Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
Borrower/Recipient | 364.40 |
P092631
Closed
Reda Hamedoun
People's Republic of China
February 17, 2006
(as of board presentation)
June 24, 2008
December 24, 2008
US$ 514.40 million
Xi'an PMO
2008
US$ 150.00 million
A
Not Applicable
March 31, 2017
BANK APPROVED
July 15, 2021
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
Borrower/Recipient | 364.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 150.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 514.40 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 15, 2014 | IBRD-75580 | Loan Disb | 123,858.62 |
Sep 15, 2014 | IBRD-75580 | Int Charges | 123,858.62 |
Sep 15, 2014 | IBRD-75580 | Loan Repay | 975,386.60 |
Feb 27, 2015 | IBRD-75580 | Loan Disb | 3,649,603.50 |
Feb 27, 2015 | IBRD-75580 | Loan Disb | 18,032,278.00 |
Mar 15, 2014 | IBRD-75580 | Loan Disb | 108,549.86 |
Mar 15, 2014 | IBRD-75580 | Int Charges | 108,549.86 |
Dec 2, 2013 | IBRD-75580 | Loan Disb | 8,904,117.00 |
Mar 7, 2014 | IBRD-75580 | Loan Disb | 9,059,933.00 |
Sep 15, 2016 | IBRD-75580 | Loan Repay | 2,734,784.20 |
Mar 15, 2016 | IBRD-75580 | Int Charges | 452,078.47 |
Mar 15, 2016 | IBRD-75580 | Loan Repay | 2,407,001.20 |
Dec 9, 2015 | IBRD-75580 | Loan Disb | 5,526,598.50 |
Sep 15, 2015 | IBRD-75580 | Int Charges | 348,030.50 |
Sep 15, 2015 | IBRD-75580 | Loan Repay | 2,254,064.00 |
Mar 15, 2015 | IBRD-75580 | Loan Disb | 147,071.72 |
Mar 15, 2015 | IBRD-75580 | Int Charges | 147,071.72 |
Mar 15, 2015 | IBRD-75580 | Loan Repay | 1,001,700.60 |
Feb 13, 2015 | IBRD-75580 | Loan Disb | 38,489,088.00 |
Sep 15, 2017 | IBRD-75580 | Int Charges | 1,176,475.10 |
Sep 15, 2017 | IBRD-75580 | Loan Repay | 2,870,337.00 |
Mar 15, 2017 | IBRD-75580 | Int Charges | 1,032,280.75 |
Mar 15, 2017 | IBRD-75580 | Loan Repay | 2,794,784.20 |
May 31, 2016 | IBRD-75580 | Loan Disb | 8,306,199.50 |
Jun 24, 2016 | IBRD-75580 | Loan Disb | 5,284,284.50 |
Sep 15, 2016 | IBRD-75580 | Int Charges | 756,158.75 |
Mar 15, 2019 | IBRD-75580 | Int Charges | 1,848,699.40 |
Mar 15, 2019 | IBRD-75580 | Loan Repay | 3,088,713.80 |
Mar 15, 2020 | IBRD-75580 | Int Charges | 1,452,276.80 |
Mar 15, 2020 | IBRD-75580 | Loan Repay | 3,240,625.20 |
Sep 15, 2019 | IBRD-75580 | Int Charges | 1,918,020.60 |
Sep 15, 2019 | IBRD-75580 | Loan Repay | 3,165,625.50 |
Jun 24, 2008 | IBRD-75580 | Loan Commitment | 150,000,000.00 |
Mar 15, 2024 | IBRD-75580 | Int Charges | 2,869,496.00 |
Mar 15, 2024 | IBRD-75580 | Loan Repay | 3,949,855.50 |
Mar 15, 2024 | IBRD-75580 | Int Charges | 50,423.87 |
Mar 15, 2023 | IBRD-75580 | Int Charges | 120,574.13 |
Mar 15, 2023 | IBRD-75580 | Int Charges | 2,369,255.80 |
Mar 15, 2023 | IBRD-75580 | Loan Repay | 3,762,837.80 |
Sep 15, 2023 | IBRD-75580 | Int Charges | 38,973.15 |
Sep 15, 2023 | IBRD-75580 | Int Charges | 2,667,427.20 |
Sep 15, 2023 | IBRD-75580 | Loan Repay | 3,852,837.80 |
Sep 15, 2022 | IBRD-75580 | Int Charges | 775,989.75 |
Sep 15, 2022 | IBRD-75580 | Loan Repay | 3,670,926.00 |
Mar 15, 2022 | IBRD-75580 | Int Charges | 263,759.12 |
Sep 15, 2013 | IBRD-75580 | Int Charges | 108,360.80 |
Sep 15, 2018 | IBRD-75580 | Loan Repay | 3,013,713.80 |
Sep 15, 2018 | IBRD-75580 | Int Charges | 1,727,542.40 |
Mar 15, 2018 | IBRD-75580 | Int Charges | 1,160,335.20 |
Mar 15, 2018 | IBRD-75580 | Loan Repay | 2,931,696.00 |
Sep 15, 2021 | IBRD-75580 | Int Charges | 293,985.12 |
Sep 15, 2021 | IBRD-75580 | Loan Repay | 3,489,567.00 |
Sep 15, 2020 | IBRD-75580 | Loan Repay | 3,331,996.80 |
Mar 15, 2021 | IBRD-75580 | Int Charges | 338,821.70 |
Mar 15, 2021 | IBRD-75580 | Loan Repay | 3,407,549.50 |
Sep 15, 2020 | IBRD-75580 | Int Charges | 623,105.75 |
Sep 15, 2013 | IBRD-75580 | Loan Disb | 108,360.80 |
Mar 15, 2022 | IBRD-75580 | Loan Repay | 3,580,926.00 |
Mar 23, 2015 | IBRD-75580 | Loan Disb | 9,858,000.00 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2017-03-31 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-03-31 |
Progress towards achievement of PDO | Satisfactory | 2017-03-31 |
Counterpart Funding | Satisfactory | 2017-03-31 |
Monitoring and Evaluation | Satisfactory | 2017-03-31 |
Project Management | Moderately Satisfactory | 2017-03-31 |
Financial Management | Moderately Satisfactory | 2017-03-31 |
