North-South Electricity Transmission Project

Abstract*

The North-South Electricity Transmission Project for Kazakhstan will ensure that business enterprises and households in southern Kazakhstan have access to adequate, reliable and cost effective supply of electricity. The project consists of the following components: (a) involves construction of a new 475 km 500 kV single circuit overhead line (OHL) from the air-insulated substation Ekibastuz (1,150/500 kV) to the airinsulated substation Agadyr (500...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The primary development objective is to ensure that business enterprises and households in southern Kazakhstan have access to a reliable, cost effective and high quality supply of electricity. The project also aims to promote competition on the electicity market.

Key Details

Project Details

  • P095155

  • Closed

  • Mirlan Aldayarov

  • N/A

  • Kazakhstan

  • June 13, 2005

  • (as of board presentation)

    October 27, 2005

  • December 22, 2005

  • US$ 113.14 million

  • B

  • January 15, 2013

  • November 30, 2011

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 100.00
Borrower/Recipient 4.30
European Bank for Reconstruction and Development 13.14
Borrowing Country's Fin. Intermediary/ies 43.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 100.00
IDA Commitment N/A
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount 13.14
Total Project Cost** 160.84

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 15, 2014 IBRD-48050 Int Charges 204,504.38
Oct 27, 2005 IBRD-48050 Loan Commitment 100,000,000.00
Apr 15, 2014 IBRD-48050 Int Charges 230,195.38
Apr 15, 2014 IBRD-48050 Loan Repay 4,077,855.80
Oct 15, 2013 IBRD-48050 Loan Repay 4,077,855.80
Oct 15, 2013 IBRD-48050 Int Charges 271,895.90
Oct 15, 2016 IBRD-48050 Int Charges 339,793.53
Oct 15, 2016 IBRD-48050 Loan Repay 4,077,855.80
Apr 15, 2016 IBRD-48050 Int Charges 249,749.56
Apr 15, 2016 IBRD-48050 Loan Repay 4,077,855.80
Oct 15, 2015 IBRD-48050 Int Charges 227,128.98
Oct 15, 2015 IBRD-48050 Loan Repay 4,077,855.80
Apr 15, 2015 IBRD-48050 Int Charges 201,331.23
Apr 15, 2015 IBRD-48050 Loan Repay 4,077,855.80
Apr 15, 2018 IBRD-48050 Int Charges 2,282.19
Apr 15, 2018 IBRD-48050 Int Charges 408,585.38
Apr 15, 2018 IBRD-48050 Loan Repay 4,077,855.80
Oct 15, 2017 IBRD-48050 Int Charges 419,923.28
Oct 15, 2017 IBRD-48050 Loan Repay 4,077,855.80
Apr 15, 2017 IBRD-48050 Int Charges 410,995.90
Apr 15, 2017 IBRD-48050 Loan Repay 4,077,855.80
Apr 15, 2020 IBRD-48050 Int Charges 306,451.25
Apr 15, 2020 IBRD-48050 Loan Repay 4,077,855.80
Oct 15, 2019 IBRD-48050 Int Charges 453,344.70
Oct 15, 2019 IBRD-48050 Loan Repay 4,077,855.80
Apr 15, 2019 IBRD-48050 Int Charges 515,188.80
Apr 15, 2019 IBRD-48050 Loan Repay 4,077,855.80
Oct 15, 2018 IBRD-48050 Int Charges 549,077.25
Oct 15, 2018 IBRD-48050 Loan Repay 4,077,855.80
Oct 15, 2021 IBRD-48050 Int Charges 46,165.90
Oct 15, 2021 IBRD-48050 Loan Repay 4,077,855.80
Apr 15, 2021 IBRD-48050 Loan Repay 4,077,855.80
Apr 15, 2021 IBRD-48050 Int Charges 61,169.35
Oct 15, 2020 IBRD-48050 Loan Repay 4,077,855.80
Oct 15, 2020 IBRD-48050 Int Charges 177,574.22
Apr 15, 2023 IBRD-48050 Int Charges 4,210.69
Oct 15, 2022 IBRD-48050 Int Charges 52,248.89
Oct 15, 2022 IBRD-48050 Loan Repay 4,117,019.00
Apr 15, 2022 IBRD-48050 Int Charges 28,172.18
Apr 15, 2022 IBRD-48050 Loan Repay 4,077,855.80
Oct 15, 2014 IBRD-48050 Loan Repay 4,077,855.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Satisfactory 2011-06-27
Progress towards achievement of PDO Satisfactory 2011-06-27
Procurement Satisfactory 2011-06-27
Project Management Satisfactory 2011-06-27
Financial Management Satisfactory 2011-06-27
Counterpart Funding Satisfactory 2011-06-27
Monitoring and Evaluation Satisfactory 2011-06-27
Overall Implementation Progress (IP) Satisfactory 2011-06-27
Overall Safeguards Rating Satisfactory 2011-06-27

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-31-2012
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-04-2013PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • PDO: Increased volume of electricity transfer from northern Kazakhstan to markets in southern Kazakhstan to reduce power deficit and improve quality of electricity supply.Value650 MW (3.9 TWh) electricity transfer from norther1,350 MW (7.5 TWh) electricity transfer through No1,350 MW (7.5 TWh) electricity transfer through No
    DateDecember 31, 2005May 18, 2011December 31, 2009
    Comment
  • PDO: Promote competition in the electricity market.ValueTransmission tariffs inadequately supportive of coEfficient transmission tariff methodology has beenZonal tranmsission tariffs implemented and later (
    DateDecember 31, 2005May 18, 2011November 30, 2011
    Comment
  • PDO: Promote competition in electricity market.ValueNo functioning real time balancing market (BM).BM is operated in trial mode.Establishment of BM.
    DateDecember 31, 2005May 18, 2011November 30, 2011
    CommentThe BM has been undergoing comprehensive performance testing and fine-tuning based on market participant feedback. Under GOKorder,the BM will start live operation on Jan. 1, 2012.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduction in the frequency of emergency outages on the North/Sourh interconnector.Value1348
    DateDecember 31, 2005May 18, 2011November 30, 2011
    CommentNumber of "first grade" technological failures.Number of "first grade" technological failures.
  • Reduction in trasmission losses on North-South interconector.Value8.8%5.3%6.5%
    DateDecember 31, 2005May 18, 2011November 30, 2011
    CommentKEGOC transmission system as a whole.KEGOC transmission system as a whole.
  • Susbstations completedValue0.0067.0067.00
    DateDecember 31, 2009May 18, 2011December 31, 2010
    CommentSubstations to be completed.All 67 substations fully completed and commissioned ("red phase') by end-2010.All substations completed/commissioned.