Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 22.00 |
Borrower/Recipient | 5.40 |
P095012
Closed
Philip Bottern
Government of Tunisia
July 19, 2005
(as of board presentation)
March 13, 2007
July 20, 2007
US$ 27.40 million
AG NATIONALE GESTION DECHETS
2007
US$ 22.00 million
B
February 10, 2015
June 30, 2014
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 22.00 |
Borrower/Recipient | 5.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 22.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 22.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 27.40 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2022 | IBRD-74320 | Int Charges | 35,259.03 |
Feb 15, 2022 | IBRD-74320 | Loan Repay | 219,981.86 |
Feb 15, 2022 | IBRD-74320 | Loan Repay | 445,358.70 |
Aug 15, 2021 | IBRD-74320 | Int Charges | 48,247.22 |
Aug 15, 2021 | IBRD-74320 | Loan Repay | 307,586.47 |
Aug 15, 2021 | IBRD-74320 | Loan Repay | 622,589.56 |
Mar 13, 2007 | IBRD-74320 | Loan Commitment | 22,000,000.00 |
Aug 15, 2023 | IBRD-74320 | Int Charges | 4,308.53 |
Aug 15, 2023 | IBRD-74320 | Int Charges | 9,708.21 |
Aug 15, 2023 | IBRD-74320 | Loan Repay | 254,286.39 |
Aug 15, 2023 | IBRD-74320 | Loan Repay | 515,023.97 |
Feb 15, 2023 | IBRD-74320 | Int Charges | 2,404.66 |
Feb 15, 2023 | IBRD-74320 | Int Charges | 17,435.34 |
Feb 15, 2023 | IBRD-74320 | Loan Repay | 207,670.17 |
Feb 15, 2023 | IBRD-74320 | Loan Repay | 420,433.38 |
Oct 31, 2014 | IBRD-74320 | Loan Disb | -583,414.44 |
Feb 15, 2014 | IBRD-74320 | Int Charges | 4,055.39 |
Feb 15, 2014 | IBRD-74320 | Int Charges | 16,343.97 |
Feb 15, 2014 | IBRD-74320 | Int Charges | 238,344.20 |
Feb 15, 2014 | IBRD-74320 | Loan Repay | 320,949.84 |
Feb 15, 2014 | IBRD-74320 | Loan Repay | 672,566.90 |
Feb 27, 2014 | IBRD-74320 | Loan Disb | 871,476.75 |
Aug 15, 2013 | IBRD-74320 | Int Charges | 502.03 |
Aug 15, 2013 | IBRD-74320 | Int Charges | 1,107.37 |
Aug 15, 2013 | IBRD-74320 | Int Charges | 3,912.99 |
Aug 15, 2013 | IBRD-74320 | Int Charges | 16,111.29 |
Aug 15, 2013 | IBRD-74320 | Int Charges | 235,912.73 |
Aug 15, 2013 | IBRD-74320 | Loan Repay | 124,367.91 |
Aug 15, 2013 | IBRD-74320 | Loan Repay | 260,734.66 |
Aug 15, 2015 | IBRD-74320 | Int Charges | 163,273.40 |
Nov 11, 2014 | IBRD-74320 | Loan Cancel | 2,697,876.20 |
Aug 15, 2014 | IBRD-74320 | Int Charges | 220,208.81 |
Aug 15, 2014 | IBRD-74320 | Loan Repay | 361,138.00 |
Aug 15, 2014 | IBRD-74320 | Loan Repay | 656,301.60 |
Aug 15, 2014 | IBRD-74320 | Int Charges | 2,905.19 |
Aug 15, 2014 | IBRD-74320 | Int Charges | 19,539.50 |
Feb 15, 2015 | IBRD-74320 | Int Charges | 13,191.67 |
Feb 15, 2015 | IBRD-74320 | Int Charges | 177,390.66 |
Feb 15, 2015 | IBRD-74320 | Loan Repay | 276,708.47 |
Feb 15, 2015 | IBRD-74320 | Loan Repay | 560,157.56 |
Feb 15, 2015 | IBRD-74320 | Int Charges | 1,216.35 |
Aug 15, 2015 | IBRD-74320 | Loan Repay | 357,504.03 |
Aug 15, 2015 | IBRD-74320 | Loan Repay | 723,637.25 |
Aug 15, 2015 | IBRD-74320 | Int Charges | 6,146.80 |
Aug 15, 2015 | IBRD-74320 | Int Charges | 1,596.81 |
Aug 15, 2016 | IBRD-74320 | Loan Repay | 712,481.70 |
Aug 15, 2016 | IBRD-74320 | Int Charges | 2,705.58 |
Aug 15, 2016 | IBRD-74320 | Int Charges | 136,162.39 |
Aug 15, 2016 | IBRD-74320 | Loan Repay | 351,884.56 |
Feb 15, 2016 | IBRD-74320 | Int Charges | 6,423.45 |
Feb 15, 2016 | IBRD-74320 | Int Charges | 149,887.30 |
Feb 15, 2016 | IBRD-74320 | Loan Repay | 352,577.62 |
Feb 15, 2016 | IBRD-74320 | Loan Repay | 713,885.00 |
Feb 15, 2017 | IBRD-74320 | Int Charges | 1,087.38 |
Feb 15, 2017 | IBRD-74320 | Int Charges | 115,991.17 |
Feb 15, 2017 | IBRD-74320 | Loan Repay | 102,318.49 |
Feb 15, 2017 | IBRD-74320 | Loan Repay | 207,184.45 |
Feb 15, 2018 | IBRD-74320 | Loan Repay | 392,916.75 |
Feb 15, 2018 | IBRD-74320 | Loan Repay | 795,562.06 |
Feb 15, 2018 | IBRD-74320 | Int Charges | 132,429.20 |
Aug 15, 2017 | IBRD-74320 | Int Charges | 328.71 |
Aug 15, 2017 | IBRD-74320 | Int Charges | 124,757.93 |
Feb 15, 2019 | IBRD-74320 | Int Charges | 92,581.00 |