Overall Safeguards Rating | Moderately Satisfactory | 2017-03-31 |
Overall Safeguards Rating | Moderately Satisfactory | 2017-03-31 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 09-29-2017 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Unsatisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 03-05-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Modest | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase MV speed on the key corridors under the project (East GAte, South First Ring, Yuxiang Gate) | Value | 12 km/hr | 43 | 20 km/hr |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Increase in number of vehicles receiving emissions testing | Value | 40 | 2500 | 500 |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component 1: New road interchanges to replace existing roundabouts on the First and Second Ring Roads. | Value | 0 | 8 | 4 |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 1: Huxian - Cross town (Dong Chen Lu to Lao Bin Lu) journey time across the railway line (mn) | Value | 36 min | 9.7 min | 15 min |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 2: Area of bus terminals (m²). | Value | 159574 | 320214 | 320214 |
Date | December 31, 2009 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 2: Number of days for maintenance | Value | 93 | 135 | 163 |
Date | December 31, 2009 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 3: Journey speeds for cars and buses on selected routes in MWC: average speed in km/h: Bei Dajie | Value | 12 | 31 | 20 |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 3: Journey speeds for cars and buses on selected routes in MWC: average speed in km/h: Nan Dajie | Value | 16 | 37 | 22 |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 3: Journey speeds for cars and buses on selected routes in MWC: average speed in km/h: Dong Dajie | Value | 12 | 41 | 19 |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 3: Journey speeds for cars and buses on selected routes in MWC: average speed in km/h: Xi Dajie | Value | 18 | 21 | 25 |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 4: Monitoring Center operational | Value | No operational center | Operational | 1 Operational |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 5: Han Chang'an Road Network in successful operation | Value | Road network not operational | Fully operational | Fully operational |
Date | December 31, 2008 | March 17, 2017 | December 31, 2014 | |
Comment |
Component 6: Completion of strategic planning study jointly by XMG UT Unit and consultant team. | Value | Study not completed | Completed | Completed |
Date | December 31, 2008 | March 17, 2017 | December 31, 2016 | |
Comment |
Component 3: Area traffic control system installed. | Value | No system installed | Installed ATC system | Installed ATC system |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 4: Environmental management information system established and operational | Value | No system in place | Database established and operational | Database established and operational |
Date | December 31, 2008 | March 17, 2017 | December 31, 2016 | |
Comment |
Component 4: Development and submission to the Xi’an Municipality of a plan to reduce vehicle emissions. | Value | No plan in place | Submitted to Xi'an Municipality | Submitted to Xi’an Municipality |
Date | December 31, 2008 | March 17, 2017 | December 31, 2013 | |
Comment |
Component 3: Journey speeds for cars and buses on selected routes in MWC: average speed in km/h: Lianhu Rd. | Value | 14 | 43 | 22 |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 3: Journey speeds for cars and buses on selected routes in MWC: average speed in km/h: Dongxi 5th Rd. | Value | 17 | 37 | 25 |
Date | December 31, 2008 | March 17, 2017 | June 30, 2016 | |
Comment |
Component 6: Completion of investment and debt risk control study. | Value | Study not completed | Completed | Completed |
Date | December 31, 2008 | March 17, 2017 | December 31, 2016 | |
Comment |
Component 6: Completion of Accident analysis study. | Value | Study not completed | Completed | Completed |
Date | December 31, 2008 | March 17, 2017 | December 31, 2016 | |
Comment |
Component 6: Training and study tours in urban management. | Value | 0 | 15 | 18 |
Date | December 31, 2008 | March 17, 2017 | December 31, 2016 | |
Comment |