Financier | Commitments |
---|---|
IDA Grant | 11.00 |
Borrower/Recipient | 2.91 |
AUSTRALIA: Australian Agency for International Development | 8.97 |
P095873
Closed
Susiana Iskandar
N/A
March 27, 2006
(as of board presentation)
June 19, 2007
September 17, 2007
US$ 22.88 million
N/A
2007
US$ 19.97 million
C
May 31, 2022
January 31, 2013
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 11.00 |
Borrower/Recipient | 2.91 |
AUSTRALIA: Australian Agency for International Development | 8.97 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 11.00 |
IBRD + IDA Commitment | 11.00 |
Lending Instrument | |
---|---|
Grant Amount | 8.97 |
Total Project Cost** | 22.88 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 19, 2007 | IDA-H3100 | Loan Commitment | 6,000,000.00 |
Jul 12, 2013 | IDA-H3100 | Loan Disb | -14,976.71 |
Jul 18, 2013 | IDA-H3100 | Loan Cancel | 72,061.62 |
Jun 27, 2013 | IDA-H5830 | Loan Cancel | 313,229.90 |
Jun 3, 2010 | IDA-H5830 | Loan Commitment | 5,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2013-07-30 |
Monitoring and Evaluation | Moderately Satisfactory | 2013-07-30 |
Procurement | Satisfactory | 2013-07-30 |
Financial Management | Satisfactory | 2013-07-30 |
Overall | Moderately Low | 2013-07-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2013-07-30 |
Overall Safeguards Rating | Satisfactory | 2013-07-30 |
Counterpart Funding | Satisfactory | 2013-07-30 |
Project Management | Moderately Satisfactory | 2013-07-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-31-2014 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 07-31-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Primary Completion Rate | Value | 73.40 | 83.24 | 80.00 |
Date | December 31, 2009 | January 18, 2013 | December 31, 2012 | |
Comment | Figure represents 2011 PCR. 2012 figure to be updated/ being processed by EMIS unit of the MoE. |
Gender Parity Index | Value | 95.00 | 98.98 | 98.00 |
Date | December 31, 2009 | January 18, 2013 | December 31, 2012 | |
Comment | Improved data collection methods have led to apparent increases in GPI |
Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions. | Value | 0.00 | 1773.00 | 2100.00 |
Date | December 31, 2007 | December 13, 2011 | December 31, 2012 | |
Comment | Including the construction/renovation and maintenance supported by the ESSP AF II, the target could be achieved by the closingdateof AF II, 31 July, 2013. |
System for learning assessment at the primary level | Value | Yes | Yes | Yes |
Date | December 31, 2009 | December 3, 2012 | December 31, 2012 | |
Comment | Two National Exams: EB Third Cycle National Exam; and General Secondary Year 3 National Exam |
MoEC staff with improved skills to effectively contribute to sectormanagement and service delivery. | Value | |||
Date | December 12, 2011 | |||
Comment | Not undertaken. | Figure provided is initial rating of 'Category 1' (on-track or partially on-track) NESP Priority Program areas. ESSP Mid TermReview and individual activity reporting identify stronger areas of skills transfer to Ministry units. However with no baselineset in 2008, unit of measurement or average of Ministry Annual Action Plan performance this indicator has not been collected.Current preparation of the Management Strengthening Project proposes a Capacity Level framework for mentioning increasedfunctionality of units toachieve the NESP |
Enhanced quality learning materials for all primary and presecondary students and teachers | Value | |||
Date | ||||
Comment | N/A. No baseline undertaken | Further information collection is proposed in development of learning material strategy on advice from Learning Materials advisor. |
Improved work skills and attributes of pre-secondary school leavers | Value | N/A | ||
Date | ||||
Comment | No baseline collected |
Utility of the learning assessment system | Value | 2.00 | 2.00 | 4.00 |
Date | December 31, 2009 | December 3, 2012 | December 31, 2012 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Satisfaction of Ministry and Development Partners with Annual Joint Review | Value | 0.00 | 87.00 | 70.00 |
Date | December 31, 2009 | November 16, 2012 | December 31, 2012 | |
Comment | N/A: the High Level Meeting held in Fall 2009 was focused on the Strategic Plan and did not really constitute an AJR | No update – next AJR planned for Dec 2012 |
Budget Execution Rate | Value | 87.50 | 95.00 | 95.00 |
Date | December 31, 2008 | February 29, 2012 | December 31, 2012 | |
Comment |
Policy and Legal Framework in place | Value | Strategic Plan under finalization | Policy and Legal Framework in place | Policy and Legal Framework in place |
Date | December 31, 2009 | January 18, 2013 | December 31, 2012 | |
Comment | NESP launched in July 2012 and now being implemented. A number of policy frameworks/ regulations are in place. |
All primary and pre-secondary school children and teachers receiving learning materials and teaching guides and the use of those materials in learning activities | Value | Lafaek magazine distributed to all Timorese primar | Literacy and Numeracy learning materials are provi | |
Date | December 31, 2007 | January 18, 2013 | December 31, 2012 | |
Comment | Lafaek was provided in 2009 and 2010 and then discontinued by the Ministry, to be replaced by locally-produced materials. TheProject provides Early Grade learning materials (for literacy and numeracy skills) Discontinuation of Lafaek support by Ministry;Learning Material advisor to strategy for learning materials for medium-term replacements. |
In-place unit to support the procurement of learning materials and textbooks | Value | Not Yet | ongoing | Unit in place |
Date | December 31, 2008 | January 18, 2013 | December 31, 2012 | |
Comment | As the Ministry is now being restructured, the process of the LMU establishment is being discuss to ensure its fit with the neworganization structure. The step being taken now is training of three key staff. |
Decline in shortfall of school furniture at the primary level | Value | 0.00 | 0.00 | 54000.00 |
Date | December 31, 2009 | January 18, 2013 | December 31, 2012 | |
Comment | school furniture funding (additional financing) not yet in place | The Ministry has allocated sufficient budget in FY 2013 to procure adequate number of furniture for primary and junior secondarylevel. Information about the exact number/volume has not yet available. |
Execution of at least two training contracts under the grant funding mechanism for post-secondary tutors | Value | 0.00 | 4.00 | 2.00 |
Date | December 31, 2009 | December 31, 2010 | December 31, 2012 | |
Comment |
Preparation of feasibility study for polytechnics | Value | Not Yet | Completed | |
Date | December 31, 2009 | December 3, 2012 | ||
Comment |
Percentage of Grade 3 students who can read with a fluency of at least 60 words a minute | Value | 30.00 | 30.00 | 0.00 |
Date | December 31, 2009 | November 16, 2012 | ||
Comment | Updated EGRA data will not be available before the end of the project. The latest accurate measure is the 2009 EGRA study. |
Primary education survival rate | Value | 38.00 | 73.50 | 0.00 |
Date | December 31, 2009 | December 31, 2012 | ||
Comment | To confirm |
In-place school siting, construction, rehabilitation and maintenance standards | Value | All but school siting standards developed | School siting standards developed | |
Date | December 31, 2008 | December 3, 2012 | ||
Comment | Maintenance standards not yet developed |