Financier | Commitments |
---|---|
Borrower/Recipient | 9.40 |
International Bank for Reconstruction and Development | 145.60 |
P096745
Closed
Toru Konishi
Economic Affairs Division
April 1, 2010
(as of board presentation)
July 1, 2010
January 21, 2011
US$ 155.00 million
Punjab Irrigation and Power Department (PID), Government of Punjab
2011
US$ 145.60 million
A
Not Applicable
June 30, 2017
BANK APPROVED
February 1, 2022
Financier | Commitments |
---|---|
Borrower/Recipient | 9.40 |
International Bank for Reconstruction and Development | 145.60 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 145.60 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 145.60 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 155.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 15, 2021 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Sep 15, 2020 | IBRD-79000 | Int Charges | 742,240.00 |
Sep 15, 2020 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Mar 15, 2021 | IBRD-79000 | Int Charges | 481,816.22 |
Mar 15, 2021 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Mar 15, 2020 | IBRD-79000 | Int Charges | 1,442,276.80 |
Mar 15, 2020 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Sep 15, 2019 | IBRD-79000 | Int Charges | 1,863,762.10 |
Sep 15, 2019 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Mar 15, 2019 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Mar 15, 2019 | IBRD-79000 | Int Charges | 1,848,425.00 |
Sep 15, 2015 | IBRD-79000 | Int Charges | 622,538.90 |
Aug 20, 2015 | IBRD-79000 | Loan Disb | 3,500,000.00 |
Jun 25, 2015 | IBRD-79000 | Loan Disb | 2,473,069.20 |
Jun 3, 2015 | IBRD-79000 | Loan Disb | 6,000,000.00 |
Jul 28, 2015 | IBRD-79000 | Loan Disb | 338,104.12 |
Sep 15, 2014 | IBRD-79000 | Loan Disb | 463,410.66 |
Sep 15, 2014 | IBRD-79000 | Int Charges | 463,410.66 |
Sep 17, 2014 | IBRD-79000 | Loan Disb | 399,032.30 |
Mar 15, 2015 | IBRD-79000 | Loan Disb | 537,452.10 |
Mar 15, 2015 | IBRD-79000 | Int Charges | 537,452.10 |
Sep 10, 2014 | IBRD-79000 | Loan Disb | 273,842.00 |
Feb 23, 2015 | IBRD-79000 | Loan Disb | 1,479,248.00 |
Aug 19, 2014 | IBRD-79000 | Loan Disb | 1,668,552.00 |
Sep 12, 2014 | IBRD-79000 | Loan Disb | 8,000,000.00 |
Jun 23, 2014 | IBRD-79000 | Loan Disb | 2,749,863.00 |
Apr 11, 2014 | IBRD-79000 | Loan Disb | 1,488,410.00 |
Mar 18, 2014 | IBRD-79000 | Loan Disb | 2,958,797.00 |
Apr 22, 2014 | IBRD-79000 | Loan Disb | 13,000,000.00 |
Mar 15, 2014 | IBRD-79000 | Loan Disb | 366,492.38 |
Mar 15, 2014 | IBRD-79000 | Int Charges | 366,492.38 |
Nov 19, 2013 | IBRD-79000 | Loan Disb | 8,196,000.00 |
Sep 15, 2013 | IBRD-79000 | Int Charges | 310,614.40 |
Sep 15, 2013 | IBRD-79000 | Loan Disb | 310,614.40 |
Jul 16, 2013 | IBRD-79000 | Loan Disb | 8,000,000.00 |
Sep 15, 2018 | IBRD-79000 | Int Charges | 1,713,331.00 |
Sep 15, 2018 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Sep 15, 2018 | IBRD-79000 | Int Charges | 81,880.96 |
Jan 22, 2018 | IBRD-79000 | Loan Disb | -2,037,482.50 |
Jan 22, 2018 | IBRD-79000 | Loan Cancel | 3,087,590.50 |
Mar 15, 2018 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Mar 15, 2018 | IBRD-79000 | Int Charges | 1,344,876.50 |
Sep 15, 2017 | IBRD-79000 | Int Charges | 1,382,085.10 |