Feb 15, 2019 | IBRD-74320 | Loan Repay | 355,113.60 |
Feb 15, 2019 | IBRD-74320 | Loan Repay | 719,019.70 |
Aug 15, 2018 | IBRD-74320 | Int Charges | 106,572.28 |
Aug 15, 2018 | IBRD-74320 | Loan Repay | 356,578.44 |
Aug 15, 2018 | IBRD-74320 | Loan Repay | 721,985.70 |
Feb 15, 2021 | IBRD-74320 | Int Charges | 63,738.97 |
Feb 15, 2021 | IBRD-74320 | Loan Repay | 364,656.44 |
Feb 15, 2021 | IBRD-74320 | Loan Repay | 738,188.20 |
Aug 15, 2020 | IBRD-74320 | Int Charges | 62,039.51 |
Feb 15, 2020 | IBRD-74320 | Loan Repay | 319,049.12 |
Feb 15, 2020 | IBRD-74320 | Int Charges | 62,947.32 |
Feb 15, 2020 | IBRD-74320 | Loan Repay | 157,632.81 |
Aug 15, 2019 | IBRD-74320 | Loan Repay | 711,461.10 |
Aug 15, 2019 | IBRD-74320 | Int Charges | 78,196.68 |
Aug 15, 2019 | IBRD-74320 | Loan Repay | 351,380.50 |
Aug 15, 2022 | IBRD-74320 | Loan Repay | 197,840.20 |
Aug 15, 2022 | IBRD-74320 | Loan Repay | 400,532.34 |
Aug 15, 2022 | IBRD-74320 | Int Charges | 24,160.15 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2014-06-25 |
Overall Safeguards Rating | Moderately Unsatisfactory | 2014-06-25 |
Project Management | Moderately Satisfactory | 2014-06-25 |
Monitoring and Evaluation | Moderately Satisfactory | 2014-06-25 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2014-06-25 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2014-06-25 |
Procurement | Moderately Satisfactory | 2014-06-25 |
Financial Management | Moderately Unsatisfactory | 2014-06-25 |
Overall Safeguards Rating | Moderately Unsatisfactory | 2014-06-25 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-30-2014 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 05-28-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Unsatisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Unsatisfactory | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
The percentage of the Tunisian urban population living in areas serviced with sanitary landfills and large dumpsites have been closed | Value | 0.00 | 63.00 | 63.50 |
Date | June 30, 2012 | May 23, 2014 | June 30, 2014 | |
Comment |
The Government of Tunisia enters the emerging market for carbon credits by selling Certified Emissions Reductions. | Value | 0.00 | 3500000.00 | 4200000.00 |
Date | June 30, 2012 | June 30, 2014 | June 30, 2014 | |
Comment | The generated CERs have been/are being certified by the UNFCCC-CDM |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Continuous monitoring system for Clean Development Mechanism (CDM) operations within ANGed in order to maximize carbon emissions reductions. | Value | This is the first CDM project in Tunisia, and no e | An operational CDM monitoring system in place. | A fully operational monitoring system in place in |
Date | December 18, 2006 | May 23, 2014 | June 30, 2014 | |
Comment | Specialized TA continues to be provided to ANGed in the context of the regular supervision missions to maximize the benefit fromthe CF operations. |
Number of landfills equipped with land fill gases treatment systems as per the CDM requirements. | Value | 0.00 | 7.00 | 8.00 |
Date | June 30, 2012 | November 8, 2013 | June 30, 2014 | |
Comment | This is a new indicator which was introduced at project restructuring in June 2012. |
The performance of the National Solid Waste Management Program (PRONGID) is reviewed and a new sector policy is endorsed by the Board of ANGed | Value | none | Sector Policy approved by ANGed Board | |
Date | June 30, 2012 | May 23, 2014 | June 30, 2014 | |
Comment | The strategic review of the MSW Program is underway but may not be completed by the Project closing date |
Number of open dumps which are closed | Value | 1.00 | 8.00 | 8.00 |
Date | June 30, 2012 | May 23, 2013 | June 30, 2014 | |
Comment |
ANGed is equipped with new tools for planning, information management and monitoring and evaluation | Value | 0 | GIS System in place and operational | GIS system in place and operational |
Date | December 18, 2006 | May 23, 2014 | June 30, 2014 | |
Comment |