Financier | Commitments |
---|---|
Borrower/Recipient | 25.36 |
IDA Credit | 172.34 |
P094513
Closed
Shankar Narayanan
N/A
March 21, 2005
(as of board presentation)
May 3, 2005
August 9, 2005
US$ 197.70 million
N/A
2005
US$ 172.34 million
B
March 31, 2014
December 31, 2011
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 25.36 |
IDA Credit | 172.34 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 172.34 |
IBRD + IDA Commitment | 172.34 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 197.70 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 15, 2015 | IDA-40540 | Loan Repay | 137,544.84 |
Apr 15, 2015 | IDA-40540 | Loan Repay | 3,533,114.20 |
Apr 15, 2015 | IDA-40540 | Int Charges | 536,833.80 |
Apr 15, 2015 | IDA-40540 | Int Charges | 536,833.80 |
Apr 15, 2017 | IDA-40540 | Loan Repay | 3,574,745.50 |
May 11, 2016 | IDA-40540 | Loan Cancel | 267,161.25 |
May 11, 2016 | IDA-40540 | Loan Disb | -267,161.25 |
Oct 15, 2016 | IDA-40540 | Loan Repay | 707.49 |
Oct 15, 2016 | IDA-40540 | Loan Repay | 3,678,838.20 |
Oct 15, 2016 | IDA-40540 | Int Charges | 496,879.80 |
Oct 15, 2016 | IDA-40540 | Int Charges | 496,879.80 |
Apr 15, 2016 | IDA-40540 | Int Charges | 521,541.10 |
Apr 15, 2016 | IDA-40540 | Int Charges | 521,541.10 |
Apr 15, 2016 | IDA-40540 | Int Charges | 43,250.22 |
Apr 15, 2016 | IDA-40540 | Int Charges | 43,250.22 |
Apr 15, 2016 | IDA-40540 | Loan Repay | 501,725.66 |
Apr 15, 2016 | IDA-40540 | Loan Repay | 3,257,129.00 |
Apr 15, 2018 | IDA-40540 | Int Charges | 23,070.50 |
Apr 15, 2018 | IDA-40540 | Int Charges | 23,070.50 |
Apr 15, 2018 | IDA-40540 | Loan Repay | 3,881,800.00 |
Apr 15, 2018 | IDA-40540 | Int Charges | 480,372.75 |
Apr 15, 2018 | IDA-40540 | Int Charges | 480,372.75 |
Oct 15, 2017 | IDA-40540 | Int Charges | 27,290.97 |
Oct 15, 2017 | IDA-40540 | Int Charges | 27,290.97 |
Oct 15, 2017 | IDA-40540 | Loan Repay | 3,775,975.50 |
Oct 15, 2017 | IDA-40540 | Int Charges | 458,995.34 |
Oct 15, 2017 | IDA-40540 | Int Charges | 458,995.34 |
Apr 15, 2017 | IDA-40540 | Int Charges | 449,709.56 |
Apr 15, 2017 | IDA-40540 | Loan Repay | 51,287.41 |
Apr 15, 2017 | IDA-40540 | Int Charges | 449,709.56 |
Oct 15, 2019 | IDA-40540 | Loan Repay | 3,658,434.20 |
Oct 15, 2019 | IDA-40540 | Int Charges | 411,573.88 |
Oct 15, 2019 | IDA-40540 | Int Charges | 411,573.88 |
Apr 15, 2019 | IDA-40540 | Int Charges | 384,914.03 |
Apr 15, 2019 | IDA-40540 | Int Charges | 384,914.03 |
Apr 15, 2019 | IDA-40540 | Int Charges | 43,027.22 |
Apr 15, 2019 | IDA-40540 | Int Charges | 43,027.22 |
Apr 15, 2019 | IDA-40540 | Loan Repay | 3,711,226.20 |
Apr 15, 2019 | IDA-40540 | Int Charges | 34,655.94 |
Apr 15, 2019 | IDA-40540 | Int Charges | 34,655.94 |
Oct 15, 2018 | IDA-40540 | Loan Repay | 3,718,243.50 |
Oct 15, 2018 | IDA-40540 | Int Charges | 404,443.70 |
Oct 15, 2018 | IDA-40540 | Int Charges | 404,443.70 |
Oct 15, 2018 | IDA-40540 | Loan Repay | 12,573.05 |
Oct 15, 2020 | IDA-40540 | Loan Repay | 1,879,190.40 |
Oct 15, 2020 | IDA-40540 | Int Charges | 392,597.94 |
Oct 15, 2020 | IDA-40540 | Int Charges | 392,597.94 |
Oct 15, 2020 | IDA-40540 | Loan Repay | 2,663.30 |
Apr 15, 2020 | IDA-40540 | Loan Repay | 3,636,539.50 |
Apr 15, 2020 | IDA-40540 | Loan Repay | 10,898.59 |
Apr 15, 2020 | IDA-40540 | Int Charges | 396,658.88 |
Apr 15, 2020 | IDA-40540 | Int Charges | 396,658.88 |
Oct 15, 2019 | IDA-40540 | Int Charges | 11,691.38 |
Oct 15, 2019 | IDA-40540 | Int Charges | 11,691.38 |
Apr 15, 2022 | IDA-40540 | Loan Repay | 1,808,117.90 |
Apr 15, 2022 | IDA-40540 | Int Charges | 362,428.06 |
Apr 15, 2022 | IDA-40540 | Int Charges | 362,428.06 |
Oct 15, 2021 | IDA-40540 | Loan Repay | 1,862,765.40 |
Oct 15, 2021 | IDA-40540 | Int Charges | 95,593.40 |
Oct 15, 2021 | IDA-40540 | Int Charges | 95,593.40 |
Oct 15, 2021 | IDA-40540 | Loan Repay | 19,568.26 |
Oct 15, 2021 | IDA-40540 | Int Charges | 285,956.62 |
Oct 15, 2021 | IDA-40540 | Int Charges | 285,956.62 |
Apr 15, 2021 | IDA-40540 | Int Charges | 3,004.67 |
Apr 15, 2021 | IDA-40540 | Int Charges | 3,004.67 |
Apr 15, 2021 | IDA-40540 | Loan Repay | 1,904,624.90 |
Apr 15, 2021 | IDA-40540 | Int Charges | 393,210.84 |
Apr 15, 2021 | IDA-40540 | Int Charges | 393,210.84 |
Apr 15, 2023 | IDA-40540 | Loan Repay | 128,563.09 |
Apr 15, 2023 | IDA-40540 | Loan Repay | 3,486,794.00 |
Apr 15, 2023 | IDA-40540 | Int Charges | 288,726.10 |
Apr 15, 2023 | IDA-40540 | Int Charges | 288,726.10 |
Oct 15, 2022 | IDA-40540 | Loan Repay | 55,050.76 |
Oct 15, 2022 | IDA-40540 | Loan Repay | 1,625,233.60 |
Oct 15, 2022 | IDA-40540 | Loan Repay | 1,726,653.00 |
Oct 15, 2022 | IDA-40540 | Int Charges | 332,200.78 |
Oct 15, 2022 | IDA-40540 | Int Charges | 332,200.78 |
Apr 15, 2022 | IDA-40540 | Loan Repay | 13,581.26 |
May 3, 2005 | IDA-40540 | Loan Commitment | 465,000,000.00 |
Apr 15, 2024 | IDA-40540 | Loan Repay | 66,085.10 |
Apr 15, 2024 | IDA-40540 | Loan Repay | 3,447,264.00 |
Apr 15, 2024 | IDA-40540 | Int Charges | 303,051.47 |
Apr 15, 2024 | IDA-40540 | Int Charges | 303,051.47 |
Oct 15, 2023 | IDA-40540 | Int Charges | 314,677.10 |
Oct 15, 2023 | IDA-40540 | Int Charges | 314,677.10 |
Oct 15, 2023 | IDA-40540 | Int Charges | 48,582.75 |
Oct 15, 2023 | IDA-40540 | Int Charges | 48,582.75 |
Oct 15, 2023 | IDA-40540 | Loan Repay | 3,496,134.20 |
Apr 15, 2014 | IDA-40540 | Int Charges | 4,817.75 |
Apr 15, 2014 | IDA-40540 | Int Charges | 4,817.75 |
Apr 15, 2014 | IDA-40540 | Int Charges | 619,380.90 |
Apr 15, 2014 | IDA-40540 | Int Charges | 619,380.90 |
Oct 15, 2013 | IDA-40540 | Int Charges | 7,889.20 |
Oct 15, 2013 | IDA-40540 | Int Charges | 7,889.20 |
Oct 15, 2013 | IDA-40540 | Int Charges | 601,116.60 |
Oct 15, 2013 | IDA-40540 | Int Charges | 601,116.60 |
Oct 15, 2014 | IDA-40540 | Int Charges | 595,417.44 |
Oct 15, 2014 | IDA-40540 | Int Charges | 595,417.44 |
Oct 15, 2014 | IDA-40540 | Int Charges | 1,523.32 |
Oct 15, 2014 | IDA-40540 | Int Charges | 1,523.32 |
Oct 15, 2014 | IDA-40540 | Loan Repay | 3,969,449.50 |
Oct 15, 2015 | IDA-40540 | Int Charges | 496,705.84 |
Oct 15, 2015 | IDA-40540 | Loan Repay | 131,471.70 |
Oct 15, 2015 | IDA-40540 | Int Charges | 496,705.84 |
Oct 15, 2015 | IDA-40540 | Loan Repay | 3,660,356.00 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Satisfactory | 2011-07-05 |
Monitoring and Evaluation | Moderately Satisfactory | 2011-07-05 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2011-07-05 |
Procurement | Moderately Satisfactory | 2011-07-05 |
Project Management | Moderately Satisfactory | 2011-07-05 |
Counterpart Funding | Satisfactory | 2011-07-05 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2011-07-05 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-25-2012 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 05-29-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | Unsatisfactory | N/a |
Government Performance | Unsatisfactory | N/a |
Implementing Agency | Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of the beneficiaries living in the reconstructed housing units | Value | N/A | about 40% | 80% |
Date | March 31, 2005 | June 15, 2011 | April 30, 2008 | |
Comment | All damaged houses have been reconstructed |
Number of boats using the reconstructed fishing harbors | Value | Being tendered | 80% | |
Date | June 15, 2011 | April 30, 2008 | ||
Comment |
Share of restored agricultural land used by farmers | Value | Restoration of agricultural lands 100% completed | 90% | |
Date | May 14, 2010 | April 30, 2008 | ||
Comment |
Extent of the use of reconstructed animal husbandry infrastructure by farmers relative to pre-tsunami period (Tamil Nadu only) | Value | Reconstruction to begin in 2007 | 90% | |
Date | June 15, 2011 | April 30, 2008 | ||
Comment | Animal Husbandry infrastructure reconstruction 100% complete. | Completed |
Percent of communities/homeowners (also beyond project beneficiaries) sensitized and willing to reconstruct their houses to disaster resistant standards | Value | N/A | 80% | |
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
Percent of communities participated in awareness program on early warning systems. | Value | N/A | 80% | |
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
Reduced distance and traveling time to evacuation shelters to percentage of communities. | Value | N/A | 80% | |
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
Percent of fully functional and community-owned evacuation shelters. | Value | 78 | Construction of evacuation shelters yet to begin. | 80% |
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
Overall no. and percent of houses completed to disaster resistant standards. | Value | 17000 | 80% | |
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
Percent of Districts which substantially complete reconstruction. | Value | 11 | 80% | |
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
Total and percent amount (of original estimate) disbursed to contractors. | Value | 80% | ||
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
Number of VHS and Public Address Systems Installed. | Value | 1000 | 80% | |
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
Percent increase in coverage of early warning systems. | Value | 40% | 80% | |
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
Number of evacuation shelters constructed. | Value | 78 | 40% | 80% |
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
Number of spot improvement projects implemented o Kilometers of roads constructed or reconstructed/rehabilitated | Value | 150km | 40% | 80% |
Date | August 14, 2009 | June 15, 2011 | December 31, 2011 | |
Comment | This is currently not being monitored - task team is reviewing the indicators and will adjust them during July-Aug 2011. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of the beneficiaries living in the reconstructed housing units | Value | about 40% | 80% | |
Date | March 31, 2005 | June 4, 2007 | April 30, 2008 | |
Comment | 100% reconstructed houses are occupied. |