Skip to Main Navigation

MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT

Development Objective

To improve social and economic recovery in targeted conflict-affected communities of Mindanao through activities which promote confidence-building, peace and demand-driven governance.

Key Details

Project Details

  • P095173

  • Closed

  • Matthew Stephens

  • Community and Family Services International,Mindanao Land Foundation,International Labour Organization

  • Philippines

  • July 20, 2005

  • (as of board presentation)

    July 20, 2005

  • March 30, 2006

  • US$ 8.26 million

  • Bangsamoro Development Agency,Office of the Presidential Adviser on the Peace Process

  • East Asia And Pacific

  • 2006

  • US$ 8.26 million

  • B

  • March 7, 2024

  • March 31, 2017

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Philippines - Multi-donor Trust Fund Program for Mindanao 8.26

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.26
Total Project Cost** 8.26

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2017-03-31
Overall Safeguards Rating Moderately Satisfactory 2017-03-31
Progress towards achievement of PDO Moderately Satisfactory 2017-03-31
Financial Management Moderately Satisfactory 2017-03-31
Monitoring and Evaluation Moderately Satisfactory 2017-03-31
Project Management Moderately Satisfactory 2017-03-31
Overall Implementation Progress (IP) Moderately Satisfactory 2017-03-31
Overall Safeguards Rating Moderately Satisfactory 2017-03-31

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-29-2018
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-28-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increase in number of community members confident that the BDA/MILF and the government of the Philippines can work together for thebenefit of the communityValue0.000.0057.00
    DateJuly 1, 2012March 31, 2017March 31, 2017
    Comment
  • The economic internal rate of return for community sub-projects will be at or beyond 12%.Value0.000.0012.90
    DateApril 3, 2006March 31, 2017March 31, 2017
    Comment
  • Direct project beneficiariesValue0.000.00638000.00
    DateJanuary 1, 2006March 27, 2018March 31, 2017
    Comment
  • Female beneficiariesValue0.000.00330738.00
    DateJanuary 1, 2006March 27, 2018March 31, 2017
    Comment
  • Communities report better access to basic services (time, distance and cost)Value0.0051.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Percentage of beneficiaries who receive entrepreneurship training and support who establish a new enterpriseValue0.0091.00
    DateDecember 11, 2012December 31, 2016
    Comment
  • Increase in number of community members reporting trust in other members/groups within their communityValue0.0016.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Increase in number of community members who think their opinion counts in what needs to be done in their communityValue0.000.0016.00
    DateJuly 1, 2012March 31, 2017March 31, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Communities with improved local infrastructure facilities and/or livelihood activities implemented by the projectValue0.000.00332.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Beneficiaries that feel project investments reflected their needs (percentage)Value0.000.0086.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Communities with sub-project investments that match one of top three identified prioritiesValue0.000.00100.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of people's organization members who are womenValue0.000.0045.74
    DateOctober 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of people's organizations with female officersValue0.000.0092.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Community members who reported participation in a collective effort and also reported improved well beingValue0.000.0038.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of project-facilitated meetings conducted without incidents of conflictValue0.000.00621.00
    DateOctober 1, 2006March 31, 2017March 31, 2017
    Comment
  • Local communities, poeple's organizations and local government units perceive BDA to be a credible development partnerValue0.000.0067.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of BDA and Sajahatra Bangsamoro Project Management Team staff participating in capacity-building sessionsValue0.000.00378.00
    DateJanuary 1, 2007March 31, 2017March 31, 2017
    Comment
  • Program partnerships forged by BDA with other organizationsValue0.000.0017.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Percentage of sub-projects with adequate workmanshipValue0.000.0082.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Regular monthly and quarterly reports delivered on time by BDAValue0.000.005.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Grievances registered related to delivery of project benefits addressed (%)Value0.000.0095.20
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Training sessions provided to people's organizationsValue0.000.002444.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of PO members trained in training sessionsValue0.000.005717.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Community members perceiving people's organizations as a functional organizationValue0.000.0084.70
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Bangsamoro Development Plan delivered with at least five community consultationsValue0.000.001.00
    DateNovember 14, 2013March 31, 2017March 31, 2017
    Comment
  • Number of people receiving entrepreneurship training and supportValue0.000.001178.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Increase in income for those who start a new enterpriseValue0.000.0025.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Number of people who receive employment skills trainingValue0.000.000.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Percentage of those who receive employment skills training who secure wage employmentValue0.000.000.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Increase in income for those who secure wage employmentValue0.000.000.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Number of common facilities constructed and being used by the communityValue0.000.008.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Total beneficiaries - female (number)Value0.00330738.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Total beneficiaries - male (number)Value0.00307622.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Beneficiaries experiencing greater security in project areas – female (number)Value0.0049610.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Beneficiaries experiencing greater security in project areas – male (number)Value0.0046089.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Beneficiaries that feel project inv. reflected their needs - female (number)Value0.000.00284435.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Total beneficiaries - female (number)Value0.000.00330738.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Total beneficiaries - male (number)Value0.000.00307262.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Beneficiaries that feel project inv. reflected their needs - male (number)Value0.000.00264245.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Grievances related to delivery of project benefits that are addressed (number)Value0.000.0021.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Beneficiaries experiencing greater security in project areas (%)Value0.0015.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Increase in number of community members reporting communications with members of a different group (ethnic, religious or different sub-village)Value0.000.0015.00
    DateJuly 1, 2012March 31, 2017March 31, 2017
    Comment
  • Community-wide meetings achieve at least 60% participation of householdsValue0.000.000.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of community-wide meetings in which at least 50% of participants are womenValue0.000.009.62
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment