Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 300.75 |
P095510
Closed
Adriana Goncalves Moreira
N/A
December 5, 2007
(as of board presentation)
October 2, 2008
December 16, 2008
US$ 300.75 million
N/A
2009
US$ 300.75 million
N/A
Not Applicable
December 31, 2009
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 300.75 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 300.75 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 300.75 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 300.75 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 15, 2020 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2016 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2020 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2020 | IBRD-76390 | Int Charges | 8,360,912.50 |
May 15, 2021 | IBRD-76010 | Int Charges | 5,518,797.00 |
May 15, 2021 | IBRD-76390 | Int Charges | 8,360,912.50 |
May 15, 2022 | IBRD-76010 | Int Charges | 5,518,797.00 |
May 15, 2022 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2021 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2021 | IBRD-76010 | Int Charges | 5,518,797.00 |
Dec 18, 2008 | IBRD-76390 | Loan Commitment | 401,003,008.00 |
Oct 2, 2008 | IBRD-76010 | Loan Commitment | 300,751,872.00 |
May 15, 2024 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2023 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2023 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2023 | IBRD-76010 | Loan Repay | 300,751,872.00 |
May 15, 2023 | IBRD-76010 | Int Charges | 5,518,797.00 |
May 15, 2023 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2022 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2022 | IBRD-76010 | Int Charges | 5,518,797.00 |
May 15, 2016 | IBRD-76390 | Int Charges | 8,360,912.50 |
May 15, 2016 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2017 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2017 | IBRD-76390 | Int Charges | 8,360,912.50 |
May 15, 2017 | IBRD-76010 | Int Charges | 5,518,797.00 |
May 15, 2017 | IBRD-76390 | Int Charges | 8,360,912.50 |
May 15, 2018 | IBRD-76390 | Int Charges | 8,360,912.50 |
May 15, 2018 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2019 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2019 | IBRD-76010 | Int Charges | 5,518,797.00 |
May 15, 2019 | IBRD-76390 | Int Charges | 8,360,912.50 |
May 15, 2019 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2018 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2018 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2014 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2014 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2013 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2013 | IBRD-76390 | Int Charges | 8,360,912.50 |
May 15, 2014 | IBRD-76010 | Int Charges | 5,518,797.00 |
May 15, 2014 | IBRD-76390 | Int Charges | 8,360,912.50 |
Nov 15, 2015 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2015 | IBRD-76390 | Int Charges | 8,360,912.50 |
May 15, 2015 | IBRD-76390 | Int Charges | 8,360,912.50 |
May 15, 2015 | IBRD-76010 | Int Charges | 5,518,797.00 |
Nov 15, 2016 | IBRD-76010 | Int Charges | 5,518,797.00 |
May 15, 2020 | IBRD-76390 | Int Charges | 8,360,912.50 |
Name | Review | Date |
---|---|---|
Program Management | Satisfactory | 2008-11-05 |
Progress towards achievement of PDO | Satisfactory | 2008-11-05 |
Monitoring and Evaluation | Satisfactory | 2008-11-05 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2010 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 10-03-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |