Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Borrower/Recipient | 4.30 |
European Bank for Reconstruction and Development | 13.14 |
Borrowing Country's Fin. Intermediary/ies | 43.40 |
P095155
Closed
Mirlan Aldayarov
N/A
June 13, 2005
(as of board presentation)
October 27, 2005
December 22, 2005
US$ 160.84 million
N/A
2006
US$ 113.14 million
B
January 15, 2013
November 30, 2011
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Borrower/Recipient | 4.30 |
European Bank for Reconstruction and Development | 13.14 |
Borrowing Country's Fin. Intermediary/ies | 43.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | 13.14 |
Total Project Cost** | 160.84 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 15, 2014 | IBRD-48050 | Int Charges | 204,504.38 |
Oct 27, 2005 | IBRD-48050 | Loan Commitment | 100,000,000.00 |
Apr 15, 2014 | IBRD-48050 | Int Charges | 230,195.38 |
Apr 15, 2014 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Oct 15, 2013 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Oct 15, 2013 | IBRD-48050 | Int Charges | 271,895.90 |
Oct 15, 2016 | IBRD-48050 | Int Charges | 339,793.53 |
Oct 15, 2016 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Apr 15, 2016 | IBRD-48050 | Int Charges | 249,749.56 |
Apr 15, 2016 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Oct 15, 2015 | IBRD-48050 | Int Charges | 227,128.98 |
Oct 15, 2015 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Apr 15, 2015 | IBRD-48050 | Int Charges | 201,331.23 |
Apr 15, 2015 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Apr 15, 2018 | IBRD-48050 | Int Charges | 2,282.19 |
Apr 15, 2018 | IBRD-48050 | Int Charges | 408,585.38 |
Apr 15, 2018 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Oct 15, 2017 | IBRD-48050 | Int Charges | 419,923.28 |
Oct 15, 2017 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Apr 15, 2017 | IBRD-48050 | Int Charges | 410,995.90 |
Apr 15, 2017 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Apr 15, 2020 | IBRD-48050 | Int Charges | 306,451.25 |
Apr 15, 2020 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Oct 15, 2019 | IBRD-48050 | Int Charges | 453,344.70 |
Oct 15, 2019 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Apr 15, 2019 | IBRD-48050 | Int Charges | 515,188.80 |
Apr 15, 2019 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Oct 15, 2018 | IBRD-48050 | Int Charges | 549,077.25 |
Oct 15, 2018 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Oct 15, 2021 | IBRD-48050 | Int Charges | 46,165.90 |
Oct 15, 2021 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Apr 15, 2021 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Apr 15, 2021 | IBRD-48050 | Int Charges | 61,169.35 |
Oct 15, 2020 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Oct 15, 2020 | IBRD-48050 | Int Charges | 177,574.22 |
Apr 15, 2023 | IBRD-48050 | Int Charges | 4,210.69 |
Oct 15, 2022 | IBRD-48050 | Int Charges | 52,248.89 |
Oct 15, 2022 | IBRD-48050 | Loan Repay | 4,117,019.00 |
Apr 15, 2022 | IBRD-48050 | Int Charges | 28,172.18 |
Apr 15, 2022 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Oct 15, 2014 | IBRD-48050 | Loan Repay | 4,077,855.80 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2011-06-27 |
Progress towards achievement of PDO | Satisfactory | 2011-06-27 |
Procurement | Satisfactory | 2011-06-27 |
Project Management | Satisfactory | 2011-06-27 |
Financial Management | Satisfactory | 2011-06-27 |
Counterpart Funding | Satisfactory | 2011-06-27 |
Monitoring and Evaluation | Satisfactory | 2011-06-27 |
Overall Implementation Progress (IP) | Satisfactory | 2011-06-27 |
Overall Safeguards Rating | Satisfactory | 2011-06-27 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-31-2012 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 11-04-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PDO: Increased volume of electricity transfer from northern Kazakhstan to markets in southern Kazakhstan to reduce power deficit and improve quality of electricity supply. | Value | 650 MW (3.9 TWh) electricity transfer from norther | 1,350 MW (7.5 TWh) electricity transfer through No | 1,350 MW (7.5 TWh) electricity transfer through No |
Date | December 31, 2005 | May 18, 2011 | December 31, 2009 | |
Comment |
PDO: Promote competition in the electricity market. | Value | Transmission tariffs inadequately supportive of co | Efficient transmission tariff methodology has been | Zonal tranmsission tariffs implemented and later ( |
Date | December 31, 2005 | May 18, 2011 | November 30, 2011 | |
Comment |
PDO: Promote competition in electricity market. | Value | No functioning real time balancing market (BM). | BM is operated in trial mode. | Establishment of BM. |
Date | December 31, 2005 | May 18, 2011 | November 30, 2011 | |
Comment | The BM has been undergoing comprehensive performance testing and fine-tuning based on market participant feedback. Under GOKorder,the BM will start live operation on Jan. 1, 2012. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduction in the frequency of emergency outages on the North/Sourh interconnector. | Value | 13 | 4 | 8 |
Date | December 31, 2005 | May 18, 2011 | November 30, 2011 | |
Comment | Number of "first grade" technological failures. | Number of "first grade" technological failures. |
Reduction in trasmission losses on North-South interconector. | Value | 8.8% | 5.3% | 6.5% |
Date | December 31, 2005 | May 18, 2011 | November 30, 2011 | |
Comment | KEGOC transmission system as a whole. | KEGOC transmission system as a whole. |
Susbstations completed | Value | 0.00 | 67.00 | 67.00 |
Date | December 31, 2009 | May 18, 2011 | December 31, 2010 | |
Comment | Substations to be completed. | All 67 substations fully completed and commissioned ("red phase') by end-2010. | All substations completed/commissioned. |