Financier | Commitments |
---|---|
Borrower/Recipient | 2.00 |
IDA Grant | 30.00 |
P096105
Closed
Hardwick Tchale
N/A
May 30, 2006
(as of board presentation)
May 22, 2007
June 30, 2008
US$ 32.00 million
Ministry of Food and Agriculture/Ministry of Trade and Industry
2007
US$ 30.00 million
B
Not Applicable
November 14, 2015
BANK APPROVED
September 11, 2023
Financier | Commitments |
---|---|
Borrower/Recipient | 2.00 |
IDA Grant | 30.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 30.00 |
IBRD + IDA Commitment | 30.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 32.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 22, 2007 | IDA-H2900 | Loan Commitment | 30,000,000.00 |
Aug 18, 2016 | IDA-H2900 | Loan Cancel | 16,390.02 |
Oct 24, 2014 | IDA-H6970 | Loan Disb | 1,873,972.50 |
Jan 20, 2014 | IDA-H2900 | Loan Disb | -1,000,000.00 |
Jan 20, 2014 | IDA-H6970 | Loan Disb | 1,000,000.00 |
Feb 11, 2014 | IDA-H6970 | Loan Disb | 648,823.50 |
Dec 16, 2013 | IDA-H6970 | Loan Disb | 532,587.40 |
Oct 1, 2013 | IDA-H6970 | Loan Disb | 772,996.30 |
Oct 1, 2013 | IDA-H2900 | Loan Disb | 287,282.12 |
Dec 3, 2014 | IDA-H6970 | Loan Disb | 557,784.30 |
Jul 22, 2013 | IDA-H2900 | Loan Disb | 389,914.72 |
Jul 22, 2013 | IDA-H6970 | Loan Disb | 534,500.10 |
Jul 17, 2013 | IDA-H2900 | Loan Disb | 412,838.72 |
Sep 29, 2014 | IDA-H2900 | Loan Disb | -500,000.00 |
Oct 9, 2014 | IDA-H6970 | Loan Disb | 431,757.03 |
Sep 29, 2014 | IDA-H6970 | Loan Disb | 500,000.00 |
Oct 24, 2014 | IDA-H2900 | Loan Disb | 125,199.46 |
May 7, 2014 | IDA-H6970 | Loan Disb | 1,212,702.80 |
Apr 7, 2014 | IDA-H6970 | Loan Disb | 692,189.50 |
Mar 13, 2014 | IDA-H6970 | Loan Disb | 545,560.20 |
Mar 12, 2014 | IDA-H2900 | Loan Disb | 374,937.97 |
Apr 16, 2014 | IDA-H6970 | Loan Disb | 1,142,911.00 |
Mar 17, 2014 | IDA-H6970 | Loan Disb | 226,624.97 |
Nov 21, 2013 | IDA-H6970 | Loan Disb | 812,142.50 |
Jan 30, 2014 | IDA-H2900 | Loan Disb | 360,902.62 |
Jan 30, 2014 | IDA-H6970 | Loan Disb | 98,934.82 |
Jan 30, 2014 | IDA-H2900 | Loan Disb | 189,469.66 |
Jan 30, 2014 | IDA-H6970 | Loan Disb | 972,423.56 |
Apr 1, 2015 | IDA-H6970 | Loan Disb | 370,215.47 |
Jul 22, 2014 | IDA-H2900 | Loan Disb | 104,249.59 |
Sep 5, 2014 | IDA-H6970 | Loan Disb | 138,957.10 |
Jul 28, 2014 | IDA-H6970 | Loan Disb | 2,112,591.80 |
Jun 24, 2014 | IDA-H6970 | Loan Disb | 458,792.30 |
Oct 29, 2015 | IDA-H6970 | Loan Disb | 111,139.57 |
Nov 20, 2015 | IDA-H2900 | Loan Disb | 481,488.06 |
Apr 2, 2015 | IDA-H6970 | Loan Disb | 1,198,981.50 |
May 19, 2011 | IDA-H6970 | Loan Commitment | 20,000,000.00 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2015-06-16 |
Procurement | Satisfactory | 2015-06-16 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2015-06-16 |
Financial Management | Moderately Satisfactory | 2015-06-16 |
Progress towards achievement of PDO | Satisfactory | 2015-06-16 |
Counterpart Funding | Satisfactory | 2015-06-16 |
Monitoring and Evaluation | Satisfactory | 2015-06-16 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-17-2016 |
---|---|
Outcomes | |
Risk to Development Outcome | Unsatisfactory |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 12-30-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Substantial | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
50% of target beneficiaries (of which 50% must women) for the selected value chain increase their production by at least 20% by theend of the Project | Value | Cassava 10mt/haRice 0.86mt/ha | Cassava: 12.34 mt/haRice: 2.05mt/ha | Cassava 12mt/haRice .88mt/ha |
Date | May 22, 2007 | November 14, 2015 | November 14, 2015 | |
Comment |
