Skip to Main Navigation

Second Water Sector Investment

Abstract*

The objectives of the Second Water Sector Investment Project are to promote more efficient management and operation of selected public irrigation schemes by participating farmers; to improve access and consumption of drinking water for rural households in communities; and to assist Ministry of Agriculture and Water Resources, Ministry of Environment and Sustainable Development, and other stakeholders to make better decisions relating to integrated...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project has three development objectives: (i) to promote more efficient management and operation of selected public irrigation schemes by participating farmers; (ii) to improve access and consumption of drinking water for rural households in communities un-served or poorly serviced at the beginning of the Project; and (iii) to assist MARH, MEDD and other stakeholders to make better decisions relating to integrated water resources management.

Key Details

Project Details

  • P095847

  • Closed

  • Gabriella Izzi

  • Ministry of Development, Investments and International Cooperation

  • Tunisia

  • July 15, 2008

  • (as of board presentation)

    May 19, 2009

  • November 10, 2009

  • US$ 162.95 million

  • Institute of Agricultural Research and Further Education (IRESA),Ministry of Environment and Sustainable Development (MEDD),National Environment Protection Agency (ANPE),Office National de l Assainissement (ONAS),Ministry of Agriculture and Water Resources (MARH)

  • Middle East and North Africa

  • 2009

  • US$ 130.07 million

  • B

  • November 14, 2022

  • March 31, 2015

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
African Development Bank 30.60
International Bank for Reconstruction and Development 30.60
Bilateral Agencies (unidentified) 7.67
Borrower/Recipient 32.88
FRANCE: French Agency for Development 61.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 30.60
IDA Commitment N/A
IBRD + IDA Commitment 30.60
Lending Instrument
Grant Amount 99.47
Total Project Cost** 162.95

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 31, 2015 IBRD-77260 Loan Disb -2,663,238.00
Jul 15, 2015 IBRD-77260 Int Charges 24,438.35
Jul 15, 2015 IBRD-77260 Loan Repay 373,897.30
Jan 15, 2015 IBRD-77260 Int Charges 37,186.98
Jul 15, 2014 IBRD-77260 Int Charges 364.55
Jul 15, 2014 IBRD-77260 Int Charges 44,088.05
Jul 29, 2014 IBRD-77260 Loan Disb 2,656,646.80
Jan 15, 2014 IBRD-77260 Int Charges 32,010.46
Nov 27, 2013 IBRD-77260 Loan Disb 836,572.00
Jul 15, 2016 IBRD-77260 Int Charges 0.01
Jul 15, 2016 IBRD-77260 Int Charges 8,570.34
Jul 15, 2016 IBRD-77260 Loan Repay 403,434.60
Jan 15, 2017 IBRD-77260 Int Charges 1,466.49
Jan 15, 2017 IBRD-77260 Loan Repay 308,518.60
Jan 15, 2016 IBRD-77260 Int Charges 0.01
Jan 15, 2016 IBRD-77260 Int Charges 16,863.02
Jan 15, 2016 IBRD-77260 Loan Repay 394,921.78
Aug 24, 2015 IBRD-77260 Loan Cancel 9,607,594.00
Jul 15, 2019 IBRD-77260 Loan Repay 653,667.60
Jan 15, 2019 IBRD-77260 Loan Repay 662,622.40
Jul 15, 2018 IBRD-77260 Loan Repay 673,750.56
Jan 15, 2018 IBRD-77260 Loan Repay 532,720.56
Jul 15, 2017 IBRD-77260 Loan Repay 0.01
Jul 15, 2021 IBRD-77260 Loan Repay 342,482.88
Jan 15, 2021 IBRD-77260 Loan Repay 351,350.70
May 19, 2009 IBRD-77260 Loan Commitment 30,600,000.00
Jul 15, 2024 IBRD-77260 Int Charges 101,622.14
Jul 15, 2024 IBRD-77260 Int Charges 100,257.20
Jul 15, 2024 IBRD-77260 Loan Repay 632,338.50
Jan 15, 2024 IBRD-77260 Int Charges 110,076.66
Jan 15, 2024 IBRD-77260 Int Charges 106,260.85
Jan 15, 2024 IBRD-77260 Loan Repay 634,396.06
Jul 15, 2023 IBRD-77260 Int Charges 54,735.69
Jul 15, 2023 IBRD-77260 Int Charges 117,016.10
Jul 15, 2023 IBRD-77260 Loan Repay 650,305.94
Jan 15, 2023 IBRD-77260 Int Charges 35,816.67
Jan 15, 2023 IBRD-77260 Loan Repay 469,993.88
Jan 15, 2022 IBRD-77260 Loan Repay 165,945.40
Jul 15, 2013 IBRD-77260 Int Charges 26,751.30

