BR Municipal APL: Sao Luis Enhancing Municipal Governance and Quality of Life Project

Abstract*

The objective of the Sao Luis Enhancing Municipal Governance and Quality of Life Project for Brazil is to improve public service in the Bacanga Basin of Sao Luis Municipality, and enhance the capacity of the city government in promoting local economic development and municipal management. There are three components to the project. The first component concerns local economic development and municipal management strengthening. This component will support...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the São Luís Enhancing Municipal Governance and Quality of Life Project is to improve public service in the Bacanga Basin of São Luís Municipality, and enhance the capacity of the city government in promoting local economic development and municipal management.

Key Details

Project Details

  • P094315

  • Closed

  • Emanuela Monteiro , Juliana Garrido

  • N/A

  • Brazil

  • January 9, 2006

  • (as of board presentation)

    July 17, 2008

  • January 28, 2009

  • US$ 59.40 million

  • Secretaria Municipal de Projetos Especiais SEMPE

  • Latin America and Caribbean

  • 2009

  • US$ 35.64 million

  • A

  • Not Applicable

  • October 30, 2015

  • BANK APPROVED

  • November 14, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 23.76
International Bank for Reconstruction and Development 35.64

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 35.64
IDA Commitment N/A
IBRD + IDA Commitment 35.64
Lending Instrument
Grant Amount N/A
Total Project Cost** 59.40

