Financier | Commitments |
---|---|
IDA Grant | 16.00 |
P095523
Closed
Pierre Bonneau
N/A
Haiti
February 22, 2006
(as of board presentation)
April 11, 2006
December 13, 2006
US$ 16.00 million
N/A
2006
US$ 16.00 million
B
Not Applicable
July 30, 2013
BANK APPROVED
March 11, 2021
Financier | Commitments |
---|---|
IDA Grant | 16.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 16.00 |
IBRD + IDA Commitment | 16.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 16.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 11, 2006 | IDA-H2130 | Loan Commitment | 16,000,000.00 |
Dec 6, 2013 | IDA-H5260 | Loan Disb | -3,695.13 |
Dec 18, 2013 | IDA-H5260 | Loan Disb | 6,439.38 |
Aug 8, 2013 | IDA-H5260 | Loan Disb | 46,004.00 |
Aug 16, 2013 | IDA-H5260 | Loan Disb | 74,524.70 |
Aug 12, 2013 | IDA-H5260 | Loan Disb | 74,879.00 |
Aug 30, 2013 | IDA-H5260 | Loan Disb | 66,756.49 |
Sep 5, 2013 | IDA-H5260 | Loan Disb | 177,103.19 |
Sep 5, 2013 | IDA-H5260 | Loan Disb | 376,912.12 |
Jul 25, 2013 | IDA-H5260 | Loan Disb | 164,932.64 |
Oct 31, 2013 | IDA-H2130 | Loan Disb | -113,760.77 |
Aug 19, 2013 | IDA-H5260 | Loan Disb | 99,606.01 |
Aug 19, 2013 | IDA-H5260 | Loan Disb | 57,048.34 |
Aug 30, 2013 | IDA-H5260 | Loan Disb | 376,912.12 |
Jul 30, 2013 | IDA-H2130 | Loan Disb | 47,198.25 |
Jul 30, 2013 | IDA-H5260 | Loan Disb | 320,787.22 |
Jul 30, 2013 | IDA-H5260 | Loan Disb | 288,657.75 |
Jul 30, 2013 | IDA-H5260 | Loan Disb | 54,291.74 |
Jan 15, 2014 | IDA-H5260 | Loan Cancel | 77,750.26 |
Dec 11, 2013 | IDA-H5260 | Loan Disb | 24,500.00 |
Dec 6, 2013 | IDA-H2130 | Loan Disb | -4,743.81 |
Nov 13, 2013 | IDA-H5260 | Loan Disb | 660,635.44 |
Nov 13, 2013 | IDA-H2130 | Loan Disb | -660,635.44 |
Jan 6, 2014 | IDA-H2130 | Loan Cancel | 820,337.70 |
Dec 27, 2013 | IDA-H5260 | Loan Disb | 1,250.00 |
Dec 19, 2013 | IDA-H5260 | Loan Disb | 13,625.00 |
Dec 30, 2013 | IDA-H5260 | Loan Disb | 10,776.64 |
Oct 25, 2013 | IDA-H5260 | Loan Disb | 114,056.01 |
Oct 25, 2013 | IDA-H5260 | Loan Disb | 320,847.75 |
Oct 18, 2013 | IDA-H5260 | Loan Disb | 18,673.51 |
Oct 18, 2013 | IDA-H5260 | Loan Disb | 24,441.88 |
Oct 3, 2013 | IDA-H5260 | Loan Disb | 81,803.94 |
Dec 16, 2013 | IDA-H5260 | Loan Disb | 3,354.62 |
Dec 8, 2009 | IDA-H5260 | Loan Commitment | 12,000,000.00 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Unsatisfactory | 2013-09-04 |
Procurement | Satisfactory | 2013-09-04 |
Overall Safeguards Rating | Satisfactory | 2013-09-04 |
Progress towards achievement of PDO | Moderately Satisfactory | 2013-09-04 |
Monitoring and Evaluation | Moderately Satisfactory | 2013-09-04 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2013-09-04 |
Counterpart Funding | Satisfactory | 2013-09-04 |
Project Management | Moderately Satisfactory | 2013-09-04 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-02-2014 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 12-30-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Unsatisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Decrease transport cost | Value | 0 | Not available | -25% |
Date | June 1, 2006 | August 15, 2011 | June 1, 2012 | |
Comment | Road rehabilitation works are still on-going on one of the two main corridors (RD41). Results with regards to this indicator willonly be measured once they are both completed. | Data collection related to this indicator is to be performed by a specialized consulting firm. |
Decrease travel time | Value | 0 | rd 41 -82%rn3 tbd | -30% |
