Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 50.00 |
Borrower/Recipient | 50.00 |
Inter-American Development Bank | 50.00 |
P095570
Closed
Maria Margarita Nunez
N/A
June 6, 2006
(as of board presentation)
December 19, 2006
July 12, 2007
US$ 150.00 million
N/A
2007
US$ 100.00 million
B
Not Applicable
December 31, 2013
BANK APPROVED
March 11, 2021
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 50.00 |
Borrower/Recipient | 50.00 |
Inter-American Development Bank | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 50.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | 50.00 |
Total Project Cost** | 150.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 5, 2013 | IBRD-74230 | Loan Disb | 1,000,000.00 |
Aug 15, 2013 | IBRD-74230 | Int Charges | 1,239.73 |
Aug 15, 2013 | IBRD-74230 | Int Charges | 174,916.40 |
May 6, 2014 | IBRD-74230 | Loan Disb | -53,970.62 |
Feb 15, 2014 | IBRD-74230 | Int Charges | 143.84 |
Feb 15, 2014 | IBRD-74230 | Int Charges | 165,731.94 |
Aug 15, 2014 | IBRD-74230 | Int Charges | 8.88 |
Aug 15, 2014 | IBRD-74230 | Int Charges | 145,717.73 |
Feb 15, 2015 | IBRD-74230 | Int Charges | 28.47 |
Feb 15, 2015 | IBRD-74230 | Int Charges | 148,033.77 |
May 30, 2014 | IBRD-74230 | Loan Cancel | 53,970.62 |
Aug 15, 2015 | IBRD-74230 | Int Charges | 158,204.06 |
Feb 15, 2016 | IBRD-74230 | Int Charges | 196,565.36 |
Aug 15, 2017 | IBRD-74230 | Loan Repay | 16,647,012.00 |
Aug 15, 2017 | IBRD-74230 | Int Charges | 266,197.90 |
Feb 15, 2017 | IBRD-74230 | Loan Repay | 16,647,012.00 |
Feb 15, 2017 | IBRD-74230 | Int Charges | 370,155.56 |
Aug 15, 2016 | IBRD-74230 | Int Charges | 280,280.47 |
Feb 15, 2018 | IBRD-74230 | Int Charges | 145,538.55 |
Feb 15, 2018 | IBRD-74230 | Loan Repay | 16,652,006.00 |
Dec 19, 2006 | IBRD-74230 | Loan Commitment | 50,000,000.00 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2014-01-18 |
Procurement | Satisfactory | 2014-01-18 |
Counterpart Funding | Satisfactory | 2014-01-18 |
Progress towards achievement of PDO | Highly Satisfactory | 2014-01-18 |
Project Management | Satisfactory | 2014-01-18 |
Financial Management | Satisfactory | 2014-01-18 |
Monitoring and Evaluation | Satisfactory | 2014-01-18 |
Overall Implementation Progress (IP) | Highly Satisfactory | 2014-01-18 |
Overall Safeguards Rating | Satisfactory | 2014-01-18 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-26-2014 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 04-27-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: 06-21-2019 |
---|---|---|
Outcome Rating | Satisfactory | Satisfactory |
Risk To Development Outcome | Significant | Substantial |
Bank Performance | Moderately Satisfactory | Satisfactory |
Borrower Performance | Satisfactory | Satisfactory |
Government Performance | Satisfactory | Not Rated |
Implementing Agency | Satisfactory | Satisfactory |
Icr Quality | Satisfactory | Not Rated |
M&e Quality | Substantial | Substantial |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Project beneficiaries | Value | 0 | 3.5 million people | |
Date | November 15, 2006 | November 30, 2013 | December 31, 2013 | |
Comment | This will be an output of the impact evaluation study, available in February 2014, and incorporated in the ICR. |
Transport cost | Value | 0.00 | 0.00 | -5.00 |
Date | November 15, 2006 | November 30, 2013 | December 31, 2013 | |
Comment | This will be an output of the impact evaluation study, available in February 2014, and incorporated in the ICR. |
Health consultations | Value | 0.00 | 0.00 | 10.00 |
Date | November 15, 2006 | November 30, 2013 | December 31, 2013 | |
Comment | This will be an output of the impact evaluation study, available in February 2014, and incorporated in the ICR. |
Children registered in school | Value | 0.00 | 0.00 | 5.00 |
Date | November 15, 2006 | November 30, 2013 | December 31, 2013 | |
Comment | This will be an output of the impact evaluation study, available in February 2014, and incorporated in the ICR. |
Travel time | Value | 0.00 | 0.00 | -20.00 |
Date | November 15, 2006 | November 30, 2013 | December 31, 2013 | |
Comment | This will be an output of the impact evaluation study, available in February 2014, and incorporated in the ICR. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Rural roads periodically maintained at project standards | Value | 0 | 7647 km | 7506 km |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | The end target was successfully achieved and exceeded before closing date. |
Non-motorized tracks rehabilitated by the program | Value | 0 | 2332 km | 2515 km |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | 93% of target has been achieved |
Bridges rehabilitated and maintained by the program | Value | 0 | 1 | 1 |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | One bridge has been rehabilitated (in Ancash). |
Resources dedicated by Provincial and District municipalities to rural transport activities | Value | 0 | US$ 250 million | US$ 75 million |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | Starting in 2007, the central Government has assigned US$ 140 million for periodic and routine maintenance. In 2011, it assignedanadditional US$ 109 million for the same activities. |
Selected PRIs/PIIs fully operational | Value | 36 | 193 | 150 |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | The end target was successfully achieved and exceeded, 193 PRIs are fully operational. |
Selected Participatory Provincial Road plans approved | Value | 0 | 194 | 194 |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | The target was successfully achieved and exceeded (one Province did not continue with the project even after the plan was alreadycreated). |
Qualified micro-enterprises delivering quality maintenance | Value | 0 | 325 | 134 |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | 325 new micro-enterprises were created and implemented. Therefore, the total number of micro-enterprises that are currentlyoperating is 857. |
One-year equivalent permanent unskilled jobs generated by micro-enterprises | Value | 0 | 3250 | 1560 |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | The target was successfully achieved and exceeded. Employment has been generated for 1,610 women and 4,140 men. |
Productive activities financed and implemented through the LDW / Number of activities identified and assessed | Value | 0/0 | 46/210 | 50/200 |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | 46 small business private initiatives were implemented and 52 business plans were financed through 210 identified and assessed. |
Rural infrastructure plans prepared and approved | Value | 0 | 15 | 15 |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | The end target was successfully achieved before closing date. |
Selected Provincial Infrastructure Institutes fully operational | Value | 0 | 0 | 15 |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | Instead of putting in place the PIIs, the Borrower prioritized the creation and expansion of PRIs, reaching 193, which exceededtheoriginal target of 150 (see indicator 10) |
Selected provinces where rural infrastructure investments prioritized by rural infrastructure plans have been implemented | Value | 0 | 0 | 15 |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | This target was not directly achieved. The Government decided to implement the RIP through MIDIS/FONIE. |
Rural Roads Rehabilitated | Value | 0.00 | 3272.00 | 3358.00 |
Date | January 1, 2007 | November 30, 2013 | December 31, 2013 | |
Comment | 97% of target has been achieved |