Financier | Commitments |
---|---|
FRANCE: French Agency for Development | 7.60 |
Special Financing | 10.00 |
P096777
Closed
Sabine Beddies
N/A
February 14, 2006
(as of board presentation)
December 19, 2006
February 27, 2007
US$ 17.60 million
N/A
2007
US$ 17.60 million
B
Not Applicable
September 30, 2011
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
FRANCE: French Agency for Development | 7.60 |
Special Financing | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 17.60 |
Total Project Cost** | 17.60 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2011-12-19 |
Project Management | Satisfactory | 2011-12-19 |
Financial Management | Satisfactory | 2011-12-19 |
Monitoring and Evaluation | Satisfactory | 2011-12-19 |
Procurement | Satisfactory | 2011-12-19 |
Counterpart Funding | Satisfactory | 2011-12-19 |
Overall Implementation Progress (IP) | Satisfactory | 2011-12-19 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-30-2012 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 10-03-2012 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |