Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
P096586
Closed
Dmytro Glazkov
Ukreximbank
October 16, 2009
(as of board presentation)
May 17, 2011
November 9, 2011
US$ 200.00 million
*UKREXIMBANK - IBRD 80640
2011
US$ 200.00 million
F
Not Applicable
March 31, 2017
BANK APPROVED
October 2, 2023
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 200.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 7, 2013 | IBRD-80640 | Loan Disb | 254,934.89 |
Oct 15, 2013 | IBRD-80640 | Int Charges | 5,243.00 |
Oct 15, 2013 | IBRD-80640 | Int Charges | 113,419.93 |
Oct 22, 2013 | IBRD-80640 | Loan Disb | 2,400,000.00 |
Oct 22, 2013 | IBRD-80640 | Loan Disb | 298,976.22 |
Aug 13, 2013 | IBRD-80640 | Loan Disb | 15,000,000.00 |
Sep 11, 2013 | IBRD-80640 | Loan Disb | 508,090.12 |
Aug 28, 2013 | IBRD-80640 | Loan Disb | 518,156.00 |
Oct 15, 2014 | IBRD-80640 | Int Charges | 305,050.06 |
Nov 17, 2014 | IBRD-80640 | Loan Disb | 6,858,655.00 |
Mar 15, 2017 | IBRD-80640 | Loan Disb | 1,221,691.50 |
Feb 28, 2017 | IBRD-80640 | Loan Disb | 969,995.60 |
Oct 15, 2017 | IBRD-80640 | Int Charges | 12,391.53 |
Oct 15, 2017 | IBRD-80640 | Int Charges | 2,084,166.60 |
Oct 15, 2017 | IBRD-80640 | Loan Repay | 2,163,441.80 |
Oct 15, 2017 | IBRD-80640 | Loan Repay | 2,096,558.20 |
Mar 3, 2017 | IBRD-80640 | Loan Disb | 3,629,328.50 |
Apr 15, 2017 | IBRD-80640 | Int Charges | 1,726,635.80 |
Apr 15, 2017 | IBRD-80640 | Int Charges | 9,993.88 |
Dec 28, 2016 | IBRD-80640 | Loan Disb | 15,000,000.00 |
Oct 31, 2016 | IBRD-80640 | Loan Disb | 1,153,788.10 |
Aug 29, 2016 | IBRD-80640 | Loan Disb | 4,806,762.00 |
Dec 19, 2016 | IBRD-80640 | Loan Disb | 877,162.60 |
Nov 28, 2016 | IBRD-80640 | Loan Disb | 2,848,440.50 |
Jan 30, 2017 | IBRD-80640 | Loan Disb | 1,950,115.40 |
Feb 6, 2017 | IBRD-80640 | Loan Disb | 3,245,523.80 |
Jun 17, 2016 | IBRD-80640 | Loan Disb | 8,503,393.00 |
May 20, 2016 | IBRD-80640 | Loan Disb | 13,915,145.00 |
Sep 26, 2016 | IBRD-80640 | Loan Disb | 991,046.80 |
Oct 15, 2016 | IBRD-80640 | Int Charges | 16,059.08 |
Oct 15, 2016 | IBRD-80640 | Int Charges | 1,156,634.10 |
Dec 29, 2016 | IBRD-80640 | Loan Disb | 2,814,240.20 |
Feb 22, 2016 | IBRD-80640 | Loan Disb | 4,725,134.00 |
Mar 18, 2016 | IBRD-80640 | Loan Disb | 10,352,603.00 |
Apr 22, 2016 | IBRD-80640 | Loan Disb | 3,077,052.20 |
Apr 15, 2016 | IBRD-80640 | Int Charges | 902.09 |
Apr 15, 2016 | IBRD-80640 | Int Charges | 633,254.06 |
Oct 23, 2015 | IBRD-80640 | Loan Disb | 1,822,712.10 |
Oct 13, 2015 | IBRD-80640 | Loan Disb | 17,273,918.00 |
Dec 4, 2015 | IBRD-80640 | Loan Disb | 1,379,532.50 |
Dec 17, 2015 | IBRD-80640 | Loan Disb | 3,913,049.00 |
Oct 30, 2015 | IBRD-80640 | Loan Disb | 1,642,264.40 |
Jan 25, 2016 | IBRD-80640 | Loan Disb | 2,066,858.90 |
Oct 15, 2015 | IBRD-80640 | Int Charges | 427,724.50 |
Nov 16, 2015 | IBRD-80640 | Loan Disb | 2,306,922.00 |
Apr 15, 2015 | IBRD-80640 | Int Charges | 365,927.00 |
Jun 17, 2014 | IBRD-80640 | Loan Disb | 17,435,584.00 |
Jun 27, 2014 | IBRD-80640 | Loan Disb | 1,730,758.90 |
Apr 15, 2014 | IBRD-80640 | Int Charges | 2,724.66 |
Apr 15, 2014 | IBRD-80640 | Int Charges | 231,961.88 |
Jan 3, 2014 | IBRD-80640 | Loan Disb | 1,095,308.10 |
Dec 6, 2013 | IBRD-80640 | Loan Disb | 1,058,722.60 |
Jan 17, 2014 | IBRD-80640 | Loan Disb | 2,075,953.40 |
Dec 23, 2013 | IBRD-80640 | Loan Disb | 640,799.25 |
Jan 3, 2014 | IBRD-80640 | Loan Disb | 1,227,848.10 |
Nov 15, 2013 | IBRD-80640 | Loan Disb | 1,167,391.60 |
Sep 18, 2013 | IBRD-80640 | Loan Disb | 2,400,000.00 |
Dec 17, 2013 | IBRD-80640 | Loan Disb | 15,040,777.00 |
Dec 17, 2013 | IBRD-80640 | Loan Disb | 174,055.90 |
May 17, 2011 | IBRD-80640 | Loan Commitment | 200,000,000.00 |
Apr 15, 2024 | IBRD-80640 | Int Charges | 51,639.38 |
Apr 15, 2024 | IBRD-80640 | Int Charges | 4,774,772.00 |
Apr 15, 2024 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Oct 15, 2023 | IBRD-80640 | Int Charges | 4,524,036.00 |
