Financier | Commitments |
---|---|
Local Sources of Borrowing Country | 18.91 |
International Bank for Reconstruction and Development | 50.00 |
Borrower/Recipient | 17.23 |
P093882
Closed
Frederic Asseline
N/A
November 8, 2005
(as of board presentation)
May 27, 2008
October 15, 2008
US$ 86.14 million
N/A
2008
US$ 50.00 million
B
Not Applicable
June 30, 2012
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Local Sources of Borrowing Country | 18.91 |
International Bank for Reconstruction and Development | 50.00 |
Borrower/Recipient | 17.23 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 50.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 86.14 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 26, 2013 | IBRD-75310 | Int Charges | 170.01 |
May 27, 2008 | IBRD-75310 | Loan Commitment | 50,000,000.00 |
Jul 26, 2013 | IBRD-75310 | Loan Repay | 119,999.99 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2012-04-10 |
Monitoring and Evaluation | Unsatisfactory | 2012-04-10 |
Overall Implementation Progress (IP) | Unsatisfactory | 2012-04-10 |
Progress towards achievement of PDO | Unsatisfactory | 2012-04-10 |
Procurement | Unsatisfactory | 2012-04-10 |
Project Management | Unsatisfactory | 2012-04-10 |
Financial Management | Unsatisfactory | 2012-04-10 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-21-2012 |
---|---|
Outcomes | Unsatisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Unsatisfactory |
Borrower Performance | Unsatisfactory |
Government Performance | Moderately Unsatisfactory |
Implementing Agency | Unsatisfactory |
INDICATOR | ICR REVIEW: 06-09-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | Unsatisfactory | N/a |
Government Performance | Unsatisfactory | N/a |
Implementing Agency | Unsatisfactory | N/a |
Icr Quality | Unsatisfactory | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Total amount of SO2 removed in the heat and power sector (tons) | Value | 10000 | N/A | 900000 |
Date | December 30, 2005 | March 1, 2012 | December 31, 2010 | |
Comment | SPEPB has been asked to provide an updated figure - it has not done so |
Total amount of SO2 emissions in Shandong reduced (tons) | Value | 2030000 | N/A | 1600000 |
Date | December 30, 2005 | March 1, 2012 | December 31, 2010 | |
Comment | SPEPB has been asked to provide an updated figure - it has not done so |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component A: Rules and Procedures issued on CEM installation, calibration, data collectin and transmission | Value | Not applicable | N/A | Operational |
Date | December 30, 2005 | March 1, 2012 | December 31, 2010 | |
Comment | A work plan for the TA to be prepared by the PMO/SPEPB was not delivered |
Component A: Number of staff, managers and operators trained | Value | 0 | N/A | 500 |
Date | December 30, 2005 | May 31, 2011 | December 31, 2010 | |
Comment | A work plan for the TA to be prepared by the PMO/SPEPB was not delivered |
Component A: Percentage of installation and proper operation of CEMs in heat and power plants | Value | 10 | N/A | 100 |
Date | December 30, 2005 | June 9, 2010 | December 31, 2010 | |
Comment | A work plan for the TA to be prepared by the PMO/SPEPB was not delivered |
Component A: Online monitoring system | Value | Not applicable | Operational | |
Date | December 30, 2005 | May 31, 2011 | December 31, 2010 | |
Comment | A work plan for the TA to be prepared by the PMO/SPEPB was not delivered |
Component A: SO2 control policy and regulation prepared | Value | Not applicable | N/A | Operational |
Date | December 30, 2005 | March 1, 2012 | December 31, 2010 | |
Comment | A work plan for the TA to be prepared by the PMO/SPEPB was not delivered |
Component B: Installation of FGDs and CEMs at the four sites on schedule | Value | Not applicable | N/A | Operational |
Date | December 30, 2005 | March 1, 2012 | December 31, 2010 | |
Comment | The three other sub-component were dropped and the task team is currently reviewing options for replacements |
Component B: Achievement of the target SO2 removal efficiency (%) | Value | 0 | N/A | 90-95 |
Date | December 30, 2005 | March 1, 2012 | December 31, 2010 | |
Comment |
Component B: Total tonnages of SO2 removed annually at the four sites | Value | 0 | N/A | 58645 |
Date | December 30, 2005 | March 1, 2012 | December 31, 2010 | |
Comment |
Component B: Achievement of the target emission rate (400 mg/NM3) | Value | Not applicable | N/A | All |
Date | December 30, 2005 | March 1, 2012 | December 31, 2010 | |
Comment |