Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Borrower/Recipient | 397.41 |
P098078
Closed
Ximing Zhang
People's Republic of China
January 5, 2006
(as of board presentation)
July 6, 2010
January 26, 2011
US$ 597.41 million
Ministry of Water Resources
2011
US$ 200.00 million
A
Not Applicable
December 31, 2016
BANK APPROVED
April 22, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Borrower/Recipient | 397.41 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 200.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 597.41 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 15, 2024 | IBRD-79380 | Int Charges | 4,303,927.50 |
May 15, 2024 | IBRD-79380 | Loan Repay | 5,880,000.00 |
Nov 15, 2023 | IBRD-79380 | Int Charges | 88,114.07 |
Nov 15, 2023 | IBRD-79380 | Int Charges | 4,242,542.50 |
Nov 15, 2023 | IBRD-79380 | Loan Repay | 5,880,000.00 |
May 15, 2023 | IBRD-79380 | Int Charges | 214,531.19 |
May 15, 2023 | IBRD-79380 | Int Charges | 3,654,496.80 |
May 15, 2023 | IBRD-79380 | Loan Repay | 5,880,000.00 |
Nov 15, 2022 | IBRD-79380 | Int Charges | 2,280,129.00 |
Nov 15, 2022 | IBRD-79380 | Loan Repay | 5,880,000.00 |
May 15, 2022 | IBRD-79380 | Loan Repay | 5,880,000.00 |
May 15, 2022 | IBRD-79380 | Int Charges | 606,945.30 |
Nov 15, 2021 | IBRD-79380 | Int Charges | 606,169.60 |
Nov 15, 2021 | IBRD-79380 | Loan Repay | 5,880,000.00 |
Nov 15, 2020 | IBRD-79380 | Loan Repay | 5,880,000.00 |
May 15, 2021 | IBRD-79380 | Int Charges | 643,304.20 |
May 15, 2021 | IBRD-79380 | Loan Repay | 5,880,000.00 |
Nov 15, 2020 | IBRD-79380 | Int Charges | 1,055,350.40 |
May 15, 2020 | IBRD-79380 | Int Charges | 2,221,854.00 |
May 15, 2020 | IBRD-79380 | Loan Repay | 5,880,000.00 |
Nov 15, 2019 | IBRD-79380 | Int Charges | 2,972,937.00 |
Nov 15, 2019 | IBRD-79380 | Loan Repay | 5,880,000.00 |
May 15, 2019 | IBRD-79380 | Loan Repay | 5,880,000.00 |
May 15, 2019 | IBRD-79380 | Int Charges | 3,269,574.00 |
Nov 15, 2018 | IBRD-79380 | Int Charges | 3,056,444.50 |
Nov 15, 2018 | IBRD-79380 | Loan Repay | 5,880,000.00 |
May 15, 2018 | IBRD-79380 | Int Charges | 2,091,555.50 |
Nov 15, 2017 | IBRD-79380 | Int Charges | 5,190.67 |
Nov 15, 2017 | IBRD-79380 | Int Charges | 1,932,000.00 |
Apr 18, 2017 | IBRD-79380 | Loan Disb | 369,395.78 |
Aug 15, 2016 | IBRD-79380 | Loan Disb | 4,489,624.50 |
May 15, 2017 | IBRD-79380 | Int Charges | 2,280.08 |
May 15, 2017 | IBRD-79380 | Int Charges | 1,647,394.80 |
Apr 10, 2017 | IBRD-79380 | Loan Disb | 2,912,025.20 |
Nov 2, 2016 | IBRD-79380 | Loan Disb | 4,932,843.00 |
Jul 27, 2016 | IBRD-79380 | Loan Disb | 175,633.92 |
Dec 2, 2016 | IBRD-79380 | Loan Disb | 3,287,875.20 |
Nov 18, 2016 | IBRD-79380 | Loan Disb | 1,835,274.90 |
Aug 5, 2014 | IBRD-79380 | Loan Disb | 5,273,936.00 |
Mar 18, 2015 | IBRD-79380 | Loan Disb | 146,145.27 |
Aug 20, 2014 | IBRD-79380 | Loan Disb | 6,552,499.50 |
Mar 19, 2014 | IBRD-79380 | Loan Disb | 2,067,929.50 |
Apr 24, 2014 | IBRD-79380 | Loan Disb | 956,235.60 |
May 15, 2014 | IBRD-79380 | Int Charges | 4,470.35 |
May 15, 2014 | IBRD-79380 | Int Charges | 368,909.56 |
Nov 6, 2013 | IBRD-79380 | Loan Disb | 1,004,847.75 |
Sep 25, 2013 | IBRD-79380 | Loan Disb | 1,384,670.60 |
Nov 15, 2013 | IBRD-79380 | Int Charges | 7,915.62 |
Nov 15, 2013 | IBRD-79380 | Int Charges | 314,062.44 |
Nov 18, 2013 | IBRD-79380 | Loan Disb | 6,188,974.50 |
Dec 5, 2013 | IBRD-79380 | Loan Disb | 1,360,001.50 |
Feb 19, 2014 | IBRD-79380 | Loan Disb | 7,157,545.50 |
Jan 15, 2014 | IBRD-79380 | Loan Disb | 816,541.30 |
Dec 19, 2013 | IBRD-79380 | Loan Disb | 817,582.30 |
Sep 3, 2013 | IBRD-79380 | Loan Disb | 935,715.10 |
Oct 17, 2013 | IBRD-79380 | Loan Disb | 5,295,618.50 |
Aug 16, 2013 | IBRD-79380 | Loan Disb | 5,795,327.00 |
Mar 5, 2014 | IBRD-79380 | Loan Disb | 860,549.75 |
Dec 17, 2013 | IBRD-79380 | Loan Disb | 1,080,845.80 |
Dec 19, 2014 | IBRD-79380 | Loan Disb | 3,763,667.80 |
Aug 7, 2013 | IBRD-79380 | Loan Disb | 787,203.90 |
Aug 5, 2013 | IBRD-79380 | Loan Disb | 4,807,309.50 |
Jul 17, 2013 | IBRD-79380 | Loan Disb | 1,154,902.90 |
Nov 15, 2014 | IBRD-79380 | Int Charges | 2,414.18 |
Nov 15, 2014 | IBRD-79380 | Int Charges | 394,148.25 |
Nov 19, 2014 | IBRD-79380 | Loan Disb | 634,923.90 |
Jul 6, 2010 | IBRD-79380 | Loan Commitment | 200,000,000.00 |
May 15, 2024 | IBRD-79380 | Int Charges | 27,841.75 |
Nov 15, 2016 | IBRD-79380 | Int Charges | 1,190,879.10 |
May 26, 2016 | IBRD-79380 | Loan Disb | 8,106,855.00 |
May 15, 2016 | IBRD-79380 | Int Charges | 812,302.75 |
May 15, 2016 | IBRD-79380 | Int Charges | 1,465.34 |
Dec 7, 2016 | IBRD-79380 | Loan Disb | 1,452,845.40 |
Mar 9, 2016 | IBRD-79380 | Loan Disb | 1,399,041.10 |
