Skip to Main Navigation

Sustainable Energy Financing Program

Abstract*

The Sustainable Energy Financing Project aims to significantly increase the adoption and use of renewable energy technologies in participating Pacific Island states through a package of incentives to encourage local financial institutions to participate in sustainable energy finance in support of equipment purchase. In addition, the global environment objective is to contribute to mitigating climate change through the reduction of greenhouse gas emissions...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Program is (i) to significantly increase the adoption and use of renewable energy technologies and the more efficient use of energy through a package of incentives to encourage local financial institutions to participate in sustainable energy finance in the Participating Pacific Island States; and (ii) to support knowledge sharing and capacity building on renewable energy and energy efficiency technologies in the Participating Pacific Island States.

Key Details

Project Details

  • P098423

  • Closed

  • Mitsunori Motohashi , Kamleshwar Prasad Khelawan

  • ANZ Banking Group Limited,Republic of Fiji

  • Pacific Islands

  • March 21, 2006

  • (as of board presentation)

    June 12, 2007

  • July 9, 2007

  • US$ 19.97 million

  • Department of Energy,Department of Energy

  • East Asia and Pacific

  • 2007

  • US$ 8.45 million

  • C

  • N/A

  • May 15, 2022

  • BANK APPROVED

  • July 12, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 0.50
Global Environment Facility (GEF) 8.45
Borrowing Country's Fin. Intermediary/ies 10.20
Sub-borrower(s) 0.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.45
Total Project Cost** 19.97

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Summary Global Objective Rating Moderately Satisfactory 2021-12-23
Project Management Satisfactory 2021-12-23
Monitoring and Evaluation Satisfactory 2021-12-23
Procurement Moderately Satisfactory 2021-12-23
Overall Implementation Progress (IP) Moderately Unsatisfactory 2021-12-23
Overall Safeguards Rating Satisfactory 2021-12-23
Counterpart Funding Satisfactory 2021-12-23
Financial Management Satisfactory 2021-12-23
Overall Safeguards Rating Satisfactory 2021-12-23

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 07-11-2023
Outcomes
Risk to Development OutcomeSubstantial
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-21-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased lending from local financial institutions for RE and EE equipment in the Recipient’s territoryValue0.0041.000.00
    DateJuly 12, 2007December 31, 2022
    Comment
  • Additional number of kW of RE and EE technology financed through approved participating financing institutionsValue0.008.800.00
    DateJuly 12, 2007December 31, 2022
    Comment
  • Carbon Dioxide emissions avoided due to financing through projectValue0.0013.000.00
    DateJuly 12, 2007December 31, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • RSF guarantees called (Component 1)Value0.002.000.00
    DateJuly 12, 2007December 31, 2022
    Comment
  • MSEs and Community organizations participating in TA or training activities (Component 2)Value0.0012.000.00
    DateJuly 12, 2007December 31, 2022
    Comment
  • Grievances registered related to delivery of project benefits that are addressedValue0.0075.0075.00
    DateJuly 12, 2007December 31, 2022
    Comment
  • Number of loans approved for (i) MSEs, (ii) community organizations and (iii) individuals (Component 1)Value0.00135.000.00
    DateJuly 12, 2007December 31, 2022
    Comment
  • Number of articles and broadcasts organized by the Recipient on the benefits of renewable energy and energy efficiency (Component 2)Value0.0051.000.00
    DateJuly 12, 2007December 31, 2022
    Comment
  • Number of showcases and community presentations organized by the Recipient on the benefits of renewable energy and energy efficiency (Component 2)Value0.00130.000.00
    DateJuly 12, 2007December 31, 2022
    Comment