September 30, 2013 | December 31, 2013 | ||
Comment |
Number of training and workshops provided to parish councils and CBOs | Value | 0.00 | 91.00 | 20.00 |
Date | September 30, 2012 | December 31, 2013 | ||
Comment |
Km of paved road surface rehabilitated and maintained | Value | 0 | 20.70 | 10.36 |
Date | June 30, 2006 | September 30, 2013 | December 31, 2013 | |
Comment |
Number of households with new or improved access to water | Value | 0.00 | 2785.00 | 2490.00 |
Date | October 31, 2012 | December 31, 2013 | ||
Comment |
Number of households with new or improved access to sewer networks | Value | 0.00 | 478.00 | 364.00 |
Date | September 30, 2013 | December 31, 2013 | ||
Comment |
Number of formal microfinance loans approved and disbursed | Value | 0.00 | 391.00 | 171.00 |
Date | September 30, 2013 | December 31, 2013 | ||
Comment |
Number of applications for land registration made to the national land agency | Value | 0.00 | 0.00 | 200.00 |
Date | September 30, 2013 | December 31, 2013 | ||
Comment |