Oct 15, 2023 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Oct 15, 2023 | IBRD-80640 | Int Charges | 80,827.27 |
Apr 15, 2023 | IBRD-80640 | Int Charges | 160,981.62 |
Apr 15, 2023 | IBRD-80640 | Int Charges | 3,783,091.50 |
Apr 15, 2023 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Oct 15, 2022 | IBRD-80640 | Int Charges | 2,165,580.50 |
Oct 15, 2022 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Apr 15, 2022 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Apr 15, 2022 | IBRD-80640 | Int Charges | 727,380.20 |
Oct 15, 2021 | IBRD-80640 | Int Charges | 801,255.30 |
Oct 15, 2021 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Apr 15, 2021 | IBRD-80640 | Int Charges | 817,336.75 |
Apr 15, 2021 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Oct 15, 2020 | IBRD-80640 | Int Charges | 1,702,534.40 |
Oct 15, 2020 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Apr 15, 2020 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Apr 15, 2020 | IBRD-80640 | Int Charges | 2,425,405.80 |
Oct 15, 2019 | IBRD-80640 | Int Charges | 3,097,055.50 |
Oct 15, 2019 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Apr 15, 2019 | IBRD-80640 | Int Charges | 3,151,848.80 |
Apr 15, 2019 | IBRD-80640 | Loan Repay | 4,260,000.00 |
Oct 15, 2018 | IBRD-80640 | Loan Repay | 3,066,073.50 |
Oct 15, 2018 | IBRD-80640 | Int Charges | 3,066,073.50 |
Oct 15, 2018 | IBRD-80640 | Loan Repay | 1,193,926.50 |
Apr 15, 2018 | IBRD-80640 | Int Charges | 10,166.67 |
Apr 15, 2018 | IBRD-80640 | Int Charges | 2,167,168.00 |
Apr 15, 2018 | IBRD-80640 | Loan Repay | 2,082,665.20 |
Apr 15, 2018 | IBRD-80640 | Loan Repay | 2,177,334.80 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2017-03-31 |
Monitoring and Evaluation | Satisfactory | 2017-03-31 |
Overall Implementation Progress (IP) | Satisfactory | 2017-03-31 |
Project Management | Satisfactory | 2017-03-31 |
Procurement | Satisfactory | 2017-03-31 |
Financial Management | Satisfactory | 2017-03-31 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 09-28-2017 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Highly Satisfactory |
INDICATOR | ICR REVIEW: 03-20-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Negligible | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Highly Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Volume of EE sub-loans | Value | 0.00 | 200000000.00 | 200000000.00 |
Date | December 15, 2010 | March 16, 2017 | March 31, 2017 | |
Comment |
Number of participating banks (PBs) | Value | 0.00 | 1.00 | 2.00 |
Date | December 15, 2010 | February 16, 2017 | March 31, 2017 | |
Comment |
Extent of energy savings (toe) | Value | 0.00 | 602200.00 | 600000.00 |
Date | December 15, 2010 | March 16, 2017 | March 31, 2017 | |
Comment |
Projected lifetime fuel savings | Value | 0.00 | 252114432.60 | 251208000.00 |
Date | December 15, 2010 | March 16, 2017 | March 31, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
The Borrower's loan committments | Value | 0.00 | 100.00 | 100.00 |
Date | December 15, 2010 | March 16, 2017 | March 31, 2017 | |
Comment |
Extent of energy savings, gas (tcm) | Value | 0.00 | 179000.00 | 160000.00 |
Date | December 15, 2010 | March 16, 2017 | March 31, 2017 | |
Comment |
The Borrower's loan disbursements | Value | 0.00 | 100.00 | 100.00 |
Date | December 15, 2010 | March 16, 2017 | March 31, 2017 | |
Comment |
Extent of energy savings, electricity (GWh) | Value | 0.00 | 174.00 | 120.00 |
Date | December 15, 2010 | March 16, 2017 | March 31, 2017 | |
Comment |
Number of Municipal Energy Efficiency Subproject | Value | 0.00 | 5.00 | 5.00 |
Date | December 15, 2010 | March 16, 2017 | March 31, 2017 | |
Comment |
Number of ESCO subprojects | Value | 0.00 | 4.00 | 2.00 |
Date | December 15, 2010 | March 16, 2017 | March 31, 2017 | |
Comment |