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2015-03-25
Monitoring and Evaluation Unsatisfactory 2015-03-25
Counterpart Funding Moderately Satisfactory 2015-03-25
Project Management Moderately Unsatisfactory 2015-03-25
Overall Implementation Progress (IP) Moderately Satisfactory 2015-03-25
Overall Safeguards Rating Moderately Unsatisfactory 2015-03-25
Progress towards achievement of PDO Moderately Unsatisfactory 2015-03-25
Financial Management Moderately Satisfactory 2015-03-25

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-30-2015
OutcomesModerately Unsatisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceUnsatisfactory
Borrower PerformanceUnsatisfactory
Government PerformanceUnsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-14-2016PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingUnsatisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualityHighN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • (i.a) Irrigation intensity in participating farms (# irrigated ha cultivated/# irrigable ha)Value0.8n.a.1.2
    DateSeptember 15, 2009March 1, 2015April 30, 2015
    Comment
  • (i.b) Share of participating GDAs in irrigation that are fully functional (as defined by the Ministry of Agriculture)Value50%n.a.80%
    DateSeptember 15, 2009March 1, 2015March 15, 2015
    Comment
  • ii.a) Average annual household water consumption of beneficiary householdsValuebaseline study not yet commissionedn.a.increase relative to baseline
    DateJune 20, 2009March 1, 2015March 31, 2015
    Comment
  • (ii.b) Share of participating GDAs in water supply that are fully functional (as defined by Ministry of Agriculture)Valuebaseline study being commissionedn.a.n.a.
    DateJune 20, 2009March 1, 2015March 31, 2015
    Comment
  • (iii.a) Integrated information system (SINEAU and its sub-systems) fully operational by 2013ValueWater quality sub-system functional. Groundwater pThe system is partially functional (56%)system installed
    DateSeptember 15, 2009March 1, 2015March 31, 2105
    Comment
  • iii.b) Study "Water 2050" published by 2013Valuefirst draft terms of reference preparednoyes
    DateJune 20, 2009March 1, 2015March 31, 2013
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Hectares where irrigation and drainage schemes created or rehabilitatedValue01,260 ha new irrigation schemes,16,555 ha rehabil2,300 ha new irrigation schemes;25,000 ha rehabil
    DateJune 20, 2009March 1, 2015April 30, 2015
    Comment
  • Rural drinking water systems improvedValue0New systems: 6,000 householdsRehabilitated: 6,70010,000 households with new service; 8 schemes impr
    DateJune 20, 2009March 1, 2015March 31, 2013
    Comment
  • share of project irrigation schemes run by GDAsValue90%n.a.100%
    DateJune 20, 2009March 1, 2015March 31, 2015
    Comment
  • # wells created by projectValue088 exploratorywells19 piezometers176 exploratory wells100 piezometers
    DateJune 20, 2009March 1, 2015March 31, 2015
    Comment
  • # of research projects financed by project underway or completedValue044
    DateJune 20, 2009March 1, 2015March 31, 2015
    Comment