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 2, 2013 IBRD-75780 Loan Repay 295,458.12
Sep 25, 2013 IBRD-75780 Loan Disb 470,279.80
Nov 15, 2015 IBRD-75780 Int Charges 43,889.96
Nov 15, 2015 IBRD-75780 Loan Repay 420,384.34
Nov 15, 2015 IBRD-75780 Int Charges 202.68
Aug 10, 2015 IBRD-75780 Loan Disb 794,834.20
Apr 7, 2015 IBRD-75780 Loan Disb 505,307.44
Jul 10, 2015 IBRD-75780 Loan Disb 368,349.22
May 15, 2023 IBRD-75780 Int Charges 383,744.90
May 15, 2023 IBRD-75780 Loan Repay 95,991.14
May 15, 2023 IBRD-75780 Loan Repay 383,744.90
Nov 15, 2022 IBRD-75780 Loan Repay 479,736.06
May 15, 2017 IBRD-75780 Int Charges 34.91
Nov 17, 2016 IBRD-75780 Int Charges 103,555.20
Nov 15, 2016 IBRD-75780 Int Charges 47.72
Nov 17, 2016 IBRD-75780 Loan Repay 479,736.06
May 15, 2016 IBRD-75780 Int Charges 502.32
May 15, 2016 IBRD-75780 Int Charges 70,737.34
May 15, 2016 IBRD-75780 Loan Repay 481,673.30
Apr 14, 2016 IBRD-75780 Loan Cancel 12,285,032.00
May 15, 2019 IBRD-75780 Int Charges 273,831.38
May 15, 2019 IBRD-75780 Loan Repay 479,736.06
Nov 15, 2018 IBRD-75780 Int Charges 252,147.27
Nov 15, 2018 IBRD-75780 Loan Repay 479,736.06
May 15, 2018 IBRD-75780 Int Charges 165,203.31
May 15, 2018 IBRD-75780 Loan Repay 479,736.06
Nov 15, 2020 IBRD-75780 Int Charges 64,461.79
Nov 15, 2020 IBRD-75780 Loan Repay 479,736.06
May 15, 2021 IBRD-75780 Int Charges 25,335.62
May 15, 2021 IBRD-75780 Loan Repay 454,400.44
May 15, 2020 IBRD-75780 Int Charges 176,845.64
May 15, 2020 IBRD-75780 Loan Repay 479,736.06
Nov 15, 2019 IBRD-75780 Int Charges 246,068.60
Nov 15, 2019 IBRD-75780 Loan Repay 479,736.06
Nov 15, 2022 IBRD-75780 Int Charges 157,776.77
May 15, 2022 IBRD-75780 Loan Repay 479,736.06
May 15, 2022 IBRD-75780 Int Charges 2.71
May 15, 2022 IBRD-75780 Int Charges 22,295.87
Nov 15, 2021 IBRD-75780 Int Charges 20,015.97
Nov 15, 2021 IBRD-75780 Loan Repay 131,494.05
Nov 16, 2021 IBRD-75780 Loan Repay 348,242.00
May 15, 2021 IBRD-75780 Loan Repay 25,335.62
Jul 17, 2008 IBRD-75780 Loan Commitment 35,640,000.00
May 15, 2024 IBRD-75780 Int Charges 410,200.40
May 15, 2024 IBRD-75780 Loan Repay 479,736.06
Nov 15, 2023 IBRD-75780 Int Charges 397,396.44
Nov 15, 2023 IBRD-75780 Loan Repay 479,736.06
May 15, 2015 IBRD-75780 Loan Repay 377,897.53
May 15, 2015 IBRD-75780 Int Charges 405.32
May 15, 2015 IBRD-75780 Int Charges 33,697.95
Apr 14, 2016 IBRD-75780 Loan Disb -85,264.29
Sep 10, 2015 IBRD-75780 Loan Disb 289,426.56
Dec 7, 2015 IBRD-75780 Loan Disb 933,849.56
Nov 25, 2015 IBRD-75780 Loan Disb 511,488.80
Oct 21, 2015 IBRD-75780 Loan Disb 994,150.94
Oct 1, 2015 IBRD-75780 Loan Disb 321,274.97
Nov 15, 2017 IBRD-75780 Int Charges 153,493.45
Nov 15, 2017 IBRD-75780 Loan Repay 479,736.06
May 15, 2017 IBRD-75780 Int Charges 135,910.06
May 15, 2017 IBRD-75780 Loan Repay 479,736.06
Dec 9, 2014 IBRD-75780 Loan Disb 931,317.75
Nov 15, 2014 IBRD-75780 Int Charges 30,811.44
Nov 15, 2014 IBRD-75780 Loan Repay 341,589.90
Sep 25, 2014 IBRD-75780 Loan Disb 773,265.60
May 15, 2014 IBRD-75780 Loan Repay 323,237.25
May 15, 2014 IBRD-75780 Int Charges 32,220.16
May 15, 2014 IBRD-75780 Int Charges 319.79
May 15, 2014 IBRD-75780 Int Charges 57.20
Jun 6, 2014 IBRD-75780 Loan Disb 882,339.90
Nov 18, 2013 IBRD-75780 Loan Disb 513,720.62
Feb 19, 2014 IBRD-75780 Loan Disb 377,721.72
Dec 2, 2013 IBRD-75780 Int Charges 36,242.85