50% of target beneficiaries for the selected value chain increase their sales by at least 10% by the end of the Project | Value | Cassava 550Le/kg; Rice 1320Le/kg; cocoa 3750Le /kg | Cassava: Le 772.44/kg;Rice: Le 2,176.35/kg; andC | Cassava 605Le/kg; Rice 1452Le/kg; cocoa 4125Le /kg |
Date | May 22, 2007 | November 14, 2015 | November 14, 2015 | |
Comment |
Number of project beneficiaries | Value | 0 | 56,000 | 50,000 |
Date | May 22, 2007 | November 14, 2015 | November 14, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Time taken to transport goods to the nearest market reduced by 20% after rehabilitation of selected feeder road | Value | Av time/km 1hr | 27 minutes/km | 10mins/km |
Date | August 5, 2009 | November 14, 2015 | November 14, 2015 | |
Comment |
Real Farm gate prices increase by at least 10% for the selected value chains of targetted beneficiaries | Value | Rice 58,500Le/50kg; Cassava Le6000/50kg; -Cocoa Le | Cassava: Le 772.44/kg;Rice: Le 2,176.35/kg; andC | 10% real increase |
Date | May 22, 2007 | November 14, 2015 | November 14, 2015 | |
Comment |
Producers confirm firm supply and contractual agreements with marketers/ processors for the selected value chains of targeted beneficiaries | Value | Cassava 550Le/kg; Rice 1320Le/kg; cocoa 3750Le /kg | 58% | At least 60% of producers have contractual agreeme |
Date | August 5, 2009 | November 14, 2015 | November 14, 2015 | |
Comment |
Producers have access to at least one new market infrastructure | Value | Not available | 220 | 13 markets infrastructure completed |
Date | May 22, 2007 | November 14, 2015 | November 14, 2015 | |
Comment |
Cultivated land under the targeted value chain increases by 10% at the end of the project period for targeted beneficiaries | Value | Cassava 0.5ha per farmer;Rice 1ha/farmer28016ha; | Cassava: 0.8ha/farmerRice: 2.3ha/farmer | 10 % real increase |
Date | May 22, 2007 | May 30, 2014 | November 14, 2015 | |
Comment |
Volume of export of selected value chain commodities increased by 10% for targeted beneficiaries | Value | -zero | 1,314.87 tons | Cocoa1500tons |
Date | June 30, 2010 | May 30, 2014 | November 14, 2015 | |
Comment |
Beneficiary FBO's are run effectively for their members | Value | Zero ( all farmers are members of national farmers | meetings once a month | 100% of beneficiary FBOs gets 80% approval rating |
Date | May 22, 2007 | May 30, 2014 | November 14, 2012 | |
Comment |
FBO's maintain records of membership dues, production levels, assets records | Value | Zero | 100% maintain records; 20% production and assets | 100% of beneficiary FBOs maintaining records |
Date | May 22, 2007 | May 30, 2014 | November 14, 2015 | |
Comment |
Improved planting materials made available to 50% of targeted beneficiaries for the selected value chains | Value | zero | 50% receive improved planting materials | 50% of FBOs received improved planting materials |
Date | May 30, 2014 | November 14, 2015 | ||
Comment |
Development of seed, fertilizer and pesticide laws and regulations | Value | N/A - project dependent | Bills still at draft stage | Laws drafted and passed by parliament |
Date | May 22, 2007 | February 28, 2013 | November 14, 2012 | |
Comment |
Harmonization of policies and regulations governing the formation and regularization of farmer based groups | Value | N/A - project dependent | NaFFSL constitution reviewed; CMMU transformed int | Policies and regulations harmonization publicized |
Date | May 22, 2007 | May 30, 2014 | November 14, 2015 | |
Comment |
Beneficiary scorecards report satisfaction with project | Value | N/A - project dependent | 80% positive response | |
Date | May 22, 2007 | May 30, 2014 | November 14, 2015 | |
Comment |
Community awareness of matching grants | Value | N/A - project dependent | 1560 | 80% of respondents are aware of the grant and 90% |
Date | May 22, 2007 | May 30, 2014 | November 14, 2015 | |
Comment |