Sep 15, 2017 | IBRD-79000 | Loan Repay | 4,499,388.50 |
May 1, 2017 | IBRD-79000 | Loan Cancel | 10,000,000.00 |
Jun 26, 2017 | IBRD-79000 | Loan Disb | 93,548.11 |
Jun 26, 2017 | IBRD-79000 | Loan Disb | 148,263.62 |
Jul 7, 2017 | IBRD-79000 | Loan Disb | 154,115.56 |
Jun 19, 2017 | IBRD-79000 | Loan Disb | 108,447.93 |
Mar 21, 2017 | IBRD-79000 | Loan Disb | 304,993.70 |
May 2, 2017 | IBRD-79000 | Loan Disb | 102,504.52 |
Jun 13, 2017 | IBRD-79000 | Loan Disb | 2,500,000.00 |
May 31, 2017 | IBRD-79000 | Loan Disb | 1,700,000.00 |
Jun 30, 2017 | IBRD-79000 | Loan Disb | 10,880.00 |
May 26, 2017 | IBRD-79000 | Loan Disb | -1,699,980.00 |
May 23, 2017 | IBRD-79000 | Loan Disb | 74,841.75 |
May 3, 2017 | IBRD-79000 | Loan Disb | 1,700,000.00 |
Nov 10, 2016 | IBRD-79000 | Loan Disb | 15,120.00 |
Mar 15, 2017 | IBRD-79000 | Loan Disb | 163,344.40 |
Mar 15, 2017 | IBRD-79000 | Int Charges | 2,836.08 |
Mar 15, 2017 | IBRD-79000 | Int Charges | 1,251,503.10 |
Mar 15, 2017 | IBRD-79000 | Loan Repay | 4,307,959.00 |
Nov 16, 2016 | IBRD-79000 | Loan Disb | 130,952.92 |
Nov 10, 2016 | IBRD-79000 | Loan Disb | 18,901.83 |
Oct 5, 2016 | IBRD-79000 | Loan Disb | 3,500,000.00 |
May 18, 2016 | IBRD-79000 | Loan Disb | 3,500,000.00 |
May 18, 2016 | IBRD-79000 | Loan Disb | 1,168,346.80 |
Oct 20, 2016 | IBRD-79000 | Loan Disb | 610,529.75 |
Nov 14, 2016 | IBRD-79000 | Loan Disb | 146,426.00 |
Jul 15, 2016 | IBRD-79000 | Loan Disb | 904,266.75 |
Sep 15, 2016 | IBRD-79000 | Int Charges | 2,056.37 |
Jul 22, 2016 | IBRD-79000 | Loan Disb | 98,922.74 |
Sep 15, 2016 | IBRD-79000 | Int Charges | 1,036,290.40 |
Sep 15, 2016 | IBRD-79000 | Loan Repay | 4,121,335.00 |
Mar 15, 2016 | IBRD-79000 | Int Charges | 747,127.80 |
Feb 29, 2016 | IBRD-79000 | Loan Disb | 825,807.50 |
Feb 29, 2016 | IBRD-79000 | Loan Disb | 3,000,000.00 |
Dec 10, 2015 | IBRD-79000 | Loan Disb | 1,500,000.00 |
Sep 15, 2015 | IBRD-79000 | Loan Disb | 622,538.90 |
Jul 1, 2010 | IBRD-79000 | Loan Commitment | 145,600,000.00 |
Mar 15, 2024 | IBRD-79000 | Int Charges | 2,198,332.50 |
Mar 15, 2024 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Sep 15, 2023 | IBRD-79000 | Int Charges | 2,102,372.20 |
Sep 15, 2023 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Mar 15, 2023 | IBRD-79000 | Int Charges | 1,738,742.20 |
Mar 15, 2023 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Sep 15, 2022 | IBRD-79000 | Int Charges | 766,478.25 |
Sep 15, 2022 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Mar 15, 2022 | IBRD-79000 | Int Charges | 380,967.12 |
Mar 15, 2022 | IBRD-79000 | Loan Repay | 4,424,011.50 |
Sep 15, 2021 | IBRD-79000 | Int Charges | 425,748.94 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2017-06-16 |
Counterpart Funding | Satisfactory | 2017-06-16 |
Monitoring and Evaluation | Satisfactory | 2017-06-16 |
Overall Implementation Progress (IP) | Satisfactory | 2017-06-16 |
Procurement | Satisfactory | 2017-06-16 |
Project Management | Satisfactory | 2017-06-16 |
Financial Management | Satisfactory | 2017-06-16 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-31-2018 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Moderately Satisfactory |
