Financier | Commitments |
---|---|
IDA Grant | 2.50 |
Borrower/Recipient | 0.15 |
NORWAY: Norwegian Agency for Dev. Coop. (NORAD) | 0.15 |
P095593
Closed
Joel Maweni
N/A
January 12, 2006
(as of board presentation)
June 28, 2007
August 13, 2007
US$ 2.80 million
N/A
2007
US$ 2.65 million
B
Not Applicable
June 30, 2012
BANK APPROVED
March 13, 2013
Financier | Commitments |
---|---|
IDA Grant | 2.50 |
Borrower/Recipient | 0.15 |
NORWAY: Norwegian Agency for Dev. Coop. (NORAD) | 0.15 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 2.50 |
IBRD + IDA Commitment | 2.50 |
Lending Instrument | |
---|---|
Grant Amount | 0.15 |
Total Project Cost** | 2.80 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 28, 2007 | IDA-H3170 | Loan Commitment | 2,500,000.00 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2012-06-26 |
Overall Safeguards Rating | Satisfactory | 2012-06-26 |
Progress towards achievement of PDO | Moderately Satisfactory | 2012-06-26 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2012-06-26 |
Counterpart Funding | Satisfactory | 2012-06-26 |
Financial Management | Unsatisfactory | 2012-06-26 |
Monitoring and Evaluation | Unsatisfactory | 2012-06-26 |
Project Management | Satisfactory | 2012-06-26 |
Overall Safeguards Rating | Satisfactory | 2012-06-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-28-2013 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | High |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Moderately Unsatisfactory |
Government Performance | Moderately Unsatisfactory |
Implementing Agency | Moderately Unsatisfactory |
INDICATOR | ICR REVIEW: 03-24-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
System losses | Value | 55.9% | 40% | 35.0% |
Date | December 30, 2006 | April 27, 2012 | June 30, 2012 | |
Comment | April 2012 data | Targeted loss reduction by the end of the project revised from 25% to 35% during the project restructuring restructuring. |
Power supply reliability | Value | # Power generation 99.5% # Power dist | N.A. | Generation: 99.5% Distribution: 99.5% |
Date | December 30, 2006 | April 27, 2012 | June 30, 2012 | |
Comment | No recent statistics available. | Generation indicator was dropped under the project restructuring. |
Power supply safety | Value | (i) Number of major accidents per year - Not known | N.A. | (i) 0.5 major (ii) 2 minor |
Date | June 4, 2008 | April 27, 2012 | June 30, 2012 | |
Comment | No recent statistics available. |
Power supply capacity increase (as a result of repair of Comoro Power Station): Cumulative | Value | 0 | N.A. | 500kW |
Date | December 30, 2006 | April 27, 2012 | June 30, 2012 | |
Comment | No recent information available | This indicator was dropped under the project restructuring. |
HR plan for MNRMEP prepared and implemented satisfactorily | Value | HR plan (including HR needs) not yet developed | N.A. | Relevant newly recruited staff participate in revi |
Date | June 4, 2008 | April 27, 2012 | June 30, 2012 | |
Comment | No HR plan has been developed yet. | This indicator was dropped under the project restructuring. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of additional transformers installed | Value | 0 | N.A. | 30 |
Date | June 4, 2008 | April 27, 2012 | December 31, 2011 | |
Comment | Installation of transformers in progress | Target change from 13 to 30 under the project restructuring. |
Km of additional LV lines on which conductor size upgraded | Value | 0 | N.A. | 25 |
Date | June 4, 2008 | April 27, 2012 | June 30, 2012 | |
Comment | No statistics available. |
Km of existing LV lines on which conductor size upgraded | Value | 0 | N.A. | 8 |
Date | June 4, 2008 | April 27, 2012 | June 30, 2012 | |
Comment | No statistics available. | Target was reduced from 20 to 8 under the project restructuring. |
No of customers on which revenue meters installed in accordance with theft resistance standard | Value | 0 | N.A. | 4000 |
Date | June 4, 2008 | April 27, 2012 | June 30, 2012 | |
Comment | Target value was increased from 4000 to 16,400 under the project restructuring. |
Annual energy savings (MWh) implied by the number of CFLs distributed to customers | Value | 0 | N.A. | 1630 |
Date | June 4, 2008 | April 27, 2012 | June 30, 2012 | |
Comment | distribution of CFLs cancelled | Indicator was dropped under the project restructuring. |
No. of new customers | Value | 0 | N.A. | 1200 |
Date | June 4, 2008 | April 27, 2012 | June 30, 2012 | |
Comment | This target was increased from 1200 to 7,100 under the project restructuring |