Financier | Commitments |
---|---|
Borrower/Recipient | 79.60 |
PROTOTYPE CARBON FUND | 3.00 |
P092015
Closed
Javier Freire Coloma
N/A
June 3, 2005
(as of board presentation)
June 2, 2006
April 27, 2006
US$ 82.60 million
N/A
2006
US$ 3.00 million
B
Not Applicable
June 14, 2017
BANK APPROVED
December 19, 2024
Financier | Commitments |
---|---|
Borrower/Recipient | 79.60 |
PROTOTYPE CARBON FUND | 3.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 3.00 |
Total Project Cost** | 82.60 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2012-11-17 |
Counterpart Funding | Satisfactory | 2012-11-17 |
Project Management | Satisfactory | 2012-11-17 |
Progress towards achievement of PDO | Moderately Satisfactory | 2012-11-17 |
Monitoring and Evaluation | Moderately Satisfactory | 2012-11-17 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Cumulated CER (tCO2e) | Value | 0 | 0 | 400000 |
Date | June 30, 2007 | August 2, 2011 | December 31, 2012 | |
Comment | No CERs have been paid yet. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Emission Reductions | Value | 0.00 | 0.00 | 400000.00 |
Date | August 2, 2011 | December 31, 2012 | ||
Comment |