Date | June 1, 2006 | June 30, 2013 | July 30, 2013 | |
Comment | Road rehabilitation works are still on-going on one of the two main corridors (RD41). Results with regards to this indicator willonly be measured once they are both completed. | Data collection related to this indicator is to be performed by a specialized consulting firm. |
Days per year during which roads are impracticable | Value | >20 (est.) | <5 | <5 |
Date | June 1, 2006 | June 30, 2013 | June 1, 2013 | |
Comment | Some critical parts of RN3 and RD41 in terms of trafficability have already been addressed in the on-going works. | Data collection related to this indicator is to be performed by a specialized consulting firm. |
Lower transit losses | Value | 0 | Not available | -30% |
Date | June 1, 2006 | April 20, 2012 | June 1, 2013 | |
Comment | Road rehabilitation works are completed on one of the two main corridors. Results with regards to this indicator will only bemeasured once they are both completed. | Data collection related to this indicator is to be performed by a specialized consulting firm. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
km of roads improved up to acceptable standards | Value | 0 | 80 | 80 |
Date | June 1, 2006 | June 30, 2012 | June 1, 2012 | |
Comment | 8.5 km of road works are completed (RN3) and 40 are nearing completion. The remainder is under a bidding process carried out by EU. |
km of roads receiving adequate levels of maintenance | Value | 0 | 0 | 80 |
Date | June 1, 2006 | June 30, 2013 | June 1, 2012 | |
Comment | Roads first both need to be rehabilitated. |
workdays generated by road maintenance activities | Value | 0 | Not available | 832,000 |
Date | June 1, 2006 | January 31, 2011 | June 1, 2012 | |
Comment | Roads first need to be both rehabilitated. Due to the earthquake, FER has practically not had any activity in 2010 or in 2011. |
increased traffic | Value | 0 | Not available | +20% |
Date | June 1, 2006 | April 1, 2010 | June 1, 2012 | |
Comment | Data collection related to this indicator is to be performed by a specialized consulting firm, once both road works are completed. | Data collection related to this indicator is to be performed by a specialized consulting firm. |
cumulated amount of acceptable productive investment proposals prioritized, assessed and presented to financiers | Value | 0 | 1,450,000 USD | 5,000,000 USD |
Date | June 1, 2006 | January 31, 2011 | June 1, 2012 | |
Comment | More projects should have been presented to potential financiers during a workshop, which was canceled due to the earthquake. Theworkshop has not yet been rescheduled. |
cumulated amount of basic infrastructure proposals financed | Value | 0 | 2300000 | 2,500,000 |
Date | June 1, 2006 | April 20, 2012 | June 1, 2012 | |
Comment | North: 15 sub-projectsSouth-East: 13 sub-projectsworks completed |
Roads rehabilitated, Rural | Value | 0.00 | 80.00 | 80.00 |
Date | December 1, 2005 | June 30, 2013 | June 30, 2013 | |
Comment | 8.5 km of road works are completed (RN3) and 40 are completed on RD41. The remainder is under a bidding process carried out by EU. |
No. spot interventions on transport infrastructure affected by natural disasters | Value | 0.00 | 22.00 | 20.00 |
Date | December 22, 2008 | January 31, 3011 | June 30, 2013 | |
Comment | This has been revised from an original value of 12 after the addition of Component 4 through the restructuring and additionalfinancing. |