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Unsatisfactory 2015-10-29
Procurement Unsatisfactory 2015-10-29
Counterpart Funding Unsatisfactory 2015-10-29
Project Management Moderately Unsatisfactory 2015-10-29
Financial Management Moderately Satisfactory 2015-10-29
Monitoring and Evaluation Moderately Unsatisfactory 2015-10-29
Overall Implementation Progress (IP) Moderately Unsatisfactory 2015-10-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 04-29-2016
OutcomesUnsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceUnsatisfactory
Borrower PerformanceUnsatisfactory
Government PerformanceUnsatisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-31-2017PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Development of the local economic development strategy, and budget allocated to undertake main actions from the strategyValueForum of Sustainability Development in Sao LuisActivities under the LED strategy were developed: Main actions from the strategy implemented
    DateOctober 1, 2008October 29, 2015October 30, 2015
    Comment
  • Development of a competitiveness enhancement plan for one economic cluster, and implementation of recommended short-term actions from the plan by the end of projectValueNo planCompetitiveness enhancement plan for the tourism cCompetitiveness enhancement plan for the tourism c
    DateOctober 1, 2008October 29, 2015October 30, 2015
    Comment
  • Increased consumer satisfaction with water, sanitation, drainage, and urban servicesValueNo survey conductedOne survey conducted (baseline). The procurement pSurvey conducted, and aggregate population satisfa
    DateOctober 1, 2008October 29, 2015October 30, 2015
    Comment
  • Increases in percent of sewage collected and treated in the targeted areaValueCollected: 39%, treated: 4%Collected: 39%, treated: 4%Collected: 80%, treated: 41%
    DateOctober 1, 2008October 29, 2015October 30, 2015
    Comment
  • Project targeted areas acquire macro drainage capacity to handle an intense storm every 25 years and micro drainage capacity for a storm every 5 yearsValueNo capacityCapacity improved: Macro drainage works in the CorCapacity exists
    DateOctober 1, 2008October 29, 2015October 30, 2015
    Comment
  • Families threatened with flooding from regular tidal movements of the Bacanga Lake in project targeted area be relocated to the satisfaction of residentsValue018% (108 families voluntarily resettled in the hou100%
    DateOctober 1, 2008October 29, 2015October 30, 2015
    Comment
  • Direct project beneficiariesValue0.006287.0092500.00
    DateOctober 29, 2015October 30, 2015
    Comment
  • Female beneficiariesValue0.003350.0046250.00
    DateOctober 29, 2015October 30, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • People trained in Project areaValue100676676
    DateOctober 1, 2008October 29, 2015October 30, 2015
    Comment
  • Bacanga Dam floodgates completely repaired and operated effectivelyValueFloodgates operating inadequatelyFloodgates operating inadequatelyBacanga dam repaired and floodgates properly opera
    DateOctober 1, 2008October 29, 2015October 30, 2015
    Comment
  • Integrated water, drainage, sanitation and solid waste plan developed and adoptedValueNo planIntegrated Municipal Sanitation Plan (WSS, drainagPlan approved and adopted
    DateOctober 1, 2008October 29, 2015October 30, 2015
    Comment
  • Development and implementation of actions for strengthening the Borrower’s procurement systemValueActions from the Strategy implementedActions from the Strategy implemented
    DateOctober 29, 2015October 30, 2015
    Comment
  • Micro-enterprises assisted in Project area (cumulative)Value5.00540.00540.00
    DateDecember 31, 2008October 29, 2015October 30, 2015
    Comment
  • Sewage collectedValue39.0039.0080.00
    DateDecember 31, 2008October 29, 2015October 30, 2015
    Comment
  • Number of people in urban areas provided with access to Improved Sanitation under the projectValue0.000.0073840.00
    DateOctober 29, 2015October 30, 2015
    Comment
  • Intervention area flooded in 25 year rainValue40.000.000.00
    DateDecember 31, 2008August 7, 2015October 30, 2015
    Comment
  • Intervention area flooded in 5 year rainValue10.000.000.00
    DateDecember 31, 2008August 7, 2015October 30, 2015
    Comment
  • Sewage treatedValue4.004.0041.00
    DateDecember 31, 2008October 29, 2015October 30, 2015
    Comment
  • Satisfaction of the population that was resettledValueSurveys not yet conducted.Survey conducted & Results satisfactory
    DateOctober 29, 2015October 30, 2015
    Comment
  • Number of people in urban areas provided with access to Improved Water Sources under the projectValue0.001720.0077551.00
    DateOctober 29, 2015October 30, 2015
    Comment
  • Families living in flood prone areas benefiting from improved drainageValue0.002083.004166.00
    DateDecember 31, 2008October 29, 2015October 30, 2015
    Comment
  • Roads rehabilitated, Non-ruralValue0.005.4262.00
    DateDecember 31, 2008October 29, 2015October 30, 2015
    Comment
  • Public space (green areas, urban parks etc.) created as a result of the projectValue0.006057.2483585.50
    DateDecember 31, 2008October 29, 2015October 30, 2015
    Comment
  • Target popln with use or ownership rights recorded as a result of the projectValue0.000.003000.00
    DateDecember 31, 2008October 29, 2015October 30, 2015
    Comment