Kenya: Adaptation to Climate Change in Arid and Semi-Arid Lands (KACCAL)

Development Objective

To improve the ability of participating districts and communities in the arid and semi-arid lands to plan and implement climate change adaptation measures

Key Details

Project Details

  • P091979

  • Closed

  • Joseph Oryokot , Ladisy Komba Chengula

  • The Republic of Kenya

  • Kenya

  • October 2, 2007

  • (as of board presentation)

    June 10, 2010

  • November 15, 2012

  • US$ 6.39 million

  • Ministry of Agriculture, Livestock and Fisheries

  • Eastern and Southern Africa

  • 2010

  • US$ 5.50 million

  • B

  • Not Applicable

  • June 30, 2017

  • BANK APPROVED

  • July 8, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 0.69
Global Environment Facility (GEF) 5.50
Local Communities 0.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 5.50
Total Project Cost** 6.39

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Summary Global Objective Rating Moderately Satisfactory 2017-03-17
Monitoring and Evaluation Moderately Satisfactory 2017-03-17
Procurement Moderately Satisfactory 2017-03-17
Project Management Satisfactory 2017-03-17
Financial Management Satisfactory 2017-03-17
Overall Implementation Progress (IP) Moderately Satisfactory 2017-03-17
Counterpart Funding Satisfactory 2017-03-17

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-27-2018
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-11-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModestN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualityModestN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of District management plans with concrete climate risk management activities reflected in the budgetValue0.004.004.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment
  • Public and private advisory agents trained in community climate risk managementValue0.00290.0080.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment
  • Community adaptation micro-projects developed and implementedValue0.00156.0032.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment
  • Percentage of Community adaptation projects rated satisfactory or better by participating communitiesValue0.0081.0075.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment
  • Climate risk profiles developed and used for district management plansValue0.0015.0015.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment
  • Methodology and tool for screening agricultural investment programs for climate risk developedValue0.001.001.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment
  • Percentage of Kenya Agriculture and Agribusiness Project, sub-projects in the Participating Districts screened for improving response to climate riskValue0.00100.00100.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment
  • Public and private sector investments rated satisfactory or better by beneficiariesValue0.0082.0075.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment
  • Community Action Plans with concrete climate risk management activities reflected in the budgetValue0.0082.0080.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment
  • Direct project beneficiariesValue0.0019024.0010000.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment
  • Female beneficiariesValue0.0054.0050.00
    DateJune 30, 2012February 24, 2017April 28, 2017
    Comment