Government Performance | Substantial |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 04-29-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Modest | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Barrage able to supply reliable and uninterrupted water supply to over 2.1 million acres of farmland benefitting about 600,000 farm families for irrigation and domestic water users | Value | Water supply to Thal Canal unreliable;DPR value 0 | Water supply to the Thal canal that serves 2.1 mil | Less interruption in water supplies to the Thai c |
Date | March 22, 2011 | May 31, 2017 | June 30, 2017 | |
Comment |
IPD’s increased functional capacity to manage water resources and irrigation system in the Province using modern tools and equipment | Value | (current level of water management) Water accounti | The PMIU is now doing improved water accounting ba | Better water allocation and accounting over 50 per |
Date | March 22, 2011 | May 31, 2017 | June 30, 2017 | |
Comment |
Barrage able to pass floods safely | Value | Barrage and its associated structures vulnerable t | After rehabilitation and modernization the barrage | Barrage is better equipped to handle floods safely |
Date | March 22, 2011 | May 31, 2017 | June 30, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component B: Management Information: - water accounting system; Modern equipment in monitoring and management of hydraulic infrastructure | Value | -- Modern systems and equipment not in place for: | --Equipment procured and installed --SCADA syste | System application |
Date | March 22, 2012 | May 31, 2017 | June 30, 2017 | |
Comment |
Timely Progress of Component A | Value | No Rehabilitation | All physical works completed and new systems opera | Rehabilitation and modernization work fully comple |
Date | March 22, 2011 | May 31, 2017 | June 30, 2017 | |
Comment |
No reduction of water supplies to the Thal canal. | Value | Unreliable and lower than the design flows in Thal | Reliable water supply as a result of improved oper | Reliable water supply as a result of improved oper |
Date | March 22, 2011 | May 31, 2017 | June 30, 2017 | |
Comment |
Retrogression Downstream of the Barrage is stopped | Value | There is heavy scouring/ retrogression immediately | Bathymetric survey carried out after completion of | Retrogression is checked |
Date | March 22, 2011 | May 31, 2017 | June 30, 2017 | |
Comment |
Operation of gates is smooth | Value | All gates have manual control; some gates malfunct | All gates renovated and provided with remote contr | All gates function efficiently |
Date | March 22, 2011 | May 31, 2017 | June 30, 2017 | |
Comment |
Component C: Baseline of monitoring is prepared and supervision of EMP and SDAP is carried out | Value | 2009: No baseline data available and no environmen | Baseline, mid-term and end-of-project surveys comp | Project impact assessment |
Date | March 22, 2011 | May 31, 2017 | June 30, 2017 | |
Comment |
Component D: Project implementation is coherent and contracts are awarded; No interruption to river and canal supplies. | Value | 2009: No project activity underway | All contracts for works, goods and services substa | All project activities satisfactorily completed. N |
Date | March 22, 2011 | May 31, 2017 | June 30, 2017 | |
Comment |