Jul 18, 2016 | IBRD-79380 | Loan Disb | 1,094,925.60 |
Jan 11, 2016 | IBRD-79380 | Loan Disb | 945,930.44 |
Oct 8, 2015 | IBRD-79380 | Loan Disb | 816,267.30 |
Nov 12, 2015 | IBRD-79380 | Loan Disb | 6,482,068.50 |
Jan 5, 2016 | IBRD-79380 | Loan Disb | -194,792.66 |
Nov 15, 2015 | IBRD-79380 | Int Charges | 148.34 |
Nov 15, 2015 | IBRD-79380 | Int Charges | 582,462.44 |
Dec 28, 2015 | IBRD-79380 | Loan Disb | 4,592,999.00 |
Sep 11, 2015 | IBRD-79380 | Loan Disb | 805,193.20 |
Oct 21, 2015 | IBRD-79380 | Loan Disb | 832,920.20 |
Jul 14, 2015 | IBRD-79380 | Loan Disb | 4,342,325.00 |
Jun 4, 2015 | IBRD-79380 | Loan Disb | 947,355.00 |
May 15, 2015 | IBRD-79380 | Int Charges | 452,152.66 |
Jun 1, 2015 | IBRD-79380 | Loan Disb | 4,638,131.00 |
Feb 5, 2015 | IBRD-79380 | Loan Disb | 4,680,857.50 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2016-12-18 |
Procurement | Satisfactory | 2016-12-18 |
Progress towards achievement of PDO | Satisfactory | 2016-12-18 |
Financial Management | Satisfactory | 2016-12-18 |
Monitoring and Evaluation | Satisfactory | 2016-12-18 |
Overall Safeguards Rating | Highly Satisfactory | 2016-12-18 |
Counterpart Funding | Satisfactory | 2016-12-18 |
Overall Implementation Progress (IP) | Satisfactory | 2016-12-18 |
Overall Safeguards Rating | Highly Satisfactory | 2016-12-18 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-26-2017 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 09-07-2017 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Modest | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PO1: Targeted rural and urban areas protected from flooding | Value | 0 KM2 | 9671.7KM2 | 9,576.2 KM2 |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
PO2: Targeted number of people protected from flooding | Value | 0 | 7.36 million | 6.64 million |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
PO3: Targeted economic losses in urban and rural areas reduced from flooding | Value | 0.0 | 796.2 million Yuan | RMB 699.5 million Yuan |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
PO4: Targeted increase of per capita agricultural incomes of farmers from flood protection | Value | 0.00 | RMB 422 Yuan/Year | RMB 233 Yuan/Year |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
PO5: Targeted increase of navigation benefits from river improvements | Value | 0.0 | RMB 184.2 million Yuan | RMB 118.4 million Yuan |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
IO1: Targeted length of dike strengthening | Value | 0.0 | 440.4 KM | 417.4 KM |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO2: Targeted length of river improvements | Value | 0.0 | 989.3 KM | 980.5 KM |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO3: Targeted number of structures constructed including pumping stations, dike structures and flood control gates and bridges | Value | 0 | 882 | 806 |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO4: Targeted number of O&M plans approved and implemented | Value | 0 | 131 | 146 |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO5: Number of functioning FDIAs established as per requirements | Value | 0 | 36 | 36 |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO6: Targeted number of major actions taken as per the EMPs implemented with budget allocated. | Value | 0 | 110 | 59 |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO7: Percent of targeted investment completed on flood disaster assessment and decision support system | Value | 0 | 99% | 100% |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO8: Percent of targeted investment completed on hydraulic model | Value | 0 | 111 % | 100% |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO9: Accuracy of targeted technical criteria reached by the flood disaster assessment and decision support system | Value | Non achieved | achieved | 1. data collection rate 90%;2. Error between comp |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO10: Targeted number of government officials who understand and help disseminate the project innovations | Value | 0 | 381 | 275 |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO11: Targeted number of project-affected people whose incomes and lives maintained or improved | Value | 0 | 82359 | 57,173 |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO12:Targeted number of resettled people whose incomes and lives maintained or improved | Value | 0 | 4968 | 7,044 |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |
IO13: Targeted number of contracts which strictly follow the Bank procurement and financial management guidelines | Value | 0 | 335 | 311 |
Date | June 15, 2009 | September 30, 2016 | December 31, 2016